CONSTRUCTION UPDATE REPORT
City of Chicago
Effective: 02/07/12 4:26 PM
| LOCATION AND DESCRIPTION |
MUNICIPALITY START DATE EST. STOP DATE COST (millions) |
COMMENTS |
|
Congress Parkway Bridge house repairs |
Chicago 8/2011 12/2011 $0.179 |
IMPACT ON TRAVEL:
60P18 Rehabilitation of the heating, ventilation and air conditioning (HVAC) systems in the east and west bridge houses along Congress Parkway over the south branch of the Chicago River in Chicago. |
|
Congress Parkway Rehabilitation of the existing bridge. |
Chicago 3/2010 11/2011 $33.012 |
IMPACT ON TRAVEL:
60D61 Rehabilitation of the existing bridge carrying Congress Parkway over the south branch of the Chicago River and bridge painting with other repairs to the structure carrying Congress Parkway between Chicago River and Post Office all located in the City of Chicago. |
|
East side of Doty Avenue Rehabilitation of existing IDOT pumping station |
Chicago 8/2010 11/2012 $6.668 |
IMPACT ON TRAVEL:
60799 Complete rehabilitation of the existing IDOT pumping station number 27 located at the east side of Doty Avenue at 110th Street along I-94/Bishop Ford Expressway. |
|
Elston Avenue over I-94 (Eden's Exp) Bridge replacement |
Chicago 11/2010 12/2011 $3.371 |
IMPACT ON TRAVEL:
60C18 Replacement of the superstructure, deck and center pier along with rehabilitation of the substructure, lighting, striping and other work on the structure carrying Elston Avenue over I-94 (Eden's Expressway) in Chicago. |
|
Hyde Park Road Resurfacing |
Chicago 9/2011 5/2012 $0.169 |
IMPACT ON TRAVEL:
60M14 0.18 mile of resurfacing on Hyde Park Road from Lake Park Avenue to Hyde Park Boulevard in the City of Chicago. |
|
I-55 (Stevenson Expressway) Bridge deck repairs |
Chicago 4/2012 8/2012 $0.482 |
IMPACT ON TRAVEL:
60P37 Bridge deck repairs on the structure carrying I-55 (Stevenson Expressway) from Prairie Avenue to the Canadian National Railway (formerly ICG RR). |
|
I-57 from I-80 to I-94 Landscaping |
Chicago, Calumet Park, Blue Island, Riverdale, Dixmoor, Posen, Harvey, Markham, Oak Forest & Country Club Hills 4/2011 5/2012 $0.522 |
IMPACT ON TRAVEL:
60L66 Landscaping along I-57 from I-80 to I-94 in Chicago, Calumet Park, Blue Island, Riverdale, Dixmoor, Posen, Harvey, Markham, Oak Forest and Country Club Hills. OTHER COMMENTS: Also in South Cook County |
|
I-90/94 Light tower foundation repairs |
Chicago 8/2011 11/2011 $0.381 |
IMPACT ON TRAVEL:
60P16 High mast light tower foundation repairs along I-90/94 (Dan Ryan Expressway) at 76th Street, 81st Street and 82nd Street in Chicago. |
|
I-90/94 Bridge repair |
Chicago 8/2011 12/2011 $1.399 |
IMPACT ON TRAVEL:
60P27 Structural repair of concrete and bridge drainage system repairs on 19 structures along I-90/94 from Maxwell Street to 28th Place in Chicago. |
|
I-90/94 (Dan Ryan Exp) New reinforced concrete truck parking area & retaining wall |
Chicago 4/2011 11/2011 $1.034 |
IMPACT ON TRAVEL:
60L61 Construction of a new reinforced concrete truck parking area and retaining wall at Pump Station #26 located along I-90/94 (Dan Ryan Expressway) on Roosevelt Road at Union Road in Chicago. |
|
I-90/94 (Dan Ryan Expressway) Painting 54 bridges |
Chicago 8/2011 6/2012 $2.948 |
IMPACT ON TRAVEL:
60N01 Painting 54 bridges at various locations along I-90/94 (Dan Ryan Expressway) from Cermak Road to Canal Street in Chicago. |
|
I-90/94 (Dan Ryan Expressway) Rehabilitation of two Pump stations |
Chicago 8/2010 6/2012 $4.004 |
IMPACT ON TRAVEL:
60828 Rehabilitation of Pump Station 26 along I-90/94 (Dan Ryan Expressway) at Roosevelt Road and Union Avenue near UIC in Chicago. |
|
I-90/94/290 Barrier wall installation, signing, drainage, and retaining wall, shoulder widening. |
Chicago 4/2012 8/2012 $1.704 |
IMPACT ON TRAVEL:
60P67 Barrier wall installation, signing modification, drainage revisions, retaining wall, shoulder widening and other work along I-90/94/290 (Circle Interchange at Hubbard Street to Polk Street and Western Street to Wells Street) in Chicago. |
|
I-94 (Bishop Ford Expressway) Bridge replacement |
Chicago 4/2011 12/2011 $3.711 |
IMPACT ON TRAVEL:
60F65 Removal and replacement of the superstructure and substructure of the bridge on FAI 94 (Bishop Ford Expressway) at Cottage Grove Avenue, replacement of the southeast retaining wall, approach pavements, lighting, fencing and drainage improvements located in Chicago. |
|
I-94/90 New retaining walls, ramp pavement, and signing. |
Chicago 6/2009 11/2011 $9.272 |
IMPACT ON TRAVEL:
62408 Construction of new retaining walls, ramp pavement, signing and other work on I-94/90 from Hubbard's Cave to I-290 in Chicago. |
|
IL 1 (Halsted St.) Bridge repairs |
Chicago 8/2011 12/2011 $0.243 |
IMPACT ON TRAVEL:
60M84 Bridge repairs to the structure carrying IL 1 (Halsted Street) over the Little Calumet River in Chicago. |
|
IL 43 (Harlem Avenue) Bridge repair |
Chicago 8/2011 11/2011 $0.361 |
IMPACT ON TRAVEL:
60L53 Bridge repair, joint reconstruction and deck sealing on the structure carrying IL 43 (Harlem Avenue) over Canadian National Railroad in Chicago. |
|
McCormick Boulevard/Dempster St. Safety traffic upgrades, traffic signal modernization |
Skokie, Lincolnwood & Chicago 3/2011 12/2011 $1.339 |
IMPACT ON TRAVEL:
60K24 Safety traffic upgrades on McCormick Boulevard from Church Street to Devon Avenue and traffic signal modernization, temporary signals and interconnect on Dempster Street from McCormick Boulevard to Keeler Avenue in Skokie, Lincolnwood and Chicago. |
|
Northside Maintenance Yard Landscaping, fencing and knee wall |
Chicago 6/2011 5/2012 $0.353 |
IMPACT ON TRAVEL:
60N78 Landscaping, fencing and knee wall installation at the IDOT Northside Maintenance Yard in Chicago. |
|
Pulaski Road Resurfacing |
Chicago 8/2011 11/2011 $0.399 |
IMPACT ON TRAVEL:
60K88 0.59 mile of resurfacing on Pulaski Road from north of IL 64 to Division Street in Chicago. |
|
Pulaski Road Drainage improvements and resurfacing |
Chicago, Oak Lawn 9/2011 12/2011 $0.671 |
IMPACT ON TRAVEL:
60P21 Drainage improvements and resurfacing along 0.20 mile of Pulaski Road at 103rd Street in Chicago and Oak Lawn. OTHER COMMENTS: Lanes closed on Piulaski Road. Expect delays |
|
Various locatiaons Bridge deck sealing |
Chicago, Hillside, Maywood, Oak Park, Bellwood, Forest Park, Elmhurst 5/2012 8/2012 $0.515 |
IMPACT ON TRAVEL:
60P61 Bridge deck sealing on various structures at various locations on Congress Parkway, Central Loop south overheads and I-290 overheads in Chicago, Hillside, Maywood, Oak Park, Bellwood, Forest Park and Elmhurst. OTHER COMMENTS: Also in DuPage County |
|
Various locations Bridge painting |
Peotone and Chicago 5/2011 12/2011 $1.067 |
IMPACT ON TRAVEL:
60L83 Bridge painting of 7 structures at various locations in Peotone and Chicago. OTHER COMMENTS: Also in Will County |