CONSTRUCTION UPDATE REPORT
Lake
Effective: 05/16/13 3:22 PM
| LOCATION AND DESCRIPTION |
MUNICIPALITY START DATE EST. STOP DATE COST (millions) |
COMMENTS |
|
Arlington Heights Road Bridge replacement, landscaping |
Vernon Township, Buffalo Grove 3/2013 9/2013 $0.43 |
IMPACT ON TRAVEL:
63713 Project consists of the removal of the existing bridge deck beams and replacing them with precast prestressed concrete deck beams (17" depth), sidewalk removal and replacement, HMA resurfacing, curb and gutter removal and replacement, pavement markings, landscaping and all other incidental item to complete the work on Arlington Heights Road at Southbound Bridge over Buffalo Creek. |
|
Atkinson Road/IL 137 Extending Atkinson Road and widening IL 137 |
Grayslake 10/2012 11/2013 $3.759 |
IMPACT ON TRAVEL:
63640 Project consists of the extension of Atkinson Road from IL Route 120 south to IL Route 137 and the addition of a lane on IL Route 137 from the new Atkinson Road intersection west to IL Route 83 (Ivanhoe Road) in the Village
of Grayslake |
|
Becah Road Resurfacing, widening, and an 8 foot recreation path |
Beach Park 8/2012 6/2013 $2.129 |
IMPACT ON TRAVEL:
63683 Project consists of road reconstruction, new roadway profile, widening and, resurfacing, drainage system, an 8 foot recreation path and all other incidental items to complete the work on FAU Route 1210 (Becah Road) between Sheridan Road and Lewis Avenue in the Village of Beach Park |
|
Bridge Carrying US 41 over Deerpath Rd. Bridge joint repairs. |
Lake Forest 6/2013 8/2013 $0.188 |
IMPACT ON TRAVEL:
60T65 Bridge Joint and approach repairs for the structure carrying US 41 (Skokie Highway) over Deerpath Road located in Lake Forest. |
|
Cedar Lake @ Monaville Road Storm sewer, curb and gutter, intersection conversion. |
Lake Villa 5/2013 8/2013 $1.534 |
IMPACT ON TRAVEL:
63682 This project consists of HMA pavement on aggregate subgrade, intersection conversion from stop controlled to roundabout, storm sewer removal and replacement, curb and gutter replacement located on Cedar Lake Road at Monaville Road in Lake Villa. |
|
Deerfield Road over East Skokie Ditch Bridge replacement |
Highland Park 4/2012 6/2013 $1.231 |
IMPACT ON TRAVEL:
62102 Removal and replacement of the superstructure of the bridge carrying Deerfield Road over East Skokie Ditch located in Highland Park. |
|
Duffy Lane Patching, resurfacing, and landscape restoration. |
Bannockburn 5/2013 7/2013 $0.398 |
IMPACT ON TRAVEL:
63751 This project consists of HMA pavement removal, HMA patching, storm sewer removal and replacement, HMA binder, HMA surface course and landscape restoration located on Duffy Lane from West Corporate Limits to Wilmot Road in the Village of Bannockburn. |
|
Gilmer Road Construction of a bike path underpass |
Fremont Township 5/2011 3/2013 $1.752 |
IMPACT ON TRAVEL:
63422 Construction of a bike path underpass, excavation, drainage structures, HMA pavement, pavement marking, lighting, landscaping and all other incidental items to complete the work on Fort Hill Trail and Glimer Road approximately 1.2 miles north of the IL Rte. 176 and Gilmer Road intersection. |
|
Grand Avenue and US 45 Pedestrian underpass |
Lake Villa Township 6/2012 6/2013 $2.654 |
IMPACT ON TRAVEL:
63665 This project consists of the construction of a pedestrian underpass under Grand Avenue to connect the existing Millennium Trail. Project is located 0.80 miles north west of the Grand Avenue and U.S. Highway 45 intersection in Lake Villa Township, Lake County. |
|
Highland Road Resurfacing, patching, and storm sewers. |
Grayslake 8/2012 5/2013 $1.236 |
IMPACT ON TRAVEL:
63712 This project consists of HMA patching and resurfacing, combination curb and gutter, storm sewer installation and sidewalk construction located on Highland Road from Lake Street to IL Route 83 in the Village of Grayslake. |
|
I-94 and IL 173 Reconstruction and widening |
Wadsworth, Old Mill Creek 11/2012 11/2013 $29.129 |
IMPACT ON TRAVEL:
60L77 2.61 miles of reconstruction and widening of I-94 from Wisconsin state line to IL 173, also reconstruction and widening of IL 173 and complete removal and reconstruction of the structure carrying IL 173 over I-94 in Wadsworth and Old Mill Creek. |
|
IL 120 Widening, resurfacing, and channilization |
Gages Lake, Waukegan 5/2013 8/2013 $0.496 |
IMPACT ON TRAVEL:
60R59 Widening, HMA surface, HMA shoulders, ditch grading, sign replacement and other work for channelization on IL 120 at Almond Rd. and River Rd. in Gages Lake and Waukegan. |
|
IL 131 @ Yorkhouse Road Intersection improvement |
Beach Park 9/2012 5/2013 $0.864 |
IMPACT ON TRAVEL:
60P63 Intersection improvemetn on IL 131 at Yorkhouse Road in Beach Park. |
|
IL 176 Replacement of two box culverts |
Wauconda 5/2012 7/2013 $3.739 |
IMPACT ON TRAVEL:
62187 Removal and replacement of two box culverts carrying IL 176 (Slocum Lake Road) over Bangs Lake Drainage Ditch roadway reconstruction and striping along 0.44 mile of IL 176 all located in Wauconda. |
|
IL 21 Temporary Pavement, tree removal |
Gurnee, Waukegan, Libertyville Township, Libertyville 9/2011 6/2013 $2.341 |
IMPACT ON TRAVEL:
60P33 2.05 miles of temporary pavement, tree removal and grading associated with the proposed reconstruction of IL Route 21 in Gurnee, Waukegan, Libertyville Township and Libertyville. |
|
IL 21 (Milwaukee Avenue) Bridge reconstruction, adding lanes and traffic signals |
Gurnee, Waukegan, Libertyville 3/2012 8/2013 $22.967 |
IMPACT ON TRAVEL:
60953 2.20 miles of roadway reconstruction, bridge reconstruction, adding lanes and traffic signal modernization on IL 21 (Milwaukee Avenue) from south of IL Route 120 to south of IL 137 (Buckely Road), in Gurnee, Waukegan and Libertyville. |
|
IL 22 Roadway reconstruction, widening and traffic signals |
Highland Park and Bannockburn 5/2011 5/2013 $11.49 |
IMPACT ON TRAVEL:
60860 2.11 miles of roadway reconstruction, widening, drainage, traffic signal modernization and other work on IL Route 22 from east of I-94 to west of U.S. Route 41 in Highland Park and Bannockburn. OTHER COMMENTS: One lane in each direction with left turn lanes at signalized intersections. |
|
Intersection of Rand Road and Fox Lake Road. Addition of a right turn lane and realignment of a driveway. |
Lakemoor, Volo 6/2013 9/2013 $0.61 |
IMPACT ON TRAVEL:
60T50 Addaition of a right turn lane and realignment of a commercial driveway at athe intersection of Rand Road and Fox Lake Road in Lakemoor and Volo. |
|
Intersections Long Grove Road, Rand Road, White Pines Road 12 foot wide through lanes and left turn lanes. |
Kildeer, Deer Park 10/2012 12/2013 $6.677 |
IMPACT ON TRAVEL:
63649 Reconstruction to provide two 12-foot through lanes and an exclusive left turn lane at the intersections of Long Grove Road, Rand Road and White Pines Road. Project begins south of Long Grove Road to Boschome Drive, located in the Village of Kildeer and the Village of Deer Park. |
|
Lake Street Resurfacing |
Libertyville 8/2012 5/2013 $1.097 |
IMPACT ON TRAVEL:
63697 This project consists of full-depth patching, drainage system, HMA resurfacing and pavement markings located on Lake Street from Butterfield Road to Brainerd Avenue in the Village of Libertyville. |
|
Main Street Sidewalk, storm sewer, and grading work |
Round Lake Park, Round Lake 9/2011 3/2013 $0.235 |
IMPACT ON TRAVEL:
63599 This project includes sidewalk, storm sewer and grading work on Main Street from MacGillis Drive in Round Lake to west of Fairlawn Drive in Round Lake Park. |
|
Old Rand Road Retaining wall, storm sewer modificatons |
Lake Zurich 9/2011 5/2013 $0.256 |
IMPACT ON TRAVEL:
63589 Project consists of the construction of sidewalks, a retaining wall, storm sewer modifications, and all other incidental items to complete the work on Old Rand Road from IL Rte. 22 to Grand Avenue and on Surryse Road from Alpine Family Center to Buesching Road in the Village of Lake Zurich. |
|
Russell Road at off and on ramps at I-94 Reconstruction |
Wadsworth 7/2012 5/2013 $9.883 |
IMPACT ON TRAVEL:
60L76 0.47 mile of reconstruction of Russell Road and the Russell Road on and off ramps at I-94 along with bridge replacement of 2 structures spanning I-94 all located in Wadsworth. |
|
US 14 (Northwest Highway) at Kelsey Road Channelization and traffic signal modernization |
Lake Barrington 5/2012 6/2013 $0.606 |
IMPACT ON TRAVEL:
60K17 Channelization and traffic signal modernization for US Route 14 (Northwest Highway) at Kelsey Road in Lake Barrington. |
|
US 41 (Skokie Highway) Bridge joint repairs. |
Lake Forest 6/2013 8/2013 $0.188 |
IMPACT ON TRAVEL:
60T65 Bridge joint and approach repairs for the structure carrying US 41 (Skokie Highway) ovr Deerpath Road located in Lake Forest. |
|
US 45 Sidewalk, landscape |
Mundelein 9/2012 5/2013 $0.349 |
IMPACT ON TRAVEL:
63725 Project consists of sidewalk installation, grading, landscape restoration and all other incidental items to complete the work on US 45 from Hawthorne Avenue to Hickory Street in the Village of Mundelein |
|
US 45 Sidewalk and tree planting. |
Mundelein 9/2012 5/2013 $0.257 |
IMPACT ON TRAVEL:
63724 Project consists of sidewalk removal and replacement, brick paver sidewalk, planting trees and all other incidental items to complete the work on US 45 from Wellington Avenue to Park Street in the Village of Mundelein. |
|
Various LED traffic signals |
Southeastern Lake County 9/2012 7/2013 $1.177 |
IMPACT ON TRAVEL:
60T41 Traffic signal modernization including installation of LED traffic signals at various locations in southeastern Lake County. |
|
Various Bridge repair on 3 structures. |
Park City, Libertyville Township, Wilmette 6/2013 11/2013 $0.216 |
IMPACT ON TRAVEL:
60T66 Structural steel repair to 3 structures located in Park City, Libertyville Township, and Wilmette. OTHER COMMENTS: Also in North Cook |
|
Various Bridge repair on 3 structures. |
Park City, Libertyville Township, Wilmette 6/2013 11/2013 $0.216 |
IMPACT ON TRAVEL:
60T66 Structural sateel repair to 3 structures located in Park City, Libertyville Township, and Wilmette. OTHER COMMENTS: Also in Cook County |
|
Various LED installation-Traffic signal modernization. |
NW Lake County 6/2013 10/2013 $0.514 |
IMPACT ON TRAVEL:
60T65 LED installation, traffic signal modernization at various locations in northwestern Lake County. |
|
Various Installation of traffic signals. |
Southwestern Lake County 5/2013 9/2013 $1.025 |
IMPACT ON TRAVEL:
60T84 Installation of LED signal heads, traffic signal modernization at various locations in southwestern Lake County. |
|
Various locations LED installation, traffic signal modernization. |
Northwestern Lake County 6/2013 10/2013 $0.514 |
IMPACT ON TRAVEL:
60T85 LED installation, traffic signal modernization at various locations in northwestern Lake County. |
|
Wadsworth Road intersection with IL 131 Reconstruct and widen. |
Beach Park 5/2013 9/2013 $7.472 |
IMPACT ON TRAVEL:
63766 Reconstruct and widen the intersection of Wadsworth Road at IL 131. Project includes pavement removal aggregate subgrade, full depth HMA, curb and gutter, storm sewer, water main, traffic signals and landscaping in the Village of Beach Park. |
|
Woodland Drive Bridge replacement |
Lake Barrington 1/2013 7/2013 $0.554 |
IMPACT ON TRAVEL:
63716 Project consists of the removal of the existing structure and replacing it with a precast prestressed concrete deck beam bridge (27" depth), pavement removal and replacement, tree removal, earth excavation, guardrail, pavement markings, temporary traffic signals, and all other incidental items to complete the work on Woodland Drive at Flint Creek in the Village of Lake Barrington. |