CONSTRUCTION UPDATE REPORT

Lake

Effective: 02/07/12 4:26 PM

LOCATION AND DESCRIPTION MUNICIPALITY
START DATE
EST. STOP DATE
COST (millions)
COMMENTS
Atkinson Road

Traffic signals, resurfacing
Grayslake
5/2011
5/2012
$1.153
IMPACT ON TRAVEL: 63498 Project consists of HMA resurfacing, pavement removal, pulverization, installation of polystyrene fill, full-depth HMA pavement, traffic signals and all other incidental items to complete the work on FAU Route 198 (Atkinson Road) between Washington Street and Brae Loch Road in the Village of Grayslake.
Cemetery Road

Resurfacing, traffic signals
Gurnee
11/2009
10/2011
$6.161
IMPACT ON TRAVEL: 83845 Improvements consist of reconstructing Cemetery Road beginning 151' south of Washington Street to the Tri-State Parkway, from west of Cemetery Road to east of Cemetery Road, reconstructing Tri-State Parkway from east of Cemetery Road to south of IL Route 132 and the installation of a traffic signal at the Cemetery Road and Washington Street intersection, all located in the Village of Gurnee.
TRAFFIC ALERT: Please watch for detour for Cemetery Road. Storm sewer & excavation work is ongoing.
Deerfield Road over East Skokie Ditch

Bridge replacement
Highland Park
4/2012
9/2012
$1.231
IMPACT ON TRAVEL: 62102 Removal and replacement of the superstructure of the bridge carrying Deerfield Road over East Skokie Ditch located in Highland Park.
Everett Road

Widening, reconstruction, resurfacing, pavement markings, lighting on single-lane roundabout
Riverwoods
7/2010
10/2011
$2.23
IMPACT ON TRAVEL: 63415 Project consists of construction of a single-lane roundabout including widening, reconstruction, resurfacing, pavement markings, lighting and all other incidental items to complete the work on Everett Road at the intersection with Riverwoods Road in Riverwoods.
Gilmer Road

Construction of a bike path underpass
Fremont Township
5/2011
5/2012
$1.752
IMPACT ON TRAVEL: 63422 Construction of a bike path underpass, excavation, drainage structures, HMA pavement, pavement marking, lighting, landscaping and all other incidental items to complete the work on Fort Hill Trail and Glimer Road approximately 1.2 miles north of the IL Rte. 176 and Gilmer Road intersection.
Grand Avenue

Fiber optic communication system interconnect 10 signals.
Waukegan
3/2011
8/2012
$2.422
IMPACT ON TRAVEL: 63436 Project consists of new traffic signal equipment, a fiber optic communication system interconnecting 10 traffic signals and minor curb and gutter removal and replacement along Grand Avenue between IL Route 131 and Sheridan Road.
Hawthorne Drive, Orchard Lane, & Hook Drive, & IL 83

Construction of new sidewalk
Round Lake Beach
4/2011
10/2011
$0.425
IMPACT ON TRAVEL: 63467 Project consists of the construction of new sidewalk along the north right-of-way of Hawthorne Drive between Cedar Lake Road and Poplar Avenue, along the east right-of-way of Orchard Lane between Rollins Road and Hook Drive, and along the north right-of-way on Hook Drive between Orchard Lane and IL Rte. 83 along with miscellaneous spot repairs of existing sidewalk, handicap access and gap closures in the Village of Round Lake Beach.
Hunt Club Road

Construction of two single lane roundabouts, and landscaping
Old Mill Creek
4/2011
11/2011
$2.654
IMPACT ON TRAVEL: 63457 Project consists of the construction of two-single-lane roundabouts, roadway reconstruction, curb and gutter, ditches, storm sewer, sidewalk, driveways, structure adjustments, landscaping and all other incidental items to complete the work on Hunt Club Road from Milburn Road to Wadsworth Road in the Village of Old Mill Creek.
IL 137 at 7th Street and on 7th Street

Resurfacing, street lighting and landscaping.
Winthrop Harbor
4/2010
12/2011
$1.422
IMPACT ON TRAVEL: 63167 Project consists of HMA pavement removal, curb and gutter removal and replacement, sidewalk removal, stamped PCC sidewalk, transition street lighting, ornamental street lighting and landscaping, located on IL 137 at 7th Street and 7th Street from Whitney Avenue to the Union Pacific Railroad tracks, in the Village of Winthrop Harbor.
IL 137 at O'Plaine Road

Widening, resurfacing
Green Oaks
8/2011
5/2012
$0.828
IMPACT ON TRAVEL: 60K19 Widening, resurfacing, drainage, traffic signal modernization and retaining wall on IL 137 at O’Plaine Road in Green Oaks.
IL 173

Bridge rehabilitation at 2 locations on IL 173
Antioch Township
3/2011
5/2012
$3.108
IMPACT ON TRAVEL: 62037 Bridge rehabilitation at 2 locations, IL 173 at East Boat Channels located 2.90 km west of IL 59, and IL 173 at West Boat Channels located 4.02 km west of IL 59, all located in Antioch Township in Lake County.
TRAFFIC ALERT: Temporary signals at bridges allowing only one lane of traffic at a time. Please watch for signs and drive responsibly.
IL 176 (Rockland Road)

Bridge replacement
Lake Bluff
3/2012
6/2012
$1.627
IMPACT ON TRAVEL: 60J67 Removal and replacement of the bridge carrying IL Route 176 (Rockland Road) over the East Skokie Ditch in Lake Bluff.
OTHER COMMENTS: Project on hold awaiting utility relocators.
IL 21

Temporary Pavement, tree removal
gurnee, Waukegan, Libertyville Township, Libertyville
9/2011
10/2011
$2.341
IMPACT ON TRAVEL: 60P33 2.05 miles of temporary pavement, tree removal and grading associated with the proposed reconstruction of IL Route 21 in Gurnee, Waukegan, Libertyville Township and Libertyville.
IL 21 (Milwaukee Avenue)

Bridge reconstruction, adding lanes and traffic signals
Gurnee, Waukegan, Libertyville
3/2012
8/2013
$22.967
IMPACT ON TRAVEL: 60953 2.20 miles of roadway reconstruction, bridge reconstruction, adding lanes and traffic signal modernization on IL 21 Milwaukee Avenue from south of IL Route 120 to south of IL 137 (Buckely Road), in Gurnee, Waukegan and Libertyville.
IL 21 (Milwaukee Avenue) over Bull Creek

Beam and bearing fabrication
Libertyville
1/2012
8/2012
$0.141
IMPACT ON TRAVEL: 60P54 Beam and bearing fabrication for the proposed reconstruction of the structure carrying IL Route 21 - Milwaukee Avenue over Bull Creek in Libertyville.
OTHER COMMENTS: There is no impact to traffic.
IL 22

Roadway reconstruction, widening and traffic signals
Highland Park and Bannockburn
5/2011
6/2012
$11.49
IMPACT ON TRAVEL: 60860 2.11 miles of roadway reconstruction, widening, drainage, traffic signal modernization and other work on IL Route 22 from east of I-94 to west of U.S. Route 41 in Highland Park and Bannockburn.
OTHER COMMENTS: One lane in each direction with left turn lanes at signalized intersections.
IL 83

Resurfacing, widening, and traffic signals
Antioch and Lake Villa
9/2009
12/2011
$13.436
IMPACT ON TRAVEL: 62700 4.41 miles of resurfacing, widening, traffic signals, drainage and intersection improvements on IL 83 from Wisconsin State line to north of Petite Lake Road in the Village of Antioch and Lake Villa.
TRAFFIC ALERT: Daytime closures only.
IL 83 (Milwaukee Avenue) @ IL 132 (Grand Ave.)

Intersection widening, traffic signals, retaining wall.
Lake Villa
3/2011
12/2011
$4.289
IMPACT ON TRAVEL: 60931 Intersection widening, traffic signal modernization and retaining wall construction on IL 83 (Milwaukee Avenue) at IL 132 (Grand Avenue) in Lake Villa.
TRAFFIC ALERT: One lane in each direction with left turn lanes at intersection.
Juniper Court

Bridge replacement
Deerfield
8/2011
12/2011
$0.295
IMPACT ON TRAVEL: 63587 Project consists of superstructure removal and replacement with a new precast prestressed concrete superstructure (17" depth), roadway approaches and all other incidental items to complete the work on Juniper Court between Cedar Street and Arbor Vitae Road in the Village of Deerfield.
Lewis Avenue

Traffic signals and inter-connecting with 22 traffic signals, detectable ADA warnings.
Waukegan, Beach Park, Zion, Winthrop Harbor
6/2010
9/2011
$3.621
IMPACT ON TRAVEL: 63344 Project consists of new traffic signal equipment, a fiber optic communication system inter-connecting 22 traffic signals, minor curb and gutter removal and replacement with detectable warning pad to accommodate ADA requirements and all other items to complete the work at 22 intersections along Lewis Avenue from 14th Street to Rosecrans Avenue in Waukegan, Beach Park, Zion, and Winthrop Harbor.
Main Street

Sidewalk, storm sewer, and grading work
Round Lake Park, Round Lake
9/2011
5/2012
$0.235
IMPACT ON TRAVEL: 63599 This project includes sidewalk, storm sewer and grading work on Main Street from MacGillis Drive in Round Lake to west of Fairlawn Drive in Round Lake Park.
Old Rand Road

Retaining wall, storm sewer modificatons
Lake Zurich
9/2011
11/2011
$0.256
IMPACT ON TRAVEL: 63589 Project consists of the construction of sidewalks, a retaining wall, storm sewer modifications, and all other incidental items to complete the work on Old Rand Road from IL Rte. 22 to Grand Avenue and on Surryse Road from Alpine Family Center to Buesching Road in the Village of Lake Zurich.
Rollins Road

Fiber optic interconnect to traffic signals controllers
Fox Lake, Round Lake Heights, Round Lake Beach & Vernon Hills
4/2011
12/2011
$1.738
IMPACT ON TRAVEL: 63472 Project consists of fiber optic interconnect to connect existing traffic signal controllers and to expand the Lake County Division of Transportation fiber optic ITS communication network, located on Rollins Road from US 12 to Lotus Drive and on IL 83 from US 45 to Westmoreland Drive in the Village of Fox Lake, Round Lake Heights, Round Lake Beach and Vernon Hills.
Sheridan Road

Traffic signals interconnections at 9 intersections
Waukegan, North Chicago
8/2011
2/2012
$0.799
IMPACT ON TRAVEL: 63592 Modernization of two traffic signals, including new poles, signal heads and controllers and the interconnection of nine intersections between Martin Luther King Jr. Drive and Belvidere Road, located in the city of North Chicago and the City of Waukegan.
US 12 and Honey Lake Road

New traffic signals and channelizaiton
Lake Zurich
8/2011
6/2012
$0.516
IMPACT ON TRAVEL: 60L68 Installation of new traffic signals and channelization at the intersection of US 12 and Honey Lake Road located in Lake Zurich.
OTHER COMMENTS: Daytime lane closures only.
US 12/IL 59

Channelization and traffic signals.
Wauconda
9/2011
5/2012
$0.499
IMPACT ON TRAVEL: 60L20 Channelization and traffic signal modernization of U.S. Route 12/IL Route 59 at Bonner Road in Wauconda.
US 14 (Northwest Highway) at Kelsey Road

Channelization and traffic signal modernization
Lake Barrington
5/2012
9/2012
$0.606
IMPACT ON TRAVEL: 60K17 Channelization and traffic signal modernization for US Route 14 (Northwest Highway) at Kelsey Road in Lake Barrington.
US 45

Roadway reconstruction, adding lanes and traffic signal modernization.
Grayslake, Third Lake, Lake County
8/2010
12/2011
$12.199
IMPACT ON TRAVEL: 60956 1.55 miles of roadway reconstruction, adding lanes and traffic signal modernization along US 45 from IL 120 (Belvidere Road) to Jeffrey Street in Grayslake, Third Lake and Lake County.
TRAFFIC ALERT: Traffic lanes will be reduced during construction activities.
OTHER COMMENTS: One lane in each direction will be maintained with occasional reductions to one lane only and flaggers.
US 45

Installation of decorative pedestrian lighting.
Mundelein
8/2010
11/2011
$0.175
IMPACT ON TRAVEL: 63448 Project consists of the installation of decorative pedestrian lighting and all other incidental items to complete the work on FAP Rte. 344 (US 45) from Park Street to IL Rte. 176 in the Village of Mundelein.
various

Traffic signal modernization
Lake County
5/2012
10/2012
$0.299
IMPACT ON TRAVEL: 60P49 Traffic signal modernization at 17 intersections along various routes in Lake County.
Various

Resurfacing, sidewalk, sign installation
North Chicago
8/2011
9/2011
$0.118
IMPACT ON TRAVEL: 63591 Project consists of sidewalk construction, curb and gutter removal and replacement, sign installation, pavement marking and all other incidental items to complete the work on various routes in the city of North Chicago.
various locations

Scour countermeasures
Lake and McHenry counties
4/2012
7/2012
$0.315
IMPACT ON TRAVEL: 60M86 Scour countermeasures at four various locations in Lake and McHenry Counties.
Various routes

Pavement patching
Lake and McHenry Counties
9/2011
12/2011
$1.693
IMPACT ON TRAVEL: 60N94 Pavement patching on various routes in Lake and McHenry Counties.
Various routes

Traffic signals
Highland Park
10/2010
9/2011
$1.755
IMPACT ON TRAVEL: 63485 Project consists of the installation of a new fiber optic interconnect cable and modification of the existing traffic signals along various routes in Highland Park.
Washington Street

Widening of Washington Street to five lanes, traffic signals and interconnect improvements.
Gurnee
2/2010
10/2011
$5.468
IMPACT ON TRAVEL: 63209 This project consists of the widening of Washington Street from two through lanes to 5 lanes of full-depth HMA pavement on an aggregate subgrade with curb and gutter, storm sewers, traffic signals and interconnect improvements starting 1,222 feet east of Cemetery Road to west of Milwaukee Avenue (east of Six Flags Drive) and project also includes the reconstruction of 350 feet of Tri-State Parkway in Gurnee.