SPRINGFIELD, ILL, -- The Illinois Department of Transportation will open bids on June 13, 2003 for various road and bridge improvement projects located throughout the state. Also included are 21 aeronautics projects, two land reclamation projects and one water resource project.

Following is a list of the projects by county:

1. Lake County, US 45 & IL 60, District 1, Contract No. 62330 milling and bituminous concrete surface on 0.28 mile of US 45 from Allanson Road to North Shore Avenue and on IL 60 at Hawley Road in Mundelein. 25 Working Days.

2. Lake County, IL 83 & IL 120, District 1, Contract No. 62331, milling and bituminous concrete surface on 0.30 mile of IL 120 from Neville Drive to Harding Street and on 0.40 mile of IL 83 from IL 137 to IL 120 in Grayslake. 15 Working Days.

3. Iroquois County, IL 1, District 3, Contract No. 66246, 7.65 miles of milling and bituminous concrete resurfacing on IL 1 from US 45/52 to US 24 in Watseka. Includes bridge rehabilitation over the Iroquois River. Completion Date October 15, 2003.

4. Ford County, IL 9, District 3, Contract No. 66296, 8.48 of milling and bituminous concrete resurfacing on IL 9 from US 45 in Paxton to the Vermilion County Line. Completion Date October 15, 2003.

5. LaSalle-Livingston Counties, IL 17, District 3, Contract No. 66357, 11.25 miles of milling and bituminous concrete resurfacing on IL 17 from Wenona to IL 23 near Wenona. Completion Date September 01, 2003 Plus 10 Working Days.

6. Champaign County, I-57, District 5, Contract No. 70009, 11.8 miles of bituminous concrete resurfacing on Interstate 57 from south of Sadorous Road to south of Interstate 74, includes resurfacing the ramps at Monticello Road in Champaign. Completion Date August 15, 2004 Plus 10 Working Days.

6P. Madison County, IL 159, District 8, Contract No. 76014, widening and resurfacing to five lanes 3.64 km of IL 159 from north of I-270 to Harvard Drive in Edwardsville. Also includes construction of 728 m of relocated IL 159, the reconstruction of Kettle River Drive and Cougar Road, the widening and resurfacing of Center Grove Road to add through and right turn lanes and the extension of pedestrian box culvert, all in Glen Carbon and Edwardsville. Completion Date June 15, 2004.

7. Piatt County, I-74, District 5, Contract No. 70027, 3.83 miles of bituminous concrete resurfacing and bridge rehabilitation on Interstate 74 from 4 miles west of Mansfield to Mansfield. Completion Date November 15, 2003 Plus 10 Working Days.

8. Morgan County, US 67/IL 104, District 6, Contract No. 72262, 1.75 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing, 4 ft bituminous shoulders, 3 ft aggregate shoulders and guardrail improvements on US 67/IL 104 approximately 1 mile northwest of Bethel. 25 Working Days.

9. Brown-Pike Counties, IL 99, District 6, Contract No. 72519, Pavement patching, bituminous surface removal, bituminous concrete resurfacing, 7 ft bituminous shoulders and 3 ft aggregate shoulders on IL 99 from Versailles extending 5.45 miles southeast to IL 104 west of Meredosia. 50 Working Days.

10. Schuyler County, IL 101, District 6, Contract No. 72520, Pavement patching, bituminous surface removal, bituminous concrete resurfacing, and 3 ft aggregate wedge shoulders on IL 101 from US 67 east of Littleton extending west 5.70 miles. 35 Working Days.

11. Adams County, IL 104, District 6, Contract No. 72521, 1.82 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing, 4 ft bituminous shoulders and 3 ft aggregate wedge shoulders on IL 104 from 0.4 mile east of Plainville Road extending east to 0.2 mile east of Columbus Road, all about 8 miles east of Quincy. 20 Working Days.

12. Montgomery County, IL 127, District 6, Contract No. 72525, 8.09 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing, 3 ft bituminous shoulders and 3 ft aggregate wedge shoulders on IL 127 from Short Street in Raymond extending south to Sealy Street in Butler. Completion Date October 31, 2003.

12P. Madison County, IL 159, District 8, Contract No. 76013, 1.82 kilometers of widening to five lanes and resurfacing of IL 159 from IL 162 in Maryville to Glen Crossing Road in Glen Carbon. Completion Date November 01, 2004.

13. Montgomery County, IL 48, District 6, Contract No. 72549, Pavement patching, bituminous surface removal, bituminous concrete resurfacing and 3 ft aggregate shoulders on IL 48 beginning at Springfield Road in Raymond and extending 2.85 miles northeast to the Christian County Line in Harvel. 30 Working Days.

14. Logan County, Old IL 121, District 6, Contract No. 72800, 2 miles of bituminous surface removal, bituminous concrete resurfacing and 4.5 ft aggregate shoulders on Old IL 121 from 3 miles north of Lincoln to 5 miles north of Lincoln. 25 Working Days.

15. Sangamon County, I-55 WFR & Panhandle Road, District 6, Contract No. 72806, 1.78 miles of bituminous surface treatment, fence replacement and pavement marking on the I-55 West Frontage Road at the north end of Williamsville. Also includes 1.83 miles of bituminous surface treatment and pavement marking on Panhandle Road on the east side of I-55 south of Springfield. 15 Working Days.

16. St. Clair County, IL 4/IL 15, District 8, Contract No. 76554, 4.8 miles of bituminous surface removal, bituminous concrete resurfacing and 1.5 ft aggregate wedge shoulders on IL 4/15 from Fayetteville to St. Libory, and on IL 15 from IL 4 in St. Libory east to Sparta Road. Completion Date October 31, 2003.

17. Bond County, IL 127 & US 40, District 8, Contract No. 76656, 10.6 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing , 3 ft bituminous wedge shoulders and 3 ft aggregate wedge shoulders on IL 127 west of Greenville from IL 140 north to the Montgomery County Line and on US 40 southwest of Greenville from CH 17 northeast 0.62 mile to 0.2 mile northeast of the CSXT Railroad Structure. 65 Working Days.

18. Madison County, IL 162, District 8, Contract No. 76661, 6.1 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing and aggregate shoulders on IL 162 from IL 111 to IL 157 at Pontoon Beach, and from IL 157 to IL 159 at Maryville. 40 Working Days.

19. Bond-Clinton Counties, IL 127, District 8, Contract No. 76663, 15.15 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing and 3 ft aggregate shoulders on IL 127 between Carlyle and Greenville. 50 Working Days.

20. Madison County, IL 143, District 8, Contract No. 76665, 3.23 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing and 3 ft aggregate shoulders on IL 143 from I-70 southeast to Cherry Street in Highland. Completion Date October 31, 2003.

21. Greene-Jersey Counties, IL 267, District 8, Contract No. 76666, 8.65 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing, and 3 ft aggregate shoulders on IL 267 from IL 108 south of Greenfield south to the Macoupin County Line north of Medora. Completion Date November 15, 2003.

22. Jersey County, IL 109, District 8, Contract No. 76680, Pavement patching, bituminous surface removal, bituminous concrete resurfacing, 3 ft bituminous shoulders and 3 ft aggregate shoulders on IL 9 from US 67 in Jerseyville south 8.18 miles to IL 3. 50 Working Days.

23. Madison County, US 40, District 8, Contract No. 76681, 4.13 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing, 3 foot bituminous shoulders and 4 foot aggregate shoulders on US 40 from east of I-55/70 at Troy east to IL 4. Completion Date November 15, 2003.

24. Effingham County, I-70, District 7, Contract No. 94862, At the I-70 eastbound National Trail Rest Area, 4 miles east of Altamont. Construct new parking areas for cars and trucks; the existing parking area will be partially removed and the remaining area will be patched and resurfaced and incorporated into the new car parking area. A new truck parking lot will be constructed behind the existing building. 70 Working Days.

25. Jefferson County, I-57, District 7, Contract No. 94932, The lengthening of the northbound and southbound exit ramp right turn lanes at the interchange of I-57 and IL 15 in Mount Vernon. 55 Working Days.

26. Jackson County, US 51 & IL 13, District 9, Contract No. 98749, 1.48 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing on US 51 from Industrial Park Road north to Airport Road; and on IL 13 (Main Street) from Wall Street east to east of Lewis Lane, all in Carbondale. 25 Working Days.

27. Jackson County, IL 4, District 9, Contract No. 98773, 10.31 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing and 2 ft aggregate shoulders on IL 4 from west of the intersection with IL 151 in Ava east to the intersection with IL 13/127. 35 Working Days.

28. Union County, IL 3, District 9, Contract No. 98788, 8.02 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing and 2 feet aggregate shoulders on IL 3 from 0.18 mile south of the Jackson/Union County Line south to the intersection with IL 146 in Ware. 40 Working Days.

29. Williamson County, IL 13, District 9, Contract No. 98791, The reconstruction of the intersection of IL 13 and Spillway Road east of Carbondale. Includes pavement removal and replacement, median removal increasing radii for turning movements, new traffic signals and lighting, and striping. 60 Working Days.

30. Franklin County, IL 37, District 9, Contract No. 98796, Pavement patching, bituminous surface removal, widening, bituminous and aggregate shoulders, and curb and gutter for construction of a left turn lane at the south approach of the intersection of IL 37 and IL 154 north of Benton. 55 Working Days.

31. Alexander County, IL 3, District 9, Contract No. 98816, 4.20 miles of pavement patching, bituminous concrete surface, 8 ft bituminous shoulders and 3 ft aggregate shoulders construction on IL 3 west of Mounds to 2 miles west of the intersection with IL 127; and also extends 2.2 miles south of the intersection with IL 127. 45 Working Days.

32. Perry County, IL 127, District 9, Contract No. 98799, Bridge deck repairs, bearing replacements and a microsilica concrete deck overlay on the bridges carrying IL 127 over Swanwick Creek and the Swanwick Creek Overflow located 4.1 and 4.25 miles south of the Washington County Line. 50 Working Days.

33. Kane County, IL 56, District 1, Contract No. 62378, Repairs to the substructure of the bridge carrying IL 56 (Butterfield Road) over Blackberry Creek located 0.4 mile north of Galena Boulevard in Sugar Grove. 15 Working Days.

34. LaSalle County, IL 251, District 2, Contract No. 64152, Removal and replacement of the existing structure carrying IL 2 over a stream located 0.4 mile north of US 52 in Mendota. Completion Date November 03, 2003.

35. Rock Island County, I-280, District 2, Contract No. 64287, Removal and replacement of the structure carrying 27th Street in Moline over Interstate 280 just west of the Interstate 74/280 interchange. Completion Date November 15, 2004.

36. Coles County, US 45, District 5, Contract No. 70286, Modernization of the traffic signals and inlay the bituminous resurfaced lanes of US 45 at the intersection of Old State Road south of Mattoon. 30 Working Days.

37. Madison County, I-270, District 8, Contract No. 76604, Lighting improvements on I-270 at IL 3 and IL 203 located west of Pontoon Beach. 35 Working Days.

38. Madison County, Various Routes, District 8, Contract No. 76641, Modernization of the traffic signals by installing LED signal heads at the following intersections at Alton: (1) IL 3 with Broadway (2) US 67 with IL 143/Landmark Blvd. (Clark Bridge) (3) IL 3 with Niagra/Virgina Avenue (4) IL 111/140 with Fosterburg Road (5) IL 140 (Broadway Connector) with IL 143/Berm Highway (6) IL 3/111 with Humbert Street (7) IL 3/111 with Godfrey Road/State Street and (8) US 67 with Northport Drive. 30 Working Days.

39. Madison County, IL 203 & IL 111, District 8, Contract No. 76642, Modernization of the traffic signals by installing LED signal heads at the following intersections: (1) IL 203 with Pontoon Road in Granite City (2) IL 203 with St.Clair Avenue/Iowa Street in Granite City (3) IL 111 with Horseshoe Lake Road at Pontoon Beach (4) IL 203 with Maryville Road north of Granite City (5) IL 111 with Madison Avenue/ Hawthorne Street at Roxana and (6) IL 111 with Poag Road/New Poag Road south of Roxana. 30 Working Days.

40. Williamson County, I-57, District 9, Contract No. 98804, installation of new weigh-in-motion (WIM) electronics to upgrade the ramp WIM sorter scales at the northbound I-57 Weigh Station south of Marion. 15 Working Days.

41. Cook County, I-94/Edens Expwy (SB), District 1, Contract No. 62455, Concrete pavement patching on the southbound entrance and exit ramps of I-94 (Eden's Expressway) at old Orchard Road in Skokie. Completion Date September 30, 2003.

42. Lake County, IL 83/McHenry Road, District 1, Contract No. 62466, Concrete pavement patching along IL 83/McHenry Road located north of Lake-Cook Road in Buffalo Grove. 15 Working Days.

43. Lake County, IL 120, District 1, Contract No. 62483, Bridge painting at 7 locations along IL 120 from Des Plaines River to Union Pacific Railroad in Waukegan and Park City. 85 Working Days.

44. Lake County, US 41, District 1, Contract No. 62489, 0.92 mile of barrier wall repair along US 41 from Lake-Cook Road to north of Clavey Road in Highland Park. Completion Date November 15, 2003 Plus 05 Working Days.

45. Lake County, IL 137, District 1, Contract No. 62561, Storm sewer maintenance consisting of cleaning existing storm sewers and drainage structures and frame and grate replacement along IL 137 from the Wisconsin state line to the south limits of Winthrop Harbor. 15 Working Days.

46. Cook County, US 12, District 1, Contract No. 62562, Storm sewer maintenance consisting of cleaning existing storm sewers and drainage structures along US 12 from IL 33 to Euclid Avenue in Wheeling. 15 Working Days.

47. Cook-Kane Counties, IL 19, District 1, Contract No. 62565, Storm sewer maintenance consisting of cleaning existing storm sewers and drainage structures along IL 19 from IL 25 to Schaumburg Road in Elgin. 25 Working Days.

48. Cook-Kane Counties, IL 72, District 1, Contract No. 62567, Storm sewer maintenance consisting of cleaning existing storm sewers and drainage structures along IL 72 from east of IL 25 to west of Beverly Road and at Oakton Street in East Dundee, Hoffman Estate and Elk Grove Village. 15 Working Days.

49. Cook County, US 14, District 1, Contract No. 62568, Storm sewer maintenance consisting of cleaning existing storm sewers and drainage structures along US 14 from Highland Avenue to Des Plaines River Road in Arlington Heights and Mount Prospect. 15 Working Days.

50. Cook County, 95th Street, District 1, Contract No. 62569, Storm sewer maintenance consisting of storm sewer cleaning and drainage structures to be cleaned along 95th Street from Melvina Avenue in Oaklawn to Western Avenue in Evergreen Park. 25 Working Days.

51. Cook County, Kedzie Avenue, District 1, Contract No. 62570, Storm sewer maintenance consisting of cleaning existing storm sewers and drainage structures located along Kedzie Avenue from 87th Street in Evergreen Park to 115th Street in Chicago. 20 Working Days.

52. Various Counties, Various Routes, District 8, Contract No. 76653, Pavement patching on various routes in various counties throughout District 8. Completion Date June 30, 2004.

53. Various Counties, Various Routes, District 8, Contract No. 76654, Pavement patching on various routes in various counties throughout District 8. Completion Date June 30, 2004.

54. Various Counties, Various Routes, District 8, Contract No. 76695, 16.82 miles of crack routing and sealing at the following locations: (1) on I-55/70 at the US 40 interchange, exit 17 at Troy (2) on US 40 from I-55/70 to Formosa Road south of Troy (3) on IL 143 from the Broadway Connector easterly 0.5 mile in Alton (4) on US 67 from 9th Street to Godfrey Road in Alton (5) on IL 255 from I-270 to New Poag Road south of Wanda (6) on IL 3 between Columbia and Waterloo (7) on US 51 between Irvington and Ashley and (8) on US 50 between Carlyle and Beckemeyer. 25 Working Days.

55. Lawrence-Richland-Effingham Counties, US 50 & I-57, District 7, Contract No. 94966, Wildflower planting at six locations on US 50 in Lawrence County, three locations on US 50 in Richland County, and two locations on I-57 in Effingham County. Completion Date December 01, 2003.

56. Pulaski-Alexander Counties, I-57, District 9, Contract No. 98802, interseeding native grasses and wildflowers (forbs) in existing turf areas of the foreslopes, ditches, backslopes, medians and infields along I-57 beginning at the Union/Pulaski County Line south of Dongola and extending south to the Mississippi River Bridge northwest of Cairo,. Completion Date December 01, 2003.

57. Johnson County, I-24, District 9, Contract No. 98811, 24 miles of continuously reinforced PCC pavement patching on I-24 from I-57 to the Massac County Line. 15 Working Days.

58. Will County, IL 394, District 1, Contract No. 62002, Removal of 2 existing structures carrying IL 394 (Bishop Ford Freeway) over the abandoned C.M. St. P.&P. Railroad. Includes construction of a concrete box culvert and 0.51 mile of pavement reconstruction, located near Goodenow Grove Forest Preserve northeast of Steger. Completion Date August 31, 2004 Plus 05 Working Days.

59. Cook County, Washington Blvd. District 1, Contract No. 62425, 4.64 miles of milling and bituminous concrete surface on Washington Blvd. from Austin Blvd. to Western Avenue in Chicago. 50 Working Days.

60. Bureau County, US 6, District 2, Contract No. 64387, 0.79 miles of bituminous concrete resurfacing and signal installation on US 6 from IL 26 (N) to IL 26 (S) in Princeton. Includes upgrading the traffic signals at the intersection of Main Street and installing new traffic signals at the intersection of Euclid. Completion Date November 24, 2004 Plus 10 Working Days.

61. Boone County, IL 76, District 2, Contract No. 64637, 15.46 miles of milling and bituminous concrete surface on IL 76 from Wisconsin State line to US Bus. 20 north of Belvidere. 60 Working Days.

62. Carroll County, Unmarked Route, District 2, Contract No. 64652, resurfacing park roads within Mississippi Palisades State Park. In addition, improvements will be made to the south entrance to park, including the construction of a right turn lane on IL 84 north of Savanna. 60 Working Days.

63. Rock Island County, IL 5, District 2, Contract No. 64859, Intersection improvement consisting of adding a right turn lane to the southbound lane of 60th Street and westbound lane of IL 5 (John Deere Road) in Moline. 40 Working Days.

64. JoDaviess County, IL 78, District 2, Contract No. 64906, 8.78 miles of milling and bituminous concrete resurfacing on IL 78 from Warren to US 20 near Stockton. 35 Working Days.

65. Grundy County, US 6, District 3, Contract No. 66116, 9.33 miles of milling and bituminous concrete resurfacing on US 6 from IL 47 in Morris east to the Will County line. Completion Date October 15, 2003 Plus 10 Working Days.

66. McLean County, IL 9, District 3, Contract No. 66163, 8.69 km of milling and bituminous concrete surface on IL 9 from IL 122 to US 150 west of Bloomington. Completion Date October 01, 2003.

67. Iroquois County, IL 49, District 3, Contract No. 66173, 6.0 miles of milling and bituminous concrete resurfacing on IL 49 from 2400 Road (2 miles south of US 45/52) to US 24 at Cresent City. Completion Date October 15, 2003.

68. LaSalle County, IL 23, District 3, Contract No. 66262, 1.37 miles of milling and bituminous concrete resurfacing on IL 23 from 840 feet south of McKinley Road north to IL 71 in Ottawa. Includes signal modernization at the signalized intersection. 40 Working Days.

69. LaSalle County, IL 351, District 3, Contract No. 66304, 2.55 miles milling and bituminous concrete resurfacing on IL 351 from 4th Street in LaSalle south to Walnut Street in Oglesby. 30 Working Days.

70. McLean County, IL 122, District 3, Contract No. 66318, Removal and replacement of an existing entrance culvert on IL 122 with a precast box culvert located 2.5 miles east of Stanford. 20 Working Days.

71. Marshall-Woodford Counties, IL 117, District 3, Contract No. 66321, 8.99 miles of milling and bituminous concrete resurfacing on IL 117 from IL 116 north to LaRose Road south of Toluca. 35 Working Days.

72. Woodford County, IL 89, District 3, Contract No. 66333, 10.53 miles of milling and bituminous concrete surface on IL 89 from IL 116 at Metamora to Washburn. Completion Date October 15, 2003 Plus 05 Working Days.

73. Marshall-LaSalle Counties, IL 251, District 3, Contract No. 66334, 7.27 miles of milling and bituminous concrete surface on IL 251 from the Woodford County line to IL 17 West south of Wenona. 30 Working Days.

74. Livingston County, IL 17, District 3, Contract No. 66347, 8.64 miles of milling and bituminous concrete surface on IL 17 from IL 23 to IL 18 north of Manville. Completion Date September 01, 2003.

75. Woodford County, IL 116, District 4, Contract No. 68094, 1.99 miles of milling and bituminous concrete resurfacing on IL 116 from Far Hills Road to the intersection of Arbor Vitae/Schmitt Lane in German Hills. 85 Working Days.

76. Knox County, US 34, District 4, Contract No. 68236, 3.1 miles of milling and bituminous concrete resurfacing on US 34 from Prospect Street in Oneida to 0.7 miles north of Wataga. 20 Working Days.

77. Tazewell County, IL 122, District 4, Contract No. 68238, 2.93 miles of milling and bituminous concrete resurfacing on IL 122 from Morris Mill Road to IL 29, west of Delavan. 15 Working Days.

78. Warren County, Old US 34, District 4, Contract No. 68282, 2.36 miles of milling and bituminous concrete resurfacing on Old US 34 from 11th Street to the east city limits in Monmouth. 15 Working Days.

79. Fulton County, IL 100, District 4, Contract No. 68336, 4.34 miles of milling and bituminous concrete resurfacing on IL 100 from IL 78 to Main Street in Bryant. 20 Working Days.

80. Champaign County, US 150 & US 45, District 5, Contract No. 70103, 0.78 of a mile of milling and bituminous concrete resurfacing on US 150 and US 45 from Prairie Street to Wright Street, and Springfield Avenue to University Avenue in Champaign. 20 Working Days.

81. DeWitt-Piatt Counties, IL 10, District 5, Contract No. 70126, 13.42 miles of milling and bituminous concrete resurfacing on IL 10 from IL 48 at Wedon to 0.4 mile west of I-72. 75 Working Days.

82. Moultrie-Piatt Counties, US 36, District 5, Contract No. 70183, 13.11 miles of bituminous concrete removal and resurfacing on US 36 from west of IL 32 to the Douglas county line. 35 Working Days.

83. Champaign County, IL 130, District 5, Contract No. 70235, 6.87 miles of milling and bituminous concrete resurfacing on IL 130 from US 150 in Urbana to Madison Street in Philo. 50 Working Days.

84. Shelby-Moultrie Counties, IL 128, District 5, Contract No. 70296, 19.58 miles of milling and bituminous concrete resurfacing on IL 128 from Dalton City to North 6th Street in Shelbyville. 40 Working Days.

85. Piatt County, IL 48, District 5, Contract No. 70305, 0.69 mile of bituminous concrete patching and resurfacing on IL 48 over Interstate 72 near Cisco. 25 Working Days.

86. Macoupin County, IL 4, District 6, Contract No. 72404, 14.31 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing, 1 ft bituminous shoulders and 3 ft aggregate shoulders on IL 4 from south of Madison Street in Girard south to the Carlinville Square. Completion Date November 01, 2003.

87. Macoupin County, IL 16, District 6, Contract No. 72412, 3.66 miles of pavement patching bituminous surface removal, bituminous concrete resurfacing and 3 ft aggregate shoulders on IL 16 from Dorchester Road east to IL 4 in Gillespie. 35 Working Days.

88. Morgan County, IL 104, District 6, Contract No. 72424, Pavement patching, bituminous surface removal, bituminous concrete resurfacing, bituminous and aggregate shoulders on IL 104 from Illinois River Bridge in Meredosia to 1.82 miles to the east. Also included in the project is the construction of a portable scale turnout. 25 Working Days.

89. Mason County, IL 10 & US 136, District 6, Contract No. 72510, 12.99 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing, 3 ft bituminous shoulders and 3 ft aggregate shoulders on IL 10 from US 136 to IL 29 at Mason City; and on US 136 from IL 10 to 1.3 miles to the east Also included is a bridge deck microsilica concrete overlay IL 10 located approximately 3 miles south of US 136. Completion Date October 31, 2003.

90. Mason County, IL 78, US 136 & IL 97, District 6, Contract No. 72517, 10.09 miles of pavement patching bituminous surface removal, bituminous concrete resurfacing, 7 ft bituminous shoulders and 3 ft aggregate shoulders on IL 78 from north of Matanza Beach north to US 136 in Havana, then east on US 136 to IL 97, then southeast to 0.3 mile north of Long Beach Road north of Kilbourne. Completion Date December 15, 2003.

91. Cass County, IL 125, District 6, Contract No. 72524, 22.86 miles of earth work, pavement patching, bituminous surface removal, bituminous concrete resurfacing, bituminous shoulders, concrete gutter, guardrail removal and replacement and 3 ft aggregate shoulders on IL 125 from east of Arenzville Road in Beardstown to Old IL 123 in Ashland. Completion Date November 15, 2003 Plus 15 Working Days.

92. Logan County, Unmarked Route, District 6, Contract No. 72629, 4.53 miles of widening and resurfacing of the internal park roads and the reconstruction of parking areas at the Edward Madigan State Park located 1 mile south of Lincoln. Also included is the resurfacing of County Road 128. Completion Date October 31, 2003.

93. Montgomery County, Nokomis Blacktop, District 6, Contract No. 72801, bituminous concrete binder and surface courses and 3 ft aggregate shoulders on the Nokomis Blacktop beginning 5 miles west of Nokomis eastward for 2 miles. 15 Working Days.

94. Jersey County, IL 3, District 8, Contract No. 76218, At Grafton, construction of left turn lanes at the intersection of IL 3 with Grafton Hills Road and at the intersection of IL 3 with IL 100 along with the resurfacing of IL Rts 3 and 100. 70 Working Days.

95. Madison County, Governors' Parkway, District 8, Contract No. 76437, In Glen Carbon, 0.5 km new pavement with curb and gutter for Governor's Highway beginning at relocated IL 159 and extending to the east. 95 Working Days.

96. Madison County, IL 255, District 8, Contract No. 76543, 4.93 kilometers of construction of full depth bituminous pavement for a four lane IL 255 with bituminous and aggregate shoulders and the construction of an interchange at Fosterburg Road from north of Alton at Fosterburg Road southeast to Bethalto the. Completion Date August 31, 2005.

97. St. Clair County, I-55/70, District 8, Contract No. 76550, 0.10 miles of construction of a turnaround road between Main Street and Fourth Street in East St. Louis for detoured traffic from the Poplar Street Complex. 35 Working Days.

98. Clinton County, IL 160, District 8, Contract No. 76555, 8.58 miles of bituminous surface removal, bituminous concrete resurfacing and 2 ft aggregate shoulders on IL 160 from IL 177 in New Memphis north to Old US 50 in Trenton. Completion Date October 31, 2003.

99. Madison County, I-270, District 8, Contract No. 76622, 6.70 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing, bituminous and aggregate shoulders on I-270 from east of I-255 at Pontoon Beach east to the interchange I-55/70/270 north of Troy. Completion Date November 15, 2003.

100. St. Clair County, IL 4 & IL 158, District 8, Contract No. 76657, 4.7 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing, 3 ft aggregate shoulders, guardrail replacement and upgrade, and median replacement at the following three locations: (1) IL 4 from South Street in Lebanon to the south ramp termini of I-64 (2) IL 4 from IL 161 to Independence Street in Mascoutah and (3) IL158 from IL 161 to IL 177 east of Belleville. Completion Date October 31, 2003.

101. Monroe County, IL 156, District 8, Contract No. 76662, 8.69 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing and 3 ft aggregate shoulders on IL 156 from IL 159 in Hecker west to Market Street in Waterloo. 60 Working Days.

102. Madison County, IL 157, District 8, Contract No. 76668, 4.16 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing, 5 ft bituminous shoulders and 7 ft aggregate shoulders on IL 157 from north of Horseshoe Lake Road north to Game Drive in Glen Carbon. Completion Date October 31, 2003.

103. Jersey County, IL 739 (Eldred-Hillview Rd), District 8, Contract No. 76669, 3.86 miles of leveling binder, bituminous concrete surface course, and 3 ft aggregate shoulders on IL 739 (Eldred-Hillview Rd) from the Greene County Line south to IL 16/100 southeast of East Hardin. Completion Date October 31, 2003.

104. Madison County, Livingston & Williamson Rd, District 8, Contract No. 76670, 2.90 miles of leveling binder, bituminous concrete surface courses and 3 ft aggregate shoulders on Livingston Road from Old Rt 66 at Livingston west to IL 4 and; on Williamson Road east of Williamson from IL 4 easterly 0.83 mile. Completion Date October 31, 2003.

105. Madison County, Beltine Rd & Caseyville Rd, District 8, Contract No. 76675, 1.70 miles of bituminous surface removal, bituminous concrete resurfacing in Collinsville on Beltline Road from IL 157 to west of Bridleridge Road and on Caseyville Road from St. Louis Avenue to Morrison Avenue. Completion Date October 31, 2003.

106. St. Clair County, Various Routes, District 8, Contract No. 76678, 3.74 miles of pavement patching, bituminous concrete surface removal, bituminous concrete resurfacing and 2 ft aggregate shoulders at the following locations: (1) Bunkum Road in East St. Louis from 37th Street to Kingshighway (2) Bond Avenue in East St. Louis from 47th Street to IL 163 and (3) Old Rt 50 (St. Clair Avenue) in Fairview Heights from Holy Cross Drive to St. Clair Road. Completion Date October 31, 2003.

107. DuPage County, York/Harger Rd, District 1, Contract No. 83630, 0.49 mile of construction of a bike path, pedestrian bridge and widening the existing York Road Bridge over East-West Tollway, Salt Creek to I-88 Tollway ramp. 125 Working Days.

108. Kane County, Williams St/Lake Marion Rd, District 1, Contract No. 83659, 1.42 miles of reconstruction of Williams Street, resurfacing of Lake Marion Road, and the improvement of traffic signals, box culverts, storm sewers and landscaping on FAU Route 1280 in Carpentersville. Completion Date October 15, 2004 Plus 10 Working Days.

109. Cook County, Roy Avenue, District 1, Contract No. 83685, 1.28 miles of milling, resurfacing and patching Roy Avenue from North Avenue to MacArthur Drive in Northlake. 30 Working Days.

110. DuPage County, N. Ardmore Ave, District 1, Contract No. 83686, 0.44 mile of pavement patching and resurfacing on North Ardmore Avenue from St. Charles Road to the Union Pacific Railroad in Villa Park 30 Working Days.

111. Kane County, Various Roads, District 1, Contract No. 83688, 0.38 mile of milling, resurfacing and patching on Webster, River and Mill Streets, from IL 31 (Lake Street) to IL 25 in Montgomery. 20 Working Days.

112. Cook County, 123rd St, District 1, Contract No. 83690, 0.27 mile of milling and bituminous resurfacing, curb and gutter repairs, sidewalk removal and replacement from Western Avenue to Vincennes Avenue in Blue Island. 20 Working Days.

113. Cook County, Southwest Hwy / 103rd St, District 1, Contract No. 83691, intersection improvements, channelization, widening, and curb and gutter on Southwest Highway at 103rd Street and Virginia Avenue, in Chicago Ridge. Completion Date October 31, 2003.

114. Cook County, Warren Avenue, District 1, Contract No. 83692, 0.5 mile of milling existing pavement and bituminous resurfacing, curb and gutter, and pavement patching on Warren Avenue from North Forest Avenue to US 45 in Hillside. 20 Working Days.

115. Cook County, Southwest Highway, District 1, Contract No. 83694, 1.516 miles of intermittent pavement patching, bituminous surface removal and resurfacing on Southwest Highway from 95th Street to Cicero Avenue in Oak Lawn. 45 Working Days.

116. Cook County, 94th Ave., District 1, Contract No. 83695, 0.99 mile of resurfacing on 94th Avenue from 151st Street to 159th Street in Orland Park. Completion Date September 19, 2003 Plus 05 Working Days.

117. DuPage County, Woodward Ave, District 1, Contract No. 83697, 5,000 feet of milling, resurfacing and patching on Woodward Ave. from 75th Street to Wheeler Street in Woodridge. 30 Working Days.

118. Livingston County, CH 6, District 3, Contract No. 87245, 5.8 miles of bituminous concrete resurfacing with aggregate shoulders on CH 6, from IL 17 to Old Rt 66 north of Odell. Completion Date November 15, 2003.

119. Ford County, CH 19, District 3, Contract No. 87246, 4.99 miles of bituminous resurfacing on CH 19 from US 24 southerly to CH 21 southeast of Piper City. 20 Working Days.

120. McLean County, CH 59, District 3, Contract No. 87247, 4.08 miles of bituminous concrete resurfacing with aggregate shoulders along CH 59 from CH 34 southerly to 2 miles northwest of McLean. 30 Working Days.

121. LaSalle County, Ed Hand Highway, District 3, Contract No. 87251, removal of existing pavement and replacement with non-reinforced portland cement concrete pavement on Ed Hand Highway from Walnut Street to the south approach slab of the Vermilion River Bridge in Oglesby. Completion Date September 15, 2003.

122. Grundy County, CH 29, District 3, Contract No. 87253, 9 miles of bituminous resurfacing of County Highway 29 from east of IL 47 to Will County Line, 4 miles north of Coal City. 30 Working Days.

123. LaSalle County, CH 33, District 3, Contract No. 87254, 9.07 miles of bituminous resurfacing of CH 33 from CH 43 easterly to IL 23, 2 miles north of Ottawa. 25 Working Days.

124. Knox County, CH 37, District 4, Contract No. 89281, 4.3 miles of bituminous surface course, aggregate shoulders, guardrail removal, pavement markings and other collateral work on CH 37 from Warren County line to Henderson. 25 Working Days.

125. Fulton County, Chestnut St., District 4, Contract No. 89287, 1.16 miles of bituminous resurfacing, milling, area reflective crack control striping, concrete sidewalk R&R, CCC&G, concrete patching on Chestnut Street from 11th Avenue to eastern city limits of Canton. 35 Working Days.

126. Knox County, Losey St, District 4, Contract No. 89289, 0.492 mile bituminous surface, milling, striping, storm sewer, inlets, concrete sidewalk and combination curb and gutter on Losey Street from Ruby Street to Henderson Street in Galesburg. 30 Working Days.

127. Fulton County, CH 17, District 4, Contract No. 89290, 7.064 miles of bituminous surfacing, striping, aggregate base course widening, and guardrail on CH 17 from IL 41 to Ellisville. 55 Working Days.

128. Mercer County, CH 24, District 4, Contract No. 89291, 0.972 mile of bituminous surfacing, striping, aggregate shoulders, bituminous surface removal-butt joints CH24 from US 67 to Matherville. 15 Working Days.

129. Macon County, CH 27, District 5, Contract No. 91288, 3.5 miles of resurfacing, aggregate shoulders and incidental work from FAS Route 631 to FAS Route 556. 40 Working Days.

130. Mason County, CH 14, District 6, Contract No. 93345, 4.29 miles resurfacing with aggregate shoulders along CH 14 from Illinois-Midland Railroad south of Manito east to Tazewell County line. 20 Working Days.

131. Sangamon County, Unmarked Route, District 6, Contract No. 93351, Construct a 0.65 mile, 10' wide bituminous concrete bike trail extension and rehabilitate an existing railroad structure on the Lost Bridge Bike Trail from Walnut Street to Community Drive in Rochester. 65 Working Days.

132. Adams County, CH 7, District 6, Contract No. 93352, 7.57 miles resurfacing with aggregate shoulders on CH 7, No Bottom Road, from the city limits north of Quincy to CH 6 west of Ursa. 25 Working Days.

133. Sangamon County, CH 10, District 6, Contract No. 93355, 13.57 miles bituminous concrete resurfacing, aggregate shoulders and miscellaneous work on County Highway 10 from Main Street in Pleasant Plains south to Loami Road (County Highway 40) including the rehabilitation of the bridge over Prairie Creek. 80 Working Days.

134. Fayette County, IL 185, District 7, Contract No. 94781, Pavement patching, bituminous surface removal, bituminous concrete base course widening, bituminous concrete resurfacing, 3 feet aggregate shoulders, and extending and replacing culverts on IL 185 from I-57 in Farina northwest for 10.23 miles. 110 Working Days.

135. White County, IL 1, District 7, Contract No. 94908, 0.9 mile of pavement patching, bituminous surface removal and bituminous concrete resurfacing on IL 1 in Carmi from Neely Drive to east of Country Club Road. 35 Working Days.

136. Jasper County, CH 21 & 6, District 7, Contract No. 95365, 6.5 miles of soil-cement base course on CH 21 and 6 from the Effingham/Jasper county line to Gila. 20 Working Days.

137. Clay County, CH 1, District 7, Contract No. 95371, 1.93 miles of bituminous concrete surface course on CH 1 from the intersection of IL 50 to north of Flora. 20 Working Days.

138. Randolph County, CH 1, District 8, Contract No. 97211, 7.65 miles of bituminous concrete overlay with aggregate wedge shoulders and culvert replacement on Walch Road from Shawneetown Trail to Schuline Road. 40 Working Days.

139. Greene County, CH 4, District 8, Contract No. 97215, intersection reconstruction of IL 267 & CH 4 and bituminous resurfacing of CH 4 from IL 267 to west of FAS Route 740 in Greenfield. 45 Working Days.

140. Jackson County, Park Roads, District 9, Contract No. 98770, Located northwest of Murphysboro the work is at the Paul Ice Recreational Area and at Lake Murphysboro State Park and will consist of resurfacing Paul Ice Road, Cook Road, Leon Winn Memorial Drive, interior parking lots and sidewalks to be surfaced, new lighting, aggregate shoulders, pavement patches and guardrail. 55 Working Days.

141. Massac County, US 45, District 9, Contract No. 98787, 4.63 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing and 2 feet aggregate shoulders on US 45 from east of IL 145 to the Ohio River Bridge in Brookport. 50 Working Days.

142. Saline County, US 45, District 9, Contract No. 98789, 1.49 miles of pavement patching, bituminous concrete resurfacing and 2 feet aggregate shoulders on US 45 approximately 2.5 miles northeast of Eldorado. 15 Working Days.

143. Franklin County, IL 149, District 9, Contract No. 98790, At the intersection of IL 149 and Orient Road in Franklin County, the work will consist of a grade raise and a grade cut and the construction of full depth asphalt pavement, culvert extensions, tree removal, earth excavation, seeding and pavement markings. 55 Working Days.

144. Jackson County, IL 13, District 9, Contract No. 98800, At the intersection of IL 13 and New Era Road in Carbondale the work will consists of bituminous surface removal and bituminous concrete resurfacing. 15 Working Days.

145. Jackson-Saline Counties, IL 13 & US 51, District 9, Contract No. 98806, The work will consists of 0.26 mile of roadway repair due to mine subsidence at the following five locations: (1) on IL 13 east of the Big Muddy River near Murphysboro (2-4) on IL 13 west of Harrisburg and (5) on US 51 north of Desoto. 25 Working Days.

146. Union County, Old US 51, District 9, Contract No. 98808, Pavement patching, bituminous surface removal, bituminous concrete resurfacing, 1 ft bituminous shoulders and 4 ft aggregate shoulders on Old US 51 from 3.1 miles north of Cobden to south of Cobden. 25 Working Days.

147. Jackson County, 11th Street, District 9, Contract No. 98817, 0.45 mile of bituminous surface removal and bituminous concrete resurfacing on Old Bus. Rt. 13 (11th Street) from IL 149 to 14th Street in Murphysbo 15 Working Days.

148. Jackson County, Town Creek Road, District 9, Contract No. 99169, aggregate widening, aggregate shoulders and bituminous resurfacing of Town Creek Road from Grimsby Road to IL 3. 50 Working Days.

149. Jackson County, CH 7, District 9, Contract No. 99180, bituminous resurfacing and installing cold B.A.M. shoulders on Ava Road from six miles northwest Murphysboro northwesterly 5.5 miles. 25 Working Days.

150. Saline County, Main / Barnett, District 9, Contract No. 99181, Construction of a 30 ft wide face to face concrete pavement with integral curb and gutter, including necessary drainage structures on Main and Barnett Streets in Harrisburg. 85 Working Days.

151. Stephenson County, IL 26, District 2, Contract No. 64898, 5.72 miles bituminous concrete surface on IL 26 from south of Orangeville to Cedar Creek and from Wisconsin State line to Oneco Road, north of Orangeville. 35 Working Days.

152. St. Clair County, Old IL 3, District 8, Contract No. 76673, 0.55 mile of pavement patching, bituminous surface removal, bituminous concrete resurfacing and 2 ft aggregate shoulders on Old IL 3 in North Dupo from the Canal Bridge south to the railroad. 30 Working Days.

153. Greene County, CH 2, District 8, Contract No. 97212, replacement of the existing 3 span bridge with a new 5 span precast, prestressed concrete deck beam bridge over Marks Creek 2.5 miles west of IL 267. 75 Working Days.

154. Jackson County, IL 3, District 9, Contract No. 98798, Bridge repairs consisting of joint and bearing replacements and a microsilica concrete overlay on IL 3 over the Missouri Pacific Railroad east of Gorham. 65 Working Days.

155. Franklin County, IL 34, District 9, Contract No. 98813, The replacement of four deteriorated prestressed concrete deck beams and the waterproofing and bituminous surface over the four beams; and removing and re-erecting a portion of the bridge rail on the structure carrying IL 34 over the CNIC railroad 1 mile west of Hanaford. 35 Working Days.

156. Cook County, I-290, District 1, Contract No. 62552, Beam replacement on two existing structures along I-290 at 25th Avenue in Bellwood and California Avenue in Chicago. 25 Working Days.

157. Rock Island County, Port Byron Road, District 2, Contract No. 64915, Replacing the wearing surface, patching the deck, and replacing the expansion joints on the Port Byron Road bridge over Interstate 88 near Hillsdale. 35 Working Days.

158. Henry County, Osco Road, District 2, Contract No. 64922, Replacing the bituminous wearing surface on two structures on Osco Road over Camp Creek and North Branch of Camp Creek located 1.25 miles north of Andover. Completion Date October 03, 2003.

159. Ford County, IL 54, District 3, Contract No. 66088, Removal and replacement of the existing structure with a double 8' x 5' reinforced concrete box culvert carrying IL 54 over an unnamed stream located 0.2 miles north of Guthrie. 30 Working Days.

160. Iroquois County, I-57, District 3, Contract No. 66351, Cleaning and painting the structure at mile marker 272 (Buckley interchange on Interstate 57). 30 Working Days.

161. McLean County, I-55, District 3, Contract No. 66352, Structural steel removal and structural steel repair on the structure carrying TR 539 over Interstate 55, 1.0 mile south of Funks Grove. 30 Working Days.

162. Grundy County, I-55, District 3, Contract No. 66354, Cleaning and painting the structure carrying TR 110 over Interstate 55, 1.0 mile south of IL 47 near Dwight. 30 Working Days.

163. Peoria County, US 150, District 4, Contract No. 68363, Emergency replacement of the two deteriorated concrete deck beams on the US 150 bridge over Kickapoo Creek, three miles west of Kickapoo. 15 Working Days.

164. Sangamon County, Old IL 4, District 6, Contract No. 72408, removal of the existing structure carrying Old IL 4 over a tributary to Lick Creek south of Springfield and the replacement with a double barrell 6' X 9' concrete box culvert. Completion Date October 31, 2003.

165. Adams, IL-Marion, MO Counties, US 24, District 6, Contract No. 72780, installation of controlled ballast and rotating drum debris deflection devices (known as Bridgeshark) on piers 26-31 and 33-36 at Quincy Memorial Bridge carrying US 24 over the Mississippi River at Quincy. 15 Working Days.

166. Sangamon County, IL 29, District 6, Contract No. 72796, installation of controlled ballast and rotating drum debris deflection devices (known as Bridgeshark) on piers 2 and 3 at the IL 29 bridge over the South Fork of the Sangamon River at Rochester. 15 Working Days.

167. Madison County, I-55 (Goshen Road), District 8, Contract No. 76677, bridge deck scarification, a microsilica concrete overlay, and milling and resurfacing of the approach roadways at the structure carrying Goshen Road over I-55 approximately 1 mile south of IL 143 east of Edwardsville. 25 Working Days.

168. St. Clair County, IL 13, District 8, Contract No. 76682, rehabilitation (Hoan Detail Retrofit Repair) of the structure carrying IL 13 over the Kaskaskia River at New Athens. 60 Working Days.

169. Winnebago County, School Street, District 2, Contract No. 85312, replacement of existing superstructure and rehabilitation of existing substructure of the School Street bridge over Kent Creek, west of Kilburn Avenue in Rockford. Completion Date October 10, 2003.

170. Lee County, East Main Street, District 2, Contract No. 85314, Remove single-span bridge and replace with a triple barrel 11' X 7' RC box culvert with approach work on East Main Street over branch of the Green River in Amboy. 75 Working Days.

171. Winnebago County, Coachmen Drive, District 2, Contract No. 85315, 0.10 mile construction with removal and replacement of the bridge carrying Coachman Drive over Keith Creek 0.2 mile north of Guilford Road, including horizontal and vertical alignment roadway work revisions, all in Rockford. 50 Working Days.

172. Carroll County, Eagle Point Road, District 2, Contract No. 85320, Construction of a double 10' x 6' RC box culvert with aggregate approaches carrying CH 21, Eagle Point Road over Eagle Creek, 4 miles Northeast of Milledgeville. 20 Working Days.

173. Livingston County, Unmarked Route, District 3, Contract No. 87237, removal of an existing structure and replacement with a reinforced concrete double box culvert carrying Franklin Street over Gooseberry Creek in Dwight. 70 Working Days.

174. McDonough County, CH 21, District 4, Contract No. 89285, Construction of a 3 span, precast, prestressed concrete deck beam bridge carrying CH 21 over Drowning Fork, 2 miles west of Prairie City. 40 Working Days.

175. Coles County, 4th Street, District 5, Contract No. 91200, replacement and rehabilitation of a precast, pre-stressed concrete deck beam bridge, 285' of composite pavement, 300' of bike trail under the structure, and relocation of the existing sanitary sewers, storm sewers and water mains, carrying 4th Street over Town Branch Creek. Completion Date December 01, 2003.

176. Vermilion County, TR 125, District 5, Contract No. 91281, Removal of existing structure and the construction of a single span, precast, prestressed concrete deck beam bridge, aggregate approaches on Township Road 125 over the Vermilion River two miles northwest of Bismark. 30 Working Days.

177. Morgan County, CH 18, District 6, Contract No. 93347, Construction of a single span precast, prestressed concrete deck beam bridge carrying CH 18 over Apple Creek Tributary 2.5 miles southwest of Waverly. 40 Working Days.

178. Montgomery County, CH 3, District 6, Contract No. 93353, Remove and replace bridge carrying Black Diamond Trail CH 3 over Horse Creek, including 0.48 mile bituminous resurfacing 4.5 miles northeast of Farmersville. 55 Working Days.

179. Brown County, CH 6, District 6, Contract No. 93354, Construction of 2 single span, precast, prestressed concrete deck beam superstructures carrying CH 6 over Wells Fork of Little Missouri Creek and Purpus Creek, 8.5 miles southwest of Mt. Sterling. 25 Working Days.

180. Jefferson County, I-57, District 7, Contract No. 94541, On I-57 south of Mt. Vernon, the improvement will be 1.27 miles in length and consist of substructure widening and superstructure replacement two structures (structure numbers 041-0008 & 0009), removing two structures over the abandoned Missouri Pacific Railroad and the replacement with earth and PCC pavement, new lanes of PCC pavement on the median side, PCC and bituminous shoulders, milling and resurfacing of the existing pavement, guardrail, pipe underdrains and pavement marking. Completion Date November 19, 2004 Plus 15 Working Days.

181. Wayne-Jefferson Counties, TR 4, District 7, Contract No. 95352, Construction of a three span precast, prestressed concrete deck beam bridge carrying TR 4 over Horse Creek, 9 miles northwest of Wayne City. 40 Working Days.

182. White County, TR 41, District 7, Contract No. 95358, bridge removal and replacement and aggregate surface course carrying TR 41 over Little Wabash River 3.5 miles northwest of Crossville. 165 Working Days.

183. Fayette County, CH 3, District 7, Contract No. 95360, replacement and rehabilitation of a precast, prestressed concrete deck beam on CH 3 over Tributary to Suck Creek, 2.5 miles north of Avena. 30 Working Days.

184. Crawford County, TR 315, District 7, Contract No. 95361, bridge removal and replacement, aggregate surface course and other work required to complete the section, 2.0 miles southeast of Hardinville. 30 Working Days.

185. Lawrence-Crawford Counties, TR 5, District 7, Contract No. 95364, Construction of single span, precast, prestressed concrete deck beam bridge carrying TR 5 over unnamed channel one mile north of Birds. 40 Working Days.

186. Jefferson County, CH 18, District 7, Contract No. 95367, bridge replacement and rehabilitation with a precast, prestressed concrete deck beam bridge on CH 18 over the Little Muddy River. 40 Working Days.

187. Jasper County, TR 359, District 7, Contract No. 95368, bridge replacement with a PPC deck beam bridge carrying TR 359 over the Fox River, 1.5 miles west of West Liberty. 35 Working Days.

188. Clay County, CH 10, District 7, Contract No. 95369, Construction of a 3 span precast, prestressed concrete deck beam bridge carrying CH 10 over Buck Creek 2 miles north of Flora. 35 Working Days.

189. Jasper County, TR 127, District 7, Contract No. 95372, bridge replacement with a precast, prestressed concrete deck beam bridge on TR 127 over Crooked Creek 2 miles southeast of Rose Hill. 30 Working Days.

190. Marion County, West Boone St, District 7, Contract No. 95373, removal of a single span bridge and replacing with a single span precast concrete structure, PCC approach roadway, PCC sidewalk, storm sewer and any work necessary to complete the section carrying Boone St. over Town Creek in Salem. 65 Working Days.

191. Clinton County, CH 8, District 8, Contract No. 97204, replacement and rehabilitation of a precast, prestressed concrete deck beam bridge on CH 8 beginning at the west end of Damiansville westerly over it's crossing with Sugar Creek. 70 Working Days.

192. Williamson County, I-57, District 9, Contract No. 98815, Approach pavement resurfacing, bridge deck patching, bridge deck microsilic concrete overlay, and floor drain extensions on the twin structures carrying I-57 over Lake Creek Branch, 4 miles north of Marion. 35 Working Days.

193. Jackson County, Kimmel Bridge Rd, District 9, Contract No. 99177, removal of an existing concrete structure, and constructing a precast concrete bridge over a tributary of Beacoup Creek on CH 15, and all earthwork and related items necessary to complete the project, 3 miles northeast of Murphysboro. 80 Working Days.

194. Pulaski County, TR 117, District 9, Contract No. 99183, Construction of a single span, precast, prestressed concrete deck beam bridge carrying Township Road 117 over tributary of Hess Bayou, 3.5 miles northeast of Mounds City. 20 Working Days.

195. Cook County, IL 131 (Greenbay Rd.), District 1, Contract No. 60880, Traffic signal modernization at IL 131 (Greenbay Road) and Kenilworth Avenue in Kenilworth. 40 Working Days.

196. Cook County, US 45, District 1, Contract No. 62173, Traffic signal modernization along US 45 (Des Plaines River Road) from Holy Family Hospital to Camp McDonald Road in Mount Prospect and Des Plaines. 50 Working Days.

197. Lake County, IL 59, District 1, Contract No. 62555, Traffic signal installation at the intersection of IL 59 and Monavill Road west of Lake Villa. 35 Working Days.

198. Winnebago County, IL 251, District 2, Contract No. 64855, Modernization of the traffic signals at the intersection of IL 251 and Sandy Hollow near Rockford. 30 Working Days.

199. Boone County, US BUS 20, District 2, Contract No. 64856, Modernization of the traffic signals at US Bus 20 and Appleton Road in Belvidere. 30 Working Days.

200. Sangamon-Macoupin Counties, IL 4 & IL 16, District 6, Contract No. 72793, replacement of the existing traffic signal heads with LED signal heads the intersections of IL 4 with Walnut Street in Chatham and at IL 16 with IL 4 in Gillespie. Completion Date November 01, 2003.

201. Christian-Sangamon Counties, IL 29 & IL 16, District 6, Contract No. 72794, LED signal upgrading, upgrade controllers, and interconnect equipment at the intersections of IL 29 with W. Main Street and Walnut Street in Rochester, and at the intersection of IL 16 and Locust Street in Pana. 15 Working Days.

202. Madison County, IL 3, District 8, Contract No. 76650, deep well rehabilitation and construction of well enclosure boxes, piezometers and electrical wiring for 7 pumps located at the IL 3 subway in Venice. 50 Working Days.

203. Various Counties, Various Routes, District 1, Contract No. 44821, Repairing assorted types and widths of pavement markings at various locations. Completion Date June 30, 2004.

204. St. Clair County, I-55/70, District 8, Contract No. 44822, removal of the existing pavement markings and applying polyurea pavement marking lines on I-55/70 in East St. Louis from milepost 3.1 (Exchange Avenue) west to the State Line. Completion Date December 15, 2003.

205. Various Counties, Various Routes, District 9, Contract No. 44823, installation of raised reflective pavement markers, removing reflectors placing new reflectors and removing damaged raised reflective pavement mark castings on various routes in various counties throughout District 9. Completion Date June 30, 2004.

206. Cook-DuPage-Will Counties, Various Routes, District 1, Contract No. 62469, Debris removal for 17 structures at various locations in Cook, DuPage and Will counties. 20 Working Days.

207. Cook County, IL 68 & Barrington Road, District 1, Contract No. 62508, Crack and joint sealing along IL 68 from IL 59 to IL 53 in Barrington Hills and along Barrington Road from IL 59 to IL 62 in Barrington, Inverness, South Barrington and Hoffman Estates. 25 Working Days.

208. Cook County, US 14, District 1, Contract No. 62513, Landscape design along US 14 (Northwest Highway) from Lake-Cook Road to Hicks Road in Barrington, Inverness and Palatine. Completion Date October 31, 2006.

209. Cook County, IL 83, District 1, Contract No. 62563, Storm sewer maintenance along IL 83 from US 14 to Palatine Road in Prospect Heights and Wheeling. 15 Working Days.

210. Cook County, IL 1, District 1, Contract No. 62564, Storm sewer maintenance consisting of cleaning existing storm sewers and drainage structures along IL 1 from 16th Street to Union Avenue in Chicago Heights. 30 Working Days.

211. Cook County, 111th Street, District 1, Contract No. 62571, Storm sewer maintenance along 111th Street from Harlem Avenue to Ridgeland Avenue in Worth. 15 Working Days.

212. Various Counties, Various Routes, District 3, Contract No. 66322, Repairing on a call out basis guardrail, attenuators, fence, etc. along various routes in Ford, Iroquois, Grundy, Livingston, Kankakee, Kendall, LaSalle, McLean, Marshall, Putnam and Woodford counties. Completion Date July 31, 2004.

213. Livingston-Iroquois-McLean Counties, Various Routes, District 3, Contract No. 66344, Storm sewer maintenance consisting of video inspection of storm sewer systems associated with existing pump houses along various routes. 15 Working Days.

214. Grundy County, IL 113, District 3, Contract No. 66345, Storm sewer maintenance along IL 113 from west of Carbon Hill Road to County Line Road in Coal City and Diamond. 15 Working Days.

215. McLean County, I-55, District 3, Contract No. 66366, Installation of a water storage tank and transfer pump station along I-55 at the Funks Grove Rest Area, 4.5 miles north of McLean. Completion Date November 01, 2003.

216. Stark County, IL 17 & IL 40, District 4, Contract No. 68254, Replacement of box culverts, inlet construction and various erosion control measures for 3 locations on IL 17 and IL 40 at Toulon and near Bradford. 15 Working Days.

217. Warren-Knox Counties, US 34, District 4, Contract No. 68326, 6.2 miles of intermittent patching on US 34 from Cameron Road to Main Street in Galesburg. 25 Working Days.

218. Henderson County, IL 116, District 4, Contract No. 68361, Replacement of the storm sewer and inlet along with patching on IL 116 just east of the viaduct east of Media. 15 Working Days.

219. Knox County, Main Street & CH 9, District 4, Contract No. 68362, Removal and replacement of an inlet, installation of a storm sewer and other related work at the intersection of Main Street and CH 9 in East Galesburg. 15 Working Days.

220. Macon County, Business Us 51, District 5, Contract No. 70294, Slope stabilization on Main Street between Decatur Street and Cleveland Street in Decatur. 25 Working Days.

221. Various Counties, Various Routes, District 5, Contract No. 70335, Landscaping on various routes at various locations in Piatt, Champaign, Vermilion and Douglas counties. Completion Date November 15, 2003.

222. Christian County, IL 29, District 6, Contract No. 72285, In Taylorville, storm sewer improvements southeast of the subway on IL 29 (Park Street) at Poplar Street, and riprap improvements at the bridge carrying IL 29 over Flat Branch Creek. 30 Working Days.

223. Pike County, I-72, District 6, Contract No. 72447, 9.75 miles of landscaping along I-72 from north of Hull to the Adams County Line. Completion Date October 15, 2003.

224. Sangamon County, I-72 (EB), District 6, Contract No. 72804, 6.31 miles of pavement patching on the eastbound lanes of I-72 between the Riverton and Illiopolis interchanges 20 Working Days.

225. Sangamon County, IL 4 (Veteran's Parkway), District 6, Contract No. 72833, The planting of 4 feet tall white pine trees at the southeast quadrant of the intersection of Veteran's Parkway with Cider Mill Road and at various locations along Veteran's Parkway between Washington and Jefferson Streets in Springfield. 15 Working Days.

226. Various Counties, Various Routes, District 8, Contract No. 76652, repairing or replacing damaged steel plate beam guardrail and traffic barrier terminals on various routes in various counties throughout District 8. 365 Working Days.

227. Madison-Bond Counties, I-70 & I-270, District 8, Contract No. 76664, cleaning and painting of the structures at the following locations: (1) IL 4 over I-70 northeast of Troy (2) IL 160 over I-70 north of Highland (3) US 40 over I-70, 1.6 miles east of Pocahontas and (4) the dual structures carrying IL 157 over I-270 at Glen Carbon. 100 Working Days.

228. St. Clair-Monroe Counties, I-255, District 8, Contract No. 76671, Located north of Columbia, the removal of silt from the triple box culvert under ramps A, D, E and F of the I-255 and IL 3 interchange; and at the double box culverts under I-255 north of the Monroe/St. Clair County Line. 15 Working Days.

229. Madison County, I-270, District 8, Contract No. 76672, removal of log jams at various piers at the bridge carrying I-270 over the Mississippi River at Granite City. 25 Working Days.

230. Clinton-St. Clair Counties, I-64, District 8, Contract No. 76676, cleaning and painting of the bridges at the following locations: (1) Summerfield Road over I-64 south of Summerfield (2) Reider Road over I-64 east of Shiloh and (3) IL 160 over I-64, 1.3 miles west of Damiansville. 75 Working Days.

231. Madison County, IL 143, District 8, Contract No. 76700, pavement patching on IL 143 1.5 miles east of I-255 under the Missouri Pacific Railroad east of Roxana. 15 Working Days.

232. Adams County, CH 14, District 6, Contract No. 93348, 0.30 mile paved ditch removal and riprap placement for 2002 flood repair on CH14, 0.75 mile north of IL 104 four miles northeast of Kingston. 15 Working Days.

233. Adams County, CH 1, District 6, Contract No. 93349, slope restoration and culvert extension on CH 1, 2.75 miles east of Lima. 25 Working Days.

234. Adams County, CH 48, District 6, Contract No. 93350, 0.76 mile of slope restoration and box culvert extension on CH 48; 6.5 mile east IL 104. 25 Working Days.

235. Various Counties, Various Routes, District 7, Contract No. 94745, Scour mitigation consisting of excavation around bridge piers and streambed to prepare the subgrade, placement of riprap and filter fabric and temporary erosion control measures at eight bridges located on various routes in various counties throughout District 7. 70 Working Days.

236. Jackson-Perry Counties, US 51 & IL 149, District 9, Contract No. 98809, In DuQuoin, inlet replacement on US 51 from IL 152 to High Street and inlet reconstruction on Washington Street. Also included is storm sewer cleaning on IL 149 from 5th Street to 6th Street in Murphysboro. 30 Working Days.

237. Lake County, IL 59, District 1, Contract No. 62437, 0.58 mile of intersection reconstruction including widening, resurfacing, landscaping and new traffic signals on IL 59 at Beach Grove Road, south of Antioch. Completion Date May 14, 2004 Plus 05 Working Days.

238. Cook County, I-80/94/US 6, District 1, Contract No. 62518, 5.63 km temporary widening and shoulder reconstruction along I-80 from west of IL 83 to Burnham Avenue; and I-94 and I-394 from 159th Street to Thornton-Lansing Road, in Lansing and South Holland. Completion Date October 31, 2003 Plus 10 Working Days.

239. Whiteside County, Pilgrim Road, District 2, Contract No. 64654, 9,324 feet of milling and bituminous concrete resurfacing on Pilgrim Road from Coleta to IL 40. 15 Working Days.

240. Bureau-Henry Counties, Unmarked Route, District 2, Contract No. 64801, resurfacing of the parking lots at various locations throughout the Hennepin Canal State Park. 30 Working Days.

241. Carroll County, IL 78, District 2, Contract No. 64910, 7.59 miles of milling and bituminous concrete resurfacing on IL 78 from US 52/IL 64 to Ideal Road near Chadwick. 40 Working Days.

242. Henry County, Cleveland Road & IL 84, District 2, Contract No. 64914, .07 mile of milling and bituminous concrete resurfacing at two railroad crossings, IL 84 and Cleveland Road in Colona. 15 Working Days.

243. Henry County, IL 82, District 2, Contract No. 64916, 0.28 mile of milling and bituminous concrete resurfacing on IL 82 from Ogden Avenue to US 6 in Geneseo 15 Working Days.

244. Henry County, IL 81, District 2, Contract No. 64917, 0.55 mile milling and bituminous concrete resurfacing on IL 81 from Washington Street to Lexington Avenue in Kewanee. 15 Working Days.

245. DuPage County, Unmarked Route, District 1, Contract No. 83635, 0.496 mile of intersection improvements to include channelization, storm sewers, traffic signals, lighting and drainage structures at the intersection of Schick Road/Springfield Drive in Bloomingdale. 65 Working Days.

246. Will County, 111th St, District 1, Contract No. 83687, 1.73 miles of reconstruction, add lanes, storm sewers, curb and gutter, traffic signals and landscaping on 111th Street from IL 59 to Plainfield-Naperville Road. Completion Date June 01, 2004 Plus 10 Working Days.

247. Cook County, St. Charles Rd, District 1, Contract No. 83689, 1.28 miles of reconstructing, resurfacing, widening and highway lighting on St. Charles Road and portions of Wolf Road and Taft Avenue from Interstate 290 to Wolf Road and from St. Charles Road to Proviso Drive in Berkeley. 195 Working Days.

248. Ogle County, Steward Road, District 2, Contract No. 85319, 2.44 miles of resurfacing and aggregate shoulder wedge on Steward Road from IL 251 at Rochelle to the Lee County line. 30 Working Days.

249. Tazewell County, Veterans Road, District 4, Contract No. 89283, 1,255 feet earthwork, bituminous pavement, curb an gutter, storm sewers and traffic signals on Veterans Road from West Jefferson Street north to West Lake Road in Morton. Completion Date June 15, 2004.

250. Tazewell County, Mall Rd, District 4, Contract No. 89292 0.24 mile reconstruction and relocation of Mall Road from 100' west of Towerline Road to Court Street in Pekin. Completion Date January 01, 2004 Plus 15 Working Days.

251. Vermilion County, US 136, District 5, Contract No. 90938, 2.14 km of bituminous concrete widening and resurfacing on US 136 from Collett Street to National Street in Danville. Completion Date November 01, 2004 Plus 10 Working Days.

252. Jefferson County, Wells By-pass, District 7, Contract No. 95339, 1.01 miles of pavement replacement, storm sewer and earthwork along 45th Street from IL 15 south approximately one mile in Mt. Vernon. 115 Working Days.

253. Madison County, Poplar St, District 8, Contract No. 97209, 0.52 mile of widening and resurfacing on Poplar Street at the intersection of US 40 and US 160 in Highland. 115 Working Days.

254. Cook County, I-80/94, District 1, Contract No. 62351, Advance work including grading, drainage and erosion control, tree removal, temporary lighting, for work to be done on I-80/94 (eastbound) and IL 394 in Lansing, South Holland and Thornton. Completion Date November 15, 2003 Plus 05 Working Days.

255. McHenry County, Bay View Lane, District 1, Contract No. 83618, Remove existing 13 span concrete slab bridge and replace with a five span concrete deck beam bridge and improve approaches on Bay View Lane over Pistake Lake in McHenry County. Completion Date November 15, 2004.

256. Effingham County, TR 115, District 7, Contract No. 95366, Construction of a single span, precast, prestressed concrete deck beam bridge carrying TR 115 over Lily Creek, 5 miles west of Effingham. 25 Working Days.

257. Massac, IL-McCracken,-Ky Counties, I-24, District 9, Contract No. 98794, Structural steel repairs to the bridge carrying I-24 over the Ohio River near Metropolis. 140 Working Days.

258. Cook County, Crawford Ave & New Glenview Rd, District 1, Contract No. 62465, Concrete pavement patching along Crawford Avenue from Wilmette Road to Old Glenview Road, and on New Glenview Road from Skokie Boulevard to Ridge Road in Wilmette. 35 Working Days.

259. Cook County, I-90/94 (Dan Ryan Exp.), District 1, Contract No. 62573, 1.95 miles of shoulder removal and replacement, installation of storm sewer, drainage structures and construction of a median cross over with temporary pavement located on I-90/94 (Dan Ryan Expressway) from 65th Street to 47th Street in Chicago. Completion Date October 31, 2003 Plus 05 Working Days.

260. Kane County, IL 25, District 1, Contract No. 62577, Construction of a retaining wall and installation of storm sewer along IL 25 at the intersection with IL 56, in North Aurora. Completion Date December 31, 2003 Plus 05 Working Days.

261. Winnebago County, Various Routes, District 2, Contract No. 64921, Storm sewer maintenance including cleaning of storm sewers and video inspections on various routes in Rockford. 20 Working Days.

262. Hancock County, US 136/IL 336, District 6, Contract No. 72632, Located 2.1 miles east of Carthage on the south side of US 136 the work will consist of the removal of two buildings, removal of trees, aggregate shoulders, remove and re-erect guardrail and backfilling building foundation 15 Working Days.

263. St. Clair County, Unmarked Route, District 8, Contract No. 76636, reconstructing the parking lot and providing landscape work at the Cahokia Courthouse State Historic site located in Cahokia. 15 Working Days.

264. St. Clair County, I-70, District 8, Contract No. 76644, replacing three existing shaft pumps and vertical hollow shaft motors with new submersible pump and motor units, modifying the existing solid state motor starters for compatability with the new pump and motors, at the Bowmann Avenue Pump Station located at Exchange Avenue and 7th Street in East St. Louis. 300 Working Days.

265. Grundy-Livingston Counties, I-55, District 3, Contract No. 66358, Prairie/Forb/Annual flower seeding of five interchanges and two rest areas along I-55 in Grundy and Livingston Counties. Completion Date December 15, 2004.

266. McLean County, US 51 Bus. (NB), District 3, Contract No. 66115, 1.6 miles of milling and bituminous concrete resurfacing on US 51 Business (NB) from Lafayette Avenue to IL 9 (Locust Street) in Bloomington. 35 Working Days.

267. McLean County, OR 51, District 3, Contract No, 66316, bituminous shoulder removal and replacement and guardrail removal and replacement at 7 culvert locations on OR 51 between Heyworth and Randolph. 50 Working Days.

268. Williamson-Pope Counties, IL 37 & IL 146, District 9, Contract No. 98762, 1.34 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing, 1.5 ft bituminous shoulders and 2 ft aggregate shoulders at the following locations: (1) 1.01 miles on IL 37 at Pulleys Mill and (2) 0.33 mile on IL 146 at Watersburg. 30 Working Days.

269. Jackson County, IL 13, District 9, Contract No. 98780, At the intersection of IL 13 and Glenview Drive in Carbondale the improvement will extend 0.2 mile east and west of Glenview Drive on IL 13 and consist of the addition of a third westbound lane and traffic signal modifications. 65 Working Days.

270, Jackson-Perry Counties, US 51, District 9, Contract No. 98763, bituminous resurfacing of approach pavements, bituminous shoulders, concrete repair, bridge deck patching and bridge deck microsilica concrete overlays on the following bridges on US 51: (1) over Collier Creek north of Tamaroa (2) over Half-Mile Creek south of DuQuoin (3) over Six Mile Creek north of Dowell and (4) over a stream in Elkville. 55 Working Days.

271. Cook-Will Counties, Various Routes, District 1, Contract No. 62497, Crack and joint routing and sealing along various routes in Cook and Will Counties. 25 Working Days.

272. Livingston County, Smith Douglas Road, District 3, Contract No. 87242, construction of a double box culvert with 0.27 mile bituminious resurfacing on approach pavement carrying Smith Douglas Road over a tributary to the Vermilion River in Streator.

273. Madison County, IL 255, District 8, Contract No. 76547, construction of a 2 span composite concrete and welded steel plate girder structure to carry Stutz Lane over IL 255 north of Alton.

1A. Palwaukee Municipal Airport, Prospect Heights, Cook County, Construct Southwest Quadrant Taxiway to Hangar 4 & 7; Construct T-Hangar Sitework.

2A. Decatur Airport, Decatur, Macon County, Rehabilitate the South T-Hangar Pavement Area, T-Hangars H,I,J & K.

3A. Southern Illinois Airport, Carbondale, Jackson County, Construct East Access Road.

4A. MidAmerica Airport, Mascoutah, St. Clair County, Construct GA Apron, Phase 2.

5A. Lake in the Hills Airport, Lake in the Hills, McHenry, County, Install PAPI.

6A. Lake in the Hills Airport, Lake in the HillsMcHenry, County, Rehabilitate T-Hangar Taxiways, Phase 1 & 2.

7A. Pontiac Municipal Airport, Pontiac, Livingston County, Parking Lot & Hangar Site Development.

8A. Greater Peoria Regional Airport, Peoria, Peoria County, Rehabilitate & Expand Terminal Parking Lot.

9A. Shelby County Airport, Shelbyville, Shelby County, Rehabilitate Taxiway Pavements.

10A. Lawrenceville-Vincennes Airport, Lawrenceville, Lawrence County, Sitework for SRE Building.

11A. WITHDRAWN

12A. Sparta Community Airport, Sparta, Randolph County, Expand Existing Apron; Remove & Reconstruct T-Hangar Taxiway.

13A. Pinkneyville-DuQuoine Airport, Pinkneyville, Perry County, Rehabilitate MIRL on Runway 18/36.

14A. Peoria Regional Airport, Peoria, Peoria County, Rehabilitate Airfield Security Gates; Rehabilitate Terminal Video & Access Control.

15A. Pekin Municipal Airport, Pekin, Tazewell County, Extend T-Hangar Access Roadway.

16A. Quincy Regional Airport, Quincy, Adams County, General Aviation Apron Expansion.

17A. Fairfield Municipal Airport, Fairfield, Wayne County, Porous Friction Course Overlay On Runway 9/27.

18A. Olney-Noble Airport, Noble, Richland County, Porous Friction Course Overlay On Runway 11/29.

19A. Flora Airport, Flora, Clay County, G.A. Apron Expansion.

20A. Centralia Municipal Airport, Centralia, Marion County, Construct Crosswind Runway 9/27.

21A. Logan County Airport, Lincoln, Logan County, Rehabilitate & Apply A Porous Friction Course To Runway 3/21.

22A. WITHDRAWN

1LR. Woodford County, W.G. Sutton mine relcamation project,The proposed reclamation project is located approximately 3/4 mile north Minonk. The proposed work includes approximately 22,000 cu yds of earth excavation, 34,500 cu yds of mine refuse excavation, installation of a 15 diameter pipe culvert, seeding and soil amendments for approximately 17 acres and the placement of approximately 900 sq yds of erosion control blanket.

2LR. St. Clair County, Lenzburg mine reclamation project, The proposed reclamation project, in the southeastern area of the Village Lenzburg, includes exploratory excavation of three mine openings (852 cu yds of special excavation), demolition and disposal of existing mine structures and ruins, earth and mine refuse excavation (2,250 cu yds) and approximately 2.4 acres of seeding and soil amendments.

1W. Lake County, Grass Lake Road improvements, Project is located on County Highway 18, Grass Lake Road between Bluff Lake Road and Lotus Drive. The project consists of resurfacing 1,326 feet and addition of left and right turn lanes to Grass Lake Road, and applying 24' wide asphalt surface to 1,200 feet of an adjacent side road which has existing aggregate base. Major construction items required for this project are 4,305 cu yds removal and disposal of unsuitable material; 4,740 cu yds borrow excavation; 2,972 sq yds bituminous surface removal 1 1/2" (coldmilling); 2,786 sq yds subbase granular material, Type 12"; 2,055 sq yds aggregate shoulders, Type A, 6"; 1,216 tons bituminous concrete surface course; 1,951 tons bituminous concrete binder course; 7,405 foot thermoplastic pavement marking line, 76 raised reflective pavement marker, and other miscellaneous items.

 

###