ILLINOIS DEPARTMENT OF TRANSPORTATION PAGE: 1 05/16/02 09:40:14 U N I T P R I C E T A B U L A T I O N O F B I D S LETTING DATE: 03/08/2002 LETTING TYPE: SCHEDULED CONTRACT NUMBER: 82581 LETTING ITEM NUMBER: 078 RESPONSIBLE DISTRICT: 01 BIDS LOCKED: Y SECTION: 88-1-Y-N-1 COUNTY: COOK ESTIMATE: -------------------------- SUMMARY OF CONTRACTOR BIDS -------------------------- "AS READ" SUMMATION SUMMATION OF NBR BIDR CONTR COMB ITEM CONTR BIDDER OF BIDDER CALCULATED LOW BIDR CALC BLANK NBR BIDDER NAME GROUP COMB GRP NBR GROUP TOTAL PRICE EXTENSIONS EXTENSIONS BID EXTENSION DIFF BIDS 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. NO ALT 5,279,729.16 5,279,729.17 5,279,729.17 0802 James Cape & Sons Co. NO ALT 4,689,440.78 4,689,440.78 4,689,440.78 3702 Martam Construction Incorporated NO ALT 5,191,783.46 5,191,783.46 5,190,583.46 1,200.00- 4813 Plote Construction, Inc. NO ALT 4,635,334.75 * 4,635,334.75 4,634,734.75 * 600.00- **** TOTAL GROUP NO ALT PAY ITEMS FOR THIS CONTRACT = 236 ---------------------- DETAIL CONTRACTOR BIDS ---------------------- ITEM NBR ITEM DESCRIPTION UNIT OF UNIT BIDDER CALCULATED BIDR CALC BIDR NBR BIDDER NAME QUANTITY MEASURE PRICE EXTENSION EXTENSION EXTENSION DIFF MX030063 STORM SEW WM REQ 300 45.800 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 165.0000 7,557.00 7,557.00 0802 James Cape & Sons Co. 204.1000 9,347.78 9,347.78 3702 Martam Construction Incorporated 224.0000 10,259.20 10,259.20 4813 Plote Construction, Inc. 167.0000 7,648.60 7,648.60 MX030104 STORM SEW WM REQ 600 31.500 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 230.0000 7,245.00 7,245.00 0802 James Cape & Sons Co. 207.8000 6,545.70 6,545.70 3702 Martam Construction Incorporated 362.0000 11,403.00 11,403.00 4813 Plote Construction, Inc. 242.4000 7,635.60 7,635.60 MX030199 TEMP PAVEMENT 1,035.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 36.0000 37,260.00 37,260.00 0802 James Cape & Sons Co. 32.8000 33,948.00 33,948.00 3702 Martam Construction Incorporated 38.0000 39,330.00 39,330.00 4813 Plote Construction, Inc. 40.0000 41,400.00 41,400.00 MX030242 SLEEPER SLAB 55.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 93.8000 5,159.00 5,159.00 0802 James Cape & Sons Co. 100.0000 5,500.00 5,500.00 3702 Martam Construction Incorporated 160.0000 8,800.00 8,800.00 4813 Plote Construction, Inc. 90.0000 4,950.00 4,950.00 MX032073 A CBL 3-1C2 AL MESS W 2,500.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 11.0000 27,500.00 27,500.00 0802 James Cape & Sons Co. 11.0000 27,500.00 27,500.00 3702 Martam Construction Incorporated 5.5000 13,750.00 13,750.00 4813 Plote Construction, Inc. 4.7000 11,750.00 11,750.00 MX032178 TEMP INFO SIGNING 24.600 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 215.0000 5,289.00 5,289.00 0802 James Cape & Sons Co. 215.0000 5,289.00 5,289.00 3702 Martam Construction Incorporated 360.0000 8,856.00 8,856.00 4813 Plote Construction, Inc. 215.0000 5,289.00 5,289.00 MX032232 WATER MAIN REMOV 200 5.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 40.0000 200.00 200.00 0802 James Cape & Sons Co. 107.2000 536.00 536.00 3702 Martam Construction Incorporated 60.0000 300.00 300.00 4813 Plote Construction, Inc. 34.0000 170.00 170.00 MX032233 WATER MAIN REMOV 300 128.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 40.0000 5,120.00 5,120.00 0802 James Cape & Sons Co. 107.2000 13,721.60 13,721.60 3702 Martam Construction Incorporated 60.0000 7,680.00 7,680.00 4813 Plote Construction, Inc. 34.0000 4,352.00 4,352.00 MX032330 TEMPORARY SIGNING 50.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 215.0000 10,750.00 10,750.00 0802 James Cape & Sons Co. 215.0000 10,750.00 10,750.00 3702 Martam Construction Incorporated 320.0000 16,000.00 16,000.00 4813 Plote Construction, Inc. 215.0000 10,750.00 10,750.00 MX032723 PREFORM DETECT LOOP 1,080.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 30.0000 32,400.00 32,400.00 0802 James Cape & Sons Co. 30.0000 32,400.00 32,400.00 3702 Martam Construction Incorporated 55.0000 59,400.00 59,400.00 4813 Plote Construction, Inc. 48.0000 51,840.00 51,840.00 MX032819 ELCBL C TRACER 14 1C 990.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3.0000 2,970.00 2,970.00 0802 James Cape & Sons Co. 3.0000 2,970.00 2,970.00 3702 Martam Construction Incorporated 1.5000 1,485.00 1,485.00 4813 Plote Construction, Inc. 1.2000 1,188.00 1,188.00 MX032920 EXP JT/SLEEPER SLAB 172.500 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 100.3000 17,301.75 17,301.75 0802 James Cape & Sons Co. 70.0000 12,075.00 12,075.00 3702 Martam Construction Incorporated 80.0000 13,800.00 13,800.00 4813 Plote Construction, Inc. 105.0000 18,112.50 18,112.50 MX033172 MA STL ST LIGHT 4.5 2.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 280.0000 560.00 560.00 0802 James Cape & Sons Co. 280.0000 560.00 560.00 3702 Martam Construction Incorporated 650.0000 1,300.00 1,300.00 4813 Plote Construction, Inc. 550.0000 1,100.00 1,100.00 MX250014 SEEDING CL 2A 1,000.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 0.4500 450.00 450.00 0802 James Cape & Sons Co. 3.0000 3,000.00 3,000.00 3702 Martam Construction Incorporated 2.0000 2,000.00 2,000.00 4813 Plote Construction, Inc. 0.2000 200.00 200.00 MX250050 TEMP EROS CONTR SEED 601.900 KG 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 12.0000 7,222.80 7,222.80 0802 James Cape & Sons Co. 6.0000 3,611.40 3,611.40 3702 Martam Construction Incorporated 13.0000 7,824.70 7,824.70 4813 Plote Construction, Inc. 1.0000 601.90 601.90 MX355200 BIT BC SUPER 200 296.600 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 21.6000 6,406.56 6,406.56 0802 James Cape & Sons Co. 16.0000 4,745.60 4,745.60 3702 Martam Construction Incorporated 26.0000 7,711.60 7,711.60 4813 Plote Construction, Inc. 39.6000 11,745.36 11,745.36 MX355250 BIT BC SUPER 250 196.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 28.1000 5,507.60 5,507.60 0802 James Cape & Sons Co. 27.9000 5,468.40 5,468.40 3702 Martam Construction Incorporated 36.0000 7,056.00 7,056.00 4813 Plote Construction, Inc. 54.0000 10,584.00 10,584.00 MX406M20 LEV BIND MM SUPER N70 499.600 M TON 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 50.5000 25,229.80 25,229.80 0802 James Cape & Sons Co. 44.0000 21,982.40 21,982.40 3702 Martam Construction Incorporated 50.0000 24,980.00 24,980.00 4813 Plote Construction, Inc. 69.0000 34,472.40 34,472.40 MX406024 BC SC SUPER "D" N70 759.200 M TON 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 50.5000 38,339.60 38,339.60 0802 James Cape & Sons Co. 42.4000 32,190.08 32,190.08 3702 Martam Construction Incorporated 52.0000 39,478.40 39,478.40 4813 Plote Construction, Inc. 83.0000 63,013.60 63,013.60 MX406900 QC/QA BITUMINOUS 4,011.700 M TON 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3.2000 12,837.44 12,837.44 0802 James Cape & Sons Co. 2.5000 10,029.25 10,029.25 3702 Martam Construction Incorporated 12.0000 48,140.40 48,140.40 4813 Plote Construction, Inc. 7.8000 31,291.26 31,291.26 MX420210 PCC PVT 245 JOINTED 17,420.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 62.5000 1,088,750.00 1,088,750.00 0802 James Cape & Sons Co. 47.6500 830,063.00 830,063.00 3702 Martam Construction Incorporated 49.0000 853,580.00 853,580.00 4813 Plote Construction, Inc. 53.0000 923,260.00 923,260.00 MX420900 QC/QA CONCRETE 6,977.000 CU M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 11.3500 79,188.95 79,188.95 0802 James Cape & Sons Co. 10.0000 69,770.00 69,770.00 3702 Martam Construction Incorporated 8.0000 55,816.00 55,816.00 4813 Plote Construction, Inc. 7.0000 48,839.00 48,839.00 MX824025 ELCBL C RAILRD 14 3C 135.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 4.5000 607.50 607.50 0802 James Cape & Sons Co. 4.5000 607.50 607.50 3702 Martam Construction Incorporated 4.2000 567.00 567.00 4813 Plote Construction, Inc. 3.5000 472.50 472.50 MX824027 ELCBL C GROUND 6 1C 625.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3.3000 2,062.50 2,062.50 0802 James Cape & Sons Co. 3.3000 2,062.50 2,062.50 3702 Martam Construction Incorporated 2.2000 1,375.00 1,375.00 4813 Plote Construction, Inc. 1.9000 1,187.50 1,187.50 MX824030 ELCBL C 20 3C TW SH 455.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3.3000 1,501.50 1,501.50 0802 James Cape & Sons Co. 3.3000 1,501.50 1,501.50 3702 Martam Construction Incorporated 3.7000 1,683.50 1,683.50 4813 Plote Construction, Inc. 3.2000 1,456.00 1,456.00 MX825055 FOCC62.5/125 MM12SM12 1,000.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 12.0000 12,000.00 12,000.00 0802 James Cape & Sons Co. 12.0000 12,000.00 12,000.00 3702 Martam Construction Incorporated 8.0000 8,000.00 8,000.00 4813 Plote Construction, Inc. 7.1000 7,100.00 7,100.00 MX830360 LT P A 15.2MH 2-4.5MA 4.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 2,135.0000 8,540.00 8,540.00 0802 James Cape & Sons Co. 2,135.0000 8,540.00 8,540.00 3702 Martam Construction Incorporated 2,800.0000 11,200.00 11,200.00 4813 Plote Construction, Inc. 2,475.1000 9,900.40 9,900.40 MZ001050 AGG SUBGRADE 300 20,362.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 15.5500 316,629.10 316,629.10 0802 James Cape & Sons Co. 11.6000 236,199.20 236,199.20 3702 Martam Construction Incorporated 12.0000 244,344.00 244,344.00 4813 Plote Construction, Inc. 12.0000 244,344.00 244,344.00 MZ022800 FENCE REMOVAL 172.300 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 18.0000 3,101.40 3,101.40 0802 James Cape & Sons Co. 16.5000 2,842.95 2,842.95 3702 Martam Construction Incorporated 22.0000 3,790.60 3,790.60 4813 Plote Construction, Inc. 16.5000 2,842.95 2,842.95 MZ067200 STEEL CASINGS 250 6.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 575.0000 3,450.00 3,450.00 0802 James Cape & Sons Co. 438.8000 2,632.80 2,632.80 3702 Martam Construction Incorporated 150.0000 900.00 900.00 4813 Plote Construction, Inc. 157.0000 942.00 942.00 MZ067700 STEEL CASINGS 500 5.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 820.0000 4,100.00 4,100.00 0802 James Cape & Sons Co. 540.0000 2,700.00 2,700.00 3702 Martam Construction Incorporated 300.0000 1,500.00 1,500.00 4813 Plote Construction, Inc. 171.2000 856.00 856.00 M2010110 TREE REMOV 6-15 325.000 UNIT 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 9.0000 2,925.00 2,925.00 0802 James Cape & Sons Co. 10.0000 3,250.00 3,250.00 3702 Martam Construction Incorporated 11.0000 3,575.00 3,575.00 4813 Plote Construction, Inc. 8.7500 2,843.75 2,843.75 M2010210 TREE REMOV OVER 15 219.000 UNIT 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 12.0000 2,628.00 2,628.00 0802 James Cape & Sons Co. 13.0000 2,847.00 2,847.00 3702 Martam Construction Incorporated 14.0000 3,066.00 3,066.00 4813 Plote Construction, Inc. 10.7500 2,354.25 2,354.25 M2010500 TREE REMOV HECTARES .345 HA 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 12,355.0000 4,262.48 4,262.48 0802 James Cape & Sons Co. 10,000.0000 3,450.00 3,450.00 3702 Martam Construction Incorporated 15,000.0000 5,175.00 5,175.00 4813 Plote Construction, Inc. 12,200.0000 4,209.00 4,209.00 M2011000 TEMPORARY FENCE 175.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 14.0000 2,450.00 2,450.00 0802 James Cape & Sons Co. 10.0000 1,750.00 1,750.00 3702 Martam Construction Incorporated 10.0000 1,750.00 1,750.00 4813 Plote Construction, Inc. 13.6000 2,380.00 2,380.00 M2020010 EARTH EXCAVATION 16,803.000 CU M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 31.2500 525,093.75 525,093.75 0802 James Cape & Sons Co. 24.6000 413,353.80 413,353.80 3702 Martam Construction Incorporated 24.0000 403,272.00 403,272.00 4813 Plote Construction, Inc. 14.7500 247,844.25 247,844.25 M2050150 EMBANKMENT 1,376.000 CU M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 9.0000 12,384.00 12,384.00 0802 James Cape & Sons Co. 12.1000 16,649.60 16,649.60 3702 Martam Construction Incorporated 12.0000 16,512.00 16,512.00 4813 Plote Construction, Inc. 5.0000 6,880.00 6,880.00 M2070420 POROUS GRAN EMB SUBGR 2,226.000 CU M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 41.0000 91,266.00 91,266.00 0802 James Cape & Sons Co. 33.7000 75,016.20 75,016.20 3702 Martam Construction Incorporated 32.0000 71,232.00 71,232.00 4813 Plote Construction, Inc. 29.2900 65,199.54 65,199.54 M2080150 TRENCH BACKFILL 4,595.400 CU M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 33.0000 151,648.20 151,648.20 0802 James Cape & Sons Co. 33.4000 153,486.36 153,486.36 3702 Martam Construction Incorporated 36.0000 165,434.40 165,434.40 4813 Plote Construction, Inc. 20.0000 91,908.00 91,908.00 M2110100 F & P TOP SOIL 100 12,600.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 2.7000 34,020.00 34,020.00 0802 James Cape & Sons Co. 1.7000 21,420.00 21,420.00 3702 Martam Construction Incorporated 2.6000 32,760.00 32,760.00 4813 Plote Construction, Inc. 1.4500 18,270.00 18,270.00 M2130108 EXPLOR TRENCH 1.8 50.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 32.0000 1,600.00 1,600.00 0802 James Cape & Sons Co. 81.0000 4,050.00 4,050.00 3702 Martam Construction Incorporated 60.0000 3,000.00 3,000.00 4813 Plote Construction, Inc. 43.0000 2,150.00 2,150.00 M2500400 NITROGEN FERT NUTR 89.000 KG 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1.6500 146.85 146.85 0802 James Cape & Sons Co. 2.0000 178.00 178.00 3702 Martam Construction Incorporated 3.0000 267.00 267.00 4813 Plote Construction, Inc. 1.5000 133.50 133.50 M2500500 PHOSPHORUS FERT NUTR 89.000 KG 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1.6500 146.85 146.85 0802 James Cape & Sons Co. 2.0000 178.00 178.00 3702 Martam Construction Incorporated 3.0000 267.00 267.00 4813 Plote Construction, Inc. 1.5000 133.50 133.50 M2500600 POTASSIUM FERT NUTR 89.000 KG 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1.6500 146.85 146.85 0802 James Cape & Sons Co. 2.0000 178.00 178.00 3702 Martam Construction Incorporated 3.0000 267.00 267.00 4813 Plote Construction, Inc. 1.5000 133.50 133.50 M2510630 EROSION CONTR BLANKET 4,000.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1.0500 4,200.00 4,200.00 0802 James Cape & Sons Co. 1.3000 5,200.00 5,200.00 3702 Martam Construction Incorporated 1.5000 6,000.00 6,000.00 4813 Plote Construction, Inc. 1.2300 4,920.00 4,920.00 M2520110 SODDING SALT TOLERANT 8,600.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3.4500 29,670.00 29,670.00 0802 James Cape & Sons Co. 3.6000 30,960.00 30,960.00 3702 Martam Construction Incorporated 4.0000 34,400.00 34,400.00 4813 Plote Construction, Inc. 3.0000 25,800.00 25,800.00 M2520200 SUPPLE WATERING 1,323.000 UNIT 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1.0000 1,323.00 1,323.00 0802 James Cape & Sons Co. 0.0100 13.23 13.23 3702 Martam Construction Incorporated 0.1000 132.30 132.30 4813 Plote Construction, Inc. 5.0000 6,615.00 6,615.00 M2800200 EARTH EX - EROS CONT 145.000 CU M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 26.0000 3,770.00 3,770.00 0802 James Cape & Sons Co. 50.0000 7,250.00 7,250.00 3702 Martam Construction Incorporated 62.0000 8,990.00 8,990.00 4813 Plote Construction, Inc. 50.0000 7,250.00 7,250.00 M2800400 PERIMETER EROS BAR 713.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 7.4000 5,276.20 5,276.20 0802 James Cape & Sons Co. 5.5000 3,921.50 3,921.50 3702 Martam Construction Incorporated 10.0000 7,130.00 7,130.00 4813 Plote Construction, Inc. 4.8000 3,422.40 3,422.40 M2810105 STONE RIPRAP CL A3 27.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 89.0000 2,403.00 2,403.00 0802 James Cape & Sons Co. 48.3000 1,304.10 1,304.10 3702 Martam Construction Incorporated 120.0000 3,240.00 3,240.00 4813 Plote Construction, Inc. 72.0000 1,944.00 1,944.00 M2820100 FILTER FAB FOR RIPRAP 18.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 2.4000 43.20 43.20 0802 James Cape & Sons Co. 10.0000 180.00 180.00 3702 Martam Construction Incorporated 5.0000 90.00 90.00 4813 Plote Construction, Inc. 21.0000 378.00 378.00 M3111100 SUB GRAN MAT B 100 7,378.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 6.0000 44,268.00 44,268.00 0802 James Cape & Sons Co. 3.8000 28,036.40 28,036.40 3702 Martam Construction Incorporated 5.0000 36,890.00 36,890.00 4813 Plote Construction, Inc. 7.0000 51,646.00 51,646.00 M3120100 STAB SUB-BASE 100 16,973.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 9.0000 152,757.00 152,757.00 0802 James Cape & Sons Co. 12.0000 203,676.00 203,676.00 3702 Martam Construction Incorporated 11.0000 186,703.00 186,703.00 4813 Plote Construction, Inc. 15.0000 254,595.00 254,595.00 M3530235 PCC BSE CSE 235 6,973.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 45.4500 316,922.85 316,922.85 0802 James Cape & Sons Co. 43.7000 304,720.10 304,720.10 3702 Martam Construction Incorporated 36.0000 251,028.00 251,028.00 4813 Plote Construction, Inc. 39.0000 271,947.00 271,947.00 M4060200 BIT MATLS PR CT 2.200 M TON 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 378.0000 831.60 831.60 0802 James Cape & Sons Co. 250.0000 550.00 550.00 3702 Martam Construction Incorporated 450.0000 990.00 990.00 4813 Plote Construction, Inc. 925.0000 2,035.00 2,035.00 M4060300 AGG PR CT 9.800 M TON 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 22.0000 215.60 215.60 0802 James Cape & Sons Co. 60.0000 588.00 588.00 3702 Martam Construction Incorporated 20.0000 196.00 196.00 4813 Plote Construction, Inc. 1.0000 9.80 9.80 M4060400 MIX CR JTS FLANGEWYS 2.200 M TON 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 158.0000 347.60 347.60 0802 James Cape & Sons Co. 275.0000 605.00 605.00 3702 Martam Construction Incorporated 600.0000 1,320.00 1,320.00 4813 Plote Construction, Inc. 575.0000 1,265.00 1,265.00 M4060980 BIT SURF REM BUTT JT 136.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 12.0000 1,632.00 1,632.00 0802 James Cape & Sons Co. 12.0000 1,632.00 1,632.00 3702 Martam Construction Incorporated 22.0000 2,992.00 2,992.00 4813 Plote Construction, Inc. 12.6000 1,713.60 1,713.60 M4080400 INCIDENTAL BIT SURF 35.500 M TON 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 72.0000 2,556.00 2,556.00 0802 James Cape & Sons Co. 70.0000 2,485.00 2,485.00 3702 Martam Construction Incorporated 150.0000 5,325.00 5,325.00 4813 Plote Construction, Inc. 120.0000 4,260.00 4,260.00 M4230200 PCC DRIVEWAY PAVT 200 362.100 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 47.0000 17,018.70 17,018.70 0802 James Cape & Sons Co. 43.0000 15,570.30 15,570.30 3702 Martam Construction Incorporated 38.0000 13,759.80 13,759.80 4813 Plote Construction, Inc. 44.8500 16,240.19 16,240.19 M4240125 PC CONC SIDEWALK 125 804.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 40.0000 32,160.00 32,160.00 0802 James Cape & Sons Co. 35.5000 28,542.00 28,542.00 3702 Martam Construction Incorporated 35.0000 28,140.00 28,140.00 4813 Plote Construction, Inc. 34.5000 27,738.00 27,738.00 M4245000 TEMP SIDEWALK 46.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 4.7500 218.50 218.50 0802 James Cape & Sons Co. 10.0000 460.00 460.00 3702 Martam Construction Incorporated 35.0000 1,610.00 1,610.00 4813 Plote Construction, Inc. 12.6000 579.60 579.60 M4401000 BIT SURF REM VAR DP 1,590.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 7.0000 11,130.00 11,130.00 0802 James Cape & Sons Co. 4.7000 7,473.00 7,473.00 3702 Martam Construction Incorporated 7.0000 11,130.00 11,130.00 4813 Plote Construction, Inc. 8.0000 12,720.00 12,720.00 M4402000 PAVEMENT REM 16,504.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 9.5000 156,788.00 156,788.00 0802 James Cape & Sons Co. 9.7000 160,088.80 160,088.80 3702 Martam Construction Incorporated 10.0000 165,040.00 165,040.00 4813 Plote Construction, Inc. 12.0000 198,048.00 198,048.00 M4402010 DRIVE PAVEMENT REM 345.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 9.5000 3,277.50 3,277.50 0802 James Cape & Sons Co. 6.7000 2,311.50 2,311.50 3702 Martam Construction Incorporated 10.0000 3,450.00 3,450.00 4813 Plote Construction, Inc. 8.0000 2,760.00 2,760.00 M4402040 COMB CURB GUTTER REM 397.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 9.8000 3,890.60 3,890.60 0802 James Cape & Sons Co. 7.1000 2,818.70 2,818.70 3702 Martam Construction Incorporated 16.0000 6,352.00 6,352.00 4813 Plote Construction, Inc. 18.0000 7,146.00 7,146.00 M4402050 SIDEWALK REM 185.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1.8000 333.00 333.00 0802 James Cape & Sons Co. 7.1000 1,313.50 1,313.50 3702 Martam Construction Incorporated 10.0000 1,850.00 1,850.00 4813 Plote Construction, Inc. 17.0000 3,145.00 3,145.00 M4402420 MEDIAN REMOVAL 365.500 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 18.0000 6,579.00 6,579.00 0802 James Cape & Sons Co. 13.4000 4,897.70 4,897.70 3702 Martam Construction Incorporated 16.0000 5,848.00 5,848.00 4813 Plote Construction, Inc. 142.0000 51,901.00 51,901.00 M4410100 PAVT REPLACE 118.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 60.0000 7,080.00 7,080.00 0802 James Cape & Sons Co. 46.0000 5,428.00 5,428.00 3702 Martam Construction Incorporated 56.0000 6,608.00 6,608.00 4813 Plote Construction, Inc. 17.0000 2,006.00 2,006.00 M4430020 STRIP REF CR CON TR 1,689.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 2.0000 3,378.00 3,378.00 0802 James Cape & Sons Co. 4.0000 6,756.00 6,756.00 3702 Martam Construction Incorporated 2.0000 3,378.00 3,378.00 4813 Plote Construction, Inc. 1.1500 1,942.35 1,942.35 M5010522 PIPE CULVERT REMOV 125.300 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 33.0000 4,134.90 4,134.90 0802 James Cape & Sons Co. 14.7000 1,841.91 1,841.91 3702 Martam Construction Incorporated 30.0000 3,759.00 3,759.00 4813 Plote Construction, Inc. 23.1000 2,894.43 2,894.43 M542C220 RCP TEE 450P 300R 2.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,500.0000 3,000.00 3,000.00 0802 James Cape & Sons Co. 527.2000 1,054.40 1,054.40 3702 Martam Construction Incorporated 400.0000 800.00 800.00 4813 Plote Construction, Inc. 485.3000 970.60 970.60 M542C228 RCP TEE 600P 300R 3.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,600.0000 4,800.00 4,800.00 0802 James Cape & Sons Co. 647.6000 1,942.80 1,942.80 3702 Martam Construction Incorporated 500.0000 1,500.00 1,500.00 4813 Plote Construction, Inc. 551.3000 1,653.90 1,653.90 M542C236 RCP TEE 750P 300R 3.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,650.0000 4,950.00 4,950.00 0802 James Cape & Sons Co. 720.9000 2,162.70 2,162.70 3702 Martam Construction Incorporated 600.0000 1,800.00 1,800.00 4813 Plote Construction, Inc. 612.0000 1,836.00 1,836.00 M542C428 RCP TEE 600P 450R 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,670.0000 1,670.00 1,670.00 0802 James Cape & Sons Co. 731.7000 731.70 731.70 3702 Martam Construction Incorporated 600.0000 600.00 600.00 4813 Plote Construction, Inc. 612.0000 612.00 612.00 M542E112 PRC FL-END SEC 300 5.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 675.0000 3,375.00 3,375.00 0802 James Cape & Sons Co. 520.3000 2,601.50 2,601.50 3702 Martam Construction Incorporated 500.0000 2,500.00 2,500.00 4813 Plote Construction, Inc. 419.1000 2,095.50 2,095.50 M542E120 PRC FL-END SEC 450 3.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 750.0000 2,250.00 2,250.00 0802 James Cape & Sons Co. 667.7000 2,003.10 2,003.10 3702 Martam Construction Incorporated 600.0000 1,800.00 1,800.00 4813 Plote Construction, Inc. 491.0000 1,473.00 1,473.00 M542E128 PRC FL-END SEC 600 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,450.0000 1,450.00 1,450.00 0802 James Cape & Sons Co. 782.9000 782.90 782.90 3702 Martam Construction Incorporated 900.0000 900.00 900.00 4813 Plote Construction, Inc. 557.0000 557.00 557.00 M542G035 GRAT-C FL END S 600 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 450.0000 450.00 450.00 0802 James Cape & Sons Co. 500.9000 500.90 500.90 3702 Martam Construction Incorporated 500.0000 500.00 500.00 4813 Plote Construction, Inc. 374.0000 374.00 374.00 M542T006 P CUL CL A 1 200 TEM 228.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 53.0000 12,084.00 12,084.00 0802 James Cape & Sons Co. 97.4000 22,207.20 22,207.20 3702 Martam Construction Incorporated 66.0000 15,048.00 15,048.00 4813 Plote Construction, Inc. 105.0000 23,940.00 23,940.00 M5421410 P CUL 1 CS/A CP 300 63.200 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 100.0000 6,320.00 6,320.00 0802 James Cape & Sons Co. 86.6000 5,473.12 5,473.12 3702 Martam Construction Incorporated 82.0000 5,182.40 5,182.40 4813 Plote Construction, Inc. 108.3000 6,844.56 6,844.56 M5502840 SS 1 RCP CL 4 300 434.600 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 99.0000 43,025.40 43,025.40 0802 James Cape & Sons Co. 83.2000 36,158.72 36,158.72 3702 Martam Construction Incorporated 92.0000 39,983.20 39,983.20 4813 Plote Construction, Inc. 74.2000 32,247.32 32,247.32 M5502860 SS 1 RCP CL 4 450 84.700 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 116.0000 9,825.20 9,825.20 0802 James Cape & Sons Co. 143.1000 12,120.57 12,120.57 3702 Martam Construction Incorporated 108.0000 9,147.60 9,147.60 4813 Plote Construction, Inc. 130.2000 11,027.94 11,027.94 M5502880 SS 1 RCP CL 4 600 163.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 132.0000 21,516.00 21,516.00 0802 James Cape & Sons Co. 149.1000 24,303.30 24,303.30 3702 Martam Construction Incorporated 148.0000 24,124.00 24,124.00 4813 Plote Construction, Inc. 150.4000 24,515.20 24,515.20 M5502900 SS 1 RCP CL 3 750 151.900 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 165.0000 25,063.50 25,063.50 0802 James Cape & Sons Co. 158.1000 24,015.39 24,015.39 3702 Martam Construction Incorporated 234.0000 35,544.60 35,544.60 4813 Plote Construction, Inc. 207.3000 31,488.87 31,488.87 M5503050 SS 2 RCP CL 3 300 125.300 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 100.0000 12,530.00 12,530.00 0802 James Cape & Sons Co. 121.6000 15,236.48 15,236.48 3702 Martam Construction Incorporated 102.0000 12,780.60 12,780.60 4813 Plote Construction, Inc. 74.2000 9,297.26 9,297.26 M5503070 SS 2 RCP CL 3 450 173.100 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 115.0000 19,906.50 19,906.50 0802 James Cape & Sons Co. 115.3000 19,958.43 19,958.43 3702 Martam Construction Incorporated 118.0000 20,425.80 20,425.80 4813 Plote Construction, Inc. 129.1000 22,347.21 22,347.21 M5503090 SS 2 RCP CL 3 600 42.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 132.0000 5,544.00 5,544.00 0802 James Cape & Sons Co. 177.7000 7,463.40 7,463.40 3702 Martam Construction Incorporated 158.0000 6,636.00 6,636.00 4813 Plote Construction, Inc. 149.0000 6,258.00 6,258.00 M5503111 SS 2 RCP CL 3 750 336.900 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 166.0000 55,925.40 55,925.40 0802 James Cape & Sons Co. 159.0000 53,567.10 53,567.10 3702 Martam Construction Incorporated 254.0000 85,572.60 85,572.60 4813 Plote Construction, Inc. 207.3000 69,839.37 69,839.37 M5504800 SS CLEANED 127.500 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 33.0000 4,207.50 4,207.50 0802 James Cape & Sons Co. 12.0000 1,530.00 1,530.00 3702 Martam Construction Incorporated 18.0000 2,295.00 2,295.00 4813 Plote Construction, Inc. 9.5000 1,211.25 1,211.25 M5510020 STORM SEWER REM 250 101.500 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 40.0000 4,060.00 4,060.00 0802 James Cape & Sons Co. 56.0000 5,684.00 5,684.00 3702 Martam Construction Incorporated 30.0000 3,045.00 3,045.00 4813 Plote Construction, Inc. 23.0000 2,334.50 2,334.50 M5610430 D I WATER MAIN 300 87.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 181.0000 15,747.00 15,747.00 0802 James Cape & Sons Co. 229.5000 19,966.50 19,966.50 3702 Martam Construction Incorporated 240.0000 20,880.00 20,880.00 4813 Plote Construction, Inc. 202.4000 17,608.80 17,608.80 M5610520 D I WATER MAIN MJ 200 7.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 158.0000 1,106.00 1,106.00 0802 James Cape & Sons Co. 540.0000 3,780.00 3,780.00 3702 Martam Construction Incorporated 320.0000 2,240.00 2,240.00 4813 Plote Construction, Inc. 384.0000 2,688.00 2,688.00 M5610530 D I WATER MAIN MJ 300 50.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 165.0000 8,250.00 8,250.00 0802 James Cape & Sons Co. 405.0000 20,250.00 20,250.00 3702 Martam Construction Incorporated 260.0000 13,000.00 13,000.00 4813 Plote Construction, Inc. 400.4000 20,020.00 20,020.00 M6011005 P UNDR FAB LN TR 100 217.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 50.0000 10,850.00 10,850.00 0802 James Cape & Sons Co. 44.6000 9,678.20 9,678.20 3702 Martam Construction Incorporated 52.0000 11,284.00 11,284.00 4813 Plote Construction, Inc. 50.0000 10,850.00 10,850.00 M6020140 CB A 1.2M D T8G 4.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,350.0000 5,400.00 5,400.00 0802 James Cape & Sons Co. 1,067.9000 4,271.60 4,271.60 3702 Martam Construction Incorporated 1,500.0000 6,000.00 6,000.00 4813 Plote Construction, Inc. 1,565.0000 6,260.00 6,260.00 M6020185 CB A 1.2M D T24F&G 14.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,450.0000 20,300.00 20,300.00 0802 James Cape & Sons Co. 1,134.5000 15,883.00 15,883.00 3702 Martam Construction Incorporated 1,600.0000 22,400.00 22,400.00 4813 Plote Construction, Inc. 1,640.0000 22,960.00 22,960.00 M6021405 MAN A 1.2D T1F OL 2.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,350.0000 2,700.00 2,700.00 0802 James Cape & Sons Co. 1,474.2000 2,948.40 2,948.40 3702 Martam Construction Incorporated 1,500.0000 3,000.00 3,000.00 4813 Plote Construction, Inc. 1,665.1000 3,330.20 3,330.20 M6021410 MAN A 1.2D T1F CL 4.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,350.0000 5,400.00 5,400.00 0802 James Cape & Sons Co. 1,225.8000 4,903.20 4,903.20 3702 Martam Construction Incorporated 1,500.0000 6,000.00 6,000.00 4813 Plote Construction, Inc. 1,665.1000 6,660.40 6,660.40 M6021610 MAN A 1.5D T1F CL 17.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,750.0000 29,750.00 29,750.00 0802 James Cape & Sons Co. 1,625.4000 27,631.80 27,631.80 3702 Martam Construction Incorporated 2,400.0000 40,800.00 40,800.00 4813 Plote Construction, Inc. 2,262.5000 38,462.50 38,462.50 M6021612 MAN A 1.5D T1F CL RP 3.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 5,000.0000 15,000.00 15,000.00 0802 James Cape & Sons Co. 4,067.6000 12,202.80 12,202.80 3702 Martam Construction Incorporated 5,200.0000 15,600.00 15,600.00 4813 Plote Construction, Inc. 4,088.5000 12,265.50 12,265.50 M6024310 VV TA 1.2MD T1F CL 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,350.0000 1,350.00 1,350.00 0802 James Cape & Sons Co. 1,266.3000 1,266.30 1,266.30 3702 Martam Construction Incorporated 1,800.0000 1,800.00 1,800.00 4813 Plote Construction, Inc. 1,860.0000 1,860.00 1,860.00 M6060010 CLASS SI CONC OUTLET 6.000 CU M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 500.0000 3,000.00 3,000.00 0802 James Cape & Sons Co. 700.0000 4,200.00 4,200.00 3702 Martam Construction Incorporated 1,000.0000 6,000.00 6,000.00 4813 Plote Construction, Inc. 352.0000 2,112.00 2,112.00 M6060070 CONC CURB TB 78.700 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 49.3500 3,883.85 3,883.85 0802 James Cape & Sons Co. 65.0000 5,115.50 5,115.50 3702 Martam Construction Incorporated 64.0000 5,036.80 5,036.80 4813 Plote Construction, Inc. 37.8500 2,978.80 2,978.80 M6060500 COMB CC&G TB15.30 320.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 70.7500 22,640.00 22,640.00 0802 James Cape & Sons Co. 49.0000 15,680.00 15,680.00 3702 Martam Construction Incorporated 48.0000 15,360.00 15,360.00 4813 Plote Construction, Inc. 35.2700 11,286.40 11,286.40 M6060700 COMB CC&G TB15.60 2,187.400 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 68.9500 150,821.23 150,821.23 0802 James Cape & Sons Co. 43.0000 94,058.20 94,058.20 3702 Martam Construction Incorporated 52.0000 113,744.80 113,744.80 4813 Plote Construction, Inc. 41.8300 91,498.94 91,498.94 M6060725 COMB CC&G TB15.60 VGF 69.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 88.6000 6,113.40 6,113.40 0802 James Cape & Sons Co. 65.5000 4,519.50 4,519.50 3702 Martam Construction Incorporated 66.0000 4,554.00 4,554.00 4813 Plote Construction, Inc. 41.7600 2,881.44 2,881.44 M6062200 COMB CC&G TM15.30 270.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 69.8000 18,846.00 18,846.00 0802 James Cape & Sons Co. 48.0000 12,960.00 12,960.00 3702 Martam Construction Incorporated 86.0000 23,220.00 23,220.00 4813 Plote Construction, Inc. 35.2400 9,514.80 9,514.80 M6062400 COMB CC&G TM15.60 25.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 78.6000 1,965.00 1,965.00 0802 James Cape & Sons Co. 59.0000 1,475.00 1,475.00 3702 Martam Construction Incorporated 122.0000 3,050.00 3,050.00 4813 Plote Construction, Inc. 41.8200 1,045.50 1,045.50 M6063540 BIT MEDIAN SURF 208.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 23.0000 4,784.00 4,784.00 0802 James Cape & Sons Co. 27.0000 5,616.00 5,616.00 3702 Martam Construction Incorporated 26.0000 5,408.00 5,408.00 4813 Plote Construction, Inc. 52.0000 10,816.00 10,816.00 M6063600 CONC MEDIAN SURF 100 175.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 45.0000 7,875.00 7,875.00 0802 James Cape & Sons Co. 53.0000 9,275.00 9,275.00 3702 Martam Construction Incorporated 36.0000 6,300.00 6,300.00 4813 Plote Construction, Inc. 29.4000 5,145.00 5,145.00 M6064100 CONC MED TSB15.30 146.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 105.0000 15,330.00 15,330.00 0802 James Cape & Sons Co. 96.8000 14,132.80 14,132.80 3702 Martam Construction Incorporated 88.0000 12,848.00 12,848.00 4813 Plote Construction, Inc. 64.7300 9,450.58 9,450.58 M6320030 GUARDRAIL REMOV 75.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 16.0000 1,200.00 1,200.00 0802 James Cape & Sons Co. 11.5000 862.50 862.50 3702 Martam Construction Incorporated 30.0000 2,250.00 2,250.00 4813 Plote Construction, Inc. 11.5000 862.50 862.50 M7030510 PAVT MARK TAPE T3 L&S 29.600 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 42.5000 1,258.00 1,258.00 0802 James Cape & Sons Co. 42.5000 1,258.00 1,258.00 3702 Martam Construction Incorporated 60.0000 1,776.00 1,776.00 4813 Plote Construction, Inc. 42.5000 1,258.00 1,258.00 M7030520 PAVT MARK TAPE T3 100 6,408.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3.4500 22,107.60 22,107.60 0802 James Cape & Sons Co. 3.5000 22,428.00 22,428.00 3702 Martam Construction Incorporated 4.2000 26,913.60 26,913.60 4813 Plote Construction, Inc. 3.4500 22,107.60 22,107.60 M7030540 PAVT MARK TAPE T3 150 268.200 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 4.6000 1,233.72 1,233.72 0802 James Cape & Sons Co. 4.6000 1,233.72 1,233.72 3702 Martam Construction Incorporated 7.2000 1,931.04 1,931.04 4813 Plote Construction, Inc. 4.6000 1,233.72 1,233.72 M7030560 PAVT MARK TAPE T3 300 53.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 10.8500 575.05 575.05 0802 James Cape & Sons Co. 10.9000 577.70 577.70 3702 Martam Construction Incorporated 15.0000 795.00 795.00 4813 Plote Construction, Inc. 10.8500 575.05 575.05 M7030580 PAVT MARK TAPE T3 600 82.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 20.6500 1,693.30 1,693.30 0802 James Cape & Sons Co. 20.7000 1,697.40 1,697.40 3702 Martam Construction Incorporated 30.0000 2,460.00 2,460.00 4813 Plote Construction, Inc. 20.6500 1,693.30 1,693.30 M7031000 WORK ZONE PAVT MK REM 801.600 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 9.7000 7,775.52 7,775.52 0802 James Cape & Sons Co. 9.7000 7,775.52 7,775.52 3702 Martam Construction Incorporated 11.0000 8,817.60 8,817.60 4813 Plote Construction, Inc. 9.7000 7,775.52 7,775.52 M7200100 SIGN PANEL T1 5.710 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 269.0000 1,535.99 1,535.99 0802 James Cape & Sons Co. 269.0000 1,535.99 1,535.99 3702 Martam Construction Incorporated 320.0000 1,827.20 1,827.20 4813 Plote Construction, Inc. 269.0000 1,535.99 1,535.99 M7800100 THPL PVT MK LTR & SYM 48.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 42.0000 2,016.00 2,016.00 0802 James Cape & Sons Co. 28.5000 1,368.00 1,368.00 3702 Martam Construction Incorporated 32.0000 1,536.00 1,536.00 4813 Plote Construction, Inc. 42.0000 2,016.00 2,016.00 M7800105 THPL PVT MK LINE 100 1,308.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1.1800 1,543.44 1,543.44 0802 James Cape & Sons Co. 1.8000 2,354.40 2,354.40 3702 Martam Construction Incorporated 1.4000 1,831.20 1,831.20 4813 Plote Construction, Inc. 1.2000 1,569.60 1,569.60 M7800115 THPL PVT MK LINE 150 361.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3.2400 1,169.64 1,169.64 0802 James Cape & Sons Co. 2.7000 974.70 974.70 3702 Martam Construction Incorporated 2.6000 938.60 938.60 4813 Plote Construction, Inc. 3.2500 1,173.25 1,173.25 M7800125 THPL PVT MK LINE 300 39.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 7.0000 273.00 273.00 0802 James Cape & Sons Co. 5.4000 210.60 210.60 3702 Martam Construction Incorporated 6.0000 234.00 234.00 4813 Plote Construction, Inc. 7.0000 273.00 273.00 M7800140 THPL PVT MK LINE 600 81.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 14.0000 1,134.00 1,134.00 0802 James Cape & Sons Co. 10.8000 874.80 874.80 3702 Martam Construction Incorporated 25.0000 2,025.00 2,025.00 4813 Plote Construction, Inc. 14.0000 1,134.00 1,134.00 M7800200 PT PVT MK LTRS & SYMB 3.390 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 32.2500 109.33 109.33 0802 James Cape & Sons Co. 15.6000 52.88 52.88 3702 Martam Construction Incorporated 28.0000 94.92 94.92 4813 Plote Construction, Inc. 11.8500 40.17 40.17 M7800205 PAINT PVT MK LN 100 3,171.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 0.4600 1,458.66 1,458.66 0802 James Cape & Sons Co. 1.2000 3,805.20 3,805.20 3702 Martam Construction Incorporated 1.0000 3,171.00 3,171.00 4813 Plote Construction, Inc. 0.4600 1,458.66 1,458.66 M7800215 PAINT PVT MK LN 150 84.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 0.8000 67.20 67.20 0802 James Cape & Sons Co. 1.8000 151.20 151.20 3702 Martam Construction Incorporated 2.0000 168.00 168.00 4813 Plote Construction, Inc. 0.8000 67.20 67.20 M7800225 PAINT PVT MK LN 300 33.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1.6000 52.80 52.80 0802 James Cape & Sons Co. 3.6000 118.80 118.80 3702 Martam Construction Incorporated 4.0000 132.00 132.00 4813 Plote Construction, Inc. 1.6000 52.80 52.80 M7800240 PAINT PVT MK LN 600 24.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3.2000 76.80 76.80 0802 James Cape & Sons Co. 7.1000 170.40 170.40 3702 Martam Construction Incorporated 10.0000 240.00 240.00 4813 Plote Construction, Inc. 3.2000 76.80 76.80 M7800600 EPOXY PVT MK LTR-SYM 74.000 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 47.0000 3,478.00 3,478.00 0802 James Cape & Sons Co. 39.3000 2,908.20 2,908.20 3702 Martam Construction Incorporated 66.0000 4,884.00 4,884.00 4813 Plote Construction, Inc. 47.0000 3,478.00 3,478.00 M7800605 EPOXY PVT MK LN 100 1,765.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1.1800 2,082.70 2,082.70 0802 James Cape & Sons Co. 1.9000 3,353.50 3,353.50 3702 Martam Construction Incorporated 3.2000 5,648.00 5,648.00 4813 Plote Construction, Inc. 1.2000 2,118.00 2,118.00 M7800615 EPOXY PVT MK LN 150 550.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1.5400 847.00 847.00 0802 James Cape & Sons Co. 2.8000 1,540.00 1,540.00 3702 Martam Construction Incorporated 5.6000 3,080.00 3,080.00 4813 Plote Construction, Inc. 1.5500 852.50 852.50 M7800620 EPOXY PVT MK LN 200 48.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 4.6200 221.76 221.76 0802 James Cape & Sons Co. 3.7000 177.60 177.60 3702 Martam Construction Incorporated 6.8000 326.40 326.40 4813 Plote Construction, Inc. 4.6000 220.80 220.80 M7800625 EPOXY PVT MK LN 300 89.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 7.0000 623.00 623.00 0802 James Cape & Sons Co. 5.7000 507.30 507.30 3702 Martam Construction Incorporated 9.0000 801.00 801.00 4813 Plote Construction, Inc. 7.0000 623.00 623.00 M7800630 EPOXY PVT MK LN 400 65.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 9.2400 600.60 600.60 0802 James Cape & Sons Co. 11.7000 760.50 760.50 3702 Martam Construction Incorporated 10.6000 689.00 689.00 4813 Plote Construction, Inc. 9.2500 601.25 601.25 M7800640 EPOXY PVT MK LN 600 111.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 14.0000 1,554.00 1,554.00 0802 James Cape & Sons Co. 22.0000 2,442.00 2,442.00 3702 Martam Construction Incorporated 16.0000 1,776.00 1,776.00 4813 Plote Construction, Inc. 14.0000 1,554.00 1,554.00 M7830100 PAVT MARKING REMOVAL 257.500 SQ M 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 11.3000 2,909.75 2,909.75 0802 James Cape & Sons Co. 16.2000 4,171.50 4,171.50 3702 Martam Construction Incorporated 22.0000 5,665.00 5,665.00 4813 Plote Construction, Inc. 11.3000 2,909.75 2,909.75 M8010115 GROUND ROD 16 X 3.0 36.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 80.0000 2,880.00 2,880.00 0802 James Cape & Sons Co. 80.0000 2,880.00 2,880.00 3702 Martam Construction Incorporated 100.0000 3,600.00 3,600.00 4813 Plote Construction, Inc. 80.2000 2,887.20 2,887.20 M8100060 CON T 50 GALVS 620.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 23.0000 14,260.00 14,260.00 0802 James Cape & Sons Co. 23.0000 14,260.00 14,260.00 3702 Martam Construction Incorporated 36.0000 22,320.00 22,320.00 4813 Plote Construction, Inc. 32.6000 20,212.00 20,212.00 M8100070 CON T 65 GALVS 100.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 32.0000 3,200.00 3,200.00 0802 James Cape & Sons Co. 32.0000 3,200.00 3,200.00 3702 Martam Construction Incorporated 45.0000 4,500.00 4,500.00 4813 Plote Construction, Inc. 38.5000 3,850.00 3,850.00 M8100080 CON T 75 GALVS 90.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 40.0000 3,600.00 3,600.00 0802 James Cape & Sons Co. 40.0000 3,600.00 3,600.00 3702 Martam Construction Incorporated 50.0000 4,500.00 4,500.00 4813 Plote Construction, Inc. 42.7000 3,843.00 3,843.00 M8100100 CON T 100 GALVS 145.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 53.0000 7,685.00 7,685.00 0802 James Cape & Sons Co. 53.0000 7,685.00 7,685.00 3702 Martam Construction Incorporated 70.0000 10,150.00 10,150.00 4813 Plote Construction, Inc. 58.1000 8,424.50 8,424.50 M8100110 CON T 125 GALVS 10.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 79.0000 790.00 790.00 0802 James Cape & Sons Co. 79.0000 790.00 790.00 3702 Martam Construction Incorporated 110.0000 1,100.00 1,100.00 4813 Plote Construction, Inc. 87.4000 874.00 874.00 M8101050 CON P 50 GALVS 100.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 47.0000 4,700.00 4,700.00 0802 James Cape & Sons Co. 47.0000 4,700.00 4,700.00 3702 Martam Construction Incorporated 55.0000 5,500.00 5,500.00 4813 Plote Construction, Inc. 44.7000 4,470.00 4,470.00 M8101070 CON P 75 GALVS 232.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 53.0000 12,296.00 12,296.00 0802 James Cape & Sons Co. 53.0000 12,296.00 12,296.00 3702 Martam Construction Incorporated 75.0000 17,400.00 17,400.00 4813 Plote Construction, Inc. 67.3000 15,613.60 15,613.60 M8101090 CON P 100 GALVS 235.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 79.0000 18,565.00 18,565.00 0802 James Cape & Sons Co. 79.0000 18,565.00 18,565.00 3702 Martam Construction Incorporated 95.0000 22,325.00 22,325.00 4813 Plote Construction, Inc. 84.1000 19,763.50 19,763.50 M8101100 CON P 125 GALVS 40.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 106.0000 4,240.00 4,240.00 0802 James Cape & Sons Co. 106.0000 4,240.00 4,240.00 3702 Martam Construction Incorporated 130.0000 5,200.00 5,200.00 4813 Plote Construction, Inc. 110.2000 4,408.00 4,408.00 M8210400 UD 3#4 #6G EPRRHW 30 3,000.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 11.4000 34,200.00 34,200.00 0802 James Cape & Sons Co. 11.4000 34,200.00 34,200.00 3702 Martam Construction Incorporated 15.0000 45,000.00 45,000.00 4813 Plote Construction, Inc. 13.3000 39,900.00 39,900.00 M8220070 EC C XLP USE 1C 1/0 200.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 10.5000 2,100.00 2,100.00 0802 James Cape & Sons Co. 10.5000 2,100.00 2,100.00 3702 Martam Construction Incorporated 6.0000 1,200.00 1,200.00 4813 Plote Construction, Inc. 5.0000 1,000.00 1,000.00 M8241220 ELCBL C SIGNAL 14 3C 345.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3.3000 1,138.50 1,138.50 0802 James Cape & Sons Co. 3.3000 1,138.50 1,138.50 3702 Martam Construction Incorporated 3.0000 1,035.00 1,035.00 4813 Plote Construction, Inc. 2.4000 828.00 828.00 M8241240 ELCBL C SIGNAL 14 5C 2,605.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3.5000 9,117.50 9,117.50 0802 James Cape & Sons Co. 3.5000 9,117.50 9,117.50 3702 Martam Construction Incorporated 3.2000 8,336.00 8,336.00 4813 Plote Construction, Inc. 2.8000 7,294.00 7,294.00 M8241250 ELCBL C SIGNAL 14 7C 290.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3.5000 1,015.00 1,015.00 0802 James Cape & Sons Co. 3.5000 1,015.00 1,015.00 3702 Martam Construction Incorporated 3.8000 1,102.00 1,102.00 4813 Plote Construction, Inc. 3.3000 957.00 957.00 M8241300 ELCBL C LEAD 14 1PR 1,360.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3.5000 4,760.00 4,760.00 0802 James Cape & Sons Co. 3.5000 4,760.00 4,760.00 3702 Martam Construction Incorporated 2.2000 2,992.00 2,992.00 4813 Plote Construction, Inc. 1.8000 2,448.00 2,448.00 M8241800 ELCBL C SERV 6 2C 105.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 12.0000 1,260.00 1,260.00 0802 James Cape & Sons Co. 12.0000 1,260.00 1,260.00 3702 Martam Construction Incorporated 6.0000 630.00 630.00 4813 Plote Construction, Inc. 5.0000 525.00 525.00 M8301130 LT P A 15.2MH 4.5MA 21.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,860.0000 39,060.00 39,060.00 0802 James Cape & Sons Co. 1,860.0000 39,060.00 39,060.00 3702 Martam Construction Incorporated 2,400.0000 50,400.00 50,400.00 4813 Plote Construction, Inc. 2,066.6000 43,398.60 43,398.60 M8310190 TEMP WP18.30 C4 4.5MA 24.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,200.0000 28,800.00 28,800.00 0802 James Cape & Sons Co. 1,200.0000 28,800.00 28,800.00 3702 Martam Construction Incorporated 1,200.0000 28,800.00 28,800.00 4813 Plote Construction, Inc. 962.0000 23,088.00 23,088.00 M8320470 TS POST GALVS 3.65 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 635.0000 635.00 635.00 0802 James Cape & Sons Co. 635.0000 635.00 635.00 3702 Martam Construction Incorporated 800.0000 800.00 800.00 4813 Plote Construction, Inc. 702.3000 702.30 702.30 M8320490 TS POST GALVS 4.25 4.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 665.0000 2,660.00 2,660.00 0802 James Cape & Sons Co. 665.0000 2,660.00 2,660.00 3702 Martam Construction Incorporated 800.0000 3,200.00 3,200.00 4813 Plote Construction, Inc. 727.6000 2,910.40 2,910.40 M8320510 TS POST GALVS 4.85 2.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 676.0000 1,352.00 1,352.00 0802 James Cape & Sons Co. 676.0000 1,352.00 1,352.00 3702 Martam Construction Incorporated 850.0000 1,700.00 1,700.00 4813 Plote Construction, Inc. 743.7000 1,487.40 1,487.40 M8320530 TS POST GALVS 5.45 2.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 705.0000 1,410.00 1,410.00 0802 James Cape & Sons Co. 705.0000 1,410.00 1,410.00 3702 Martam Construction Incorporated 950.0000 1,900.00 1,900.00 4813 Plote Construction, Inc. 857.8000 1,715.60 1,715.60 M8340035 S MAA & P 7.92 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3,370.0000 3,370.00 3,370.00 0802 James Cape & Sons Co. 3,370.0000 3,370.00 3,370.00 3702 Martam Construction Incorporated 3,000.0000 3,000.00 3,000.00 4813 Plote Construction, Inc. 2,757.3000 2,757.30 2,757.30 M8340040 S MAA & P 8.53 2.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3,380.0000 6,760.00 6,760.00 0802 James Cape & Sons Co. 3,380.0000 6,760.00 6,760.00 3702 Martam Construction Incorporated 3,000.0000 6,000.00 6,000.00 4813 Plote Construction, Inc. 2,757.3000 5,514.60 5,514.60 M8340060 S MAA & P 10.97 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3,825.0000 3,825.00 3,825.00 0802 James Cape & Sons Co. 3,825.0000 3,825.00 3,825.00 3702 Martam Construction Incorporated 3,800.0000 3,800.00 3,800.00 4813 Plote Construction, Inc. 3,522.5000 3,522.50 3,522.50 M8340070 S MAA & P 12.19 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3,900.0000 3,900.00 3,900.00 0802 James Cape & Sons Co. 3,900.0000 3,900.00 3,900.00 3702 Martam Construction Incorporated 3,800.0000 3,800.00 3,800.00 4813 Plote Construction, Inc. 3,586.0000 3,586.00 3,586.00 M8340720 STL COMB MAA&P 6.70 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3,850.0000 3,850.00 3,850.00 0802 James Cape & Sons Co. 3,850.0000 3,850.00 3,850.00 3702 Martam Construction Incorporated 3,800.0000 3,800.00 3,800.00 4813 Plote Construction, Inc. 3,476.3000 3,476.30 3,476.30 M8340735 STL COMB MAA&P 8.53 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 3,940.0000 3,940.00 3,940.00 0802 James Cape & Sons Co. 3,940.0000 3,940.00 3,940.00 3702 Martam Construction Incorporated 4,000.0000 4,000.00 4,000.00 4813 Plote Construction, Inc. 3,666.3000 3,666.30 3,666.30 M8340780 STL COMB MAA&P 15.24 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 5,165.0000 5,165.00 5,165.00 0802 James Cape & Sons Co. 5,165.0000 5,165.00 5,165.00 3702 Martam Construction Incorporated 5,500.0000 5,500.00 5,500.00 4813 Plote Construction, Inc. 4,908.5000 4,908.50 4,908.50 M8360100 LIGHT POLE FDN 600 75.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 396.0000 29,700.00 29,700.00 0802 James Cape & Sons Co. 396.0000 29,700.00 29,700.00 3702 Martam Construction Incorporated 360.0000 27,000.00 27,000.00 4813 Plote Construction, Inc. 316.7000 23,752.50 23,752.50 M8380100 CONC FDN TY A 9.600 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 396.0000 3,801.60 3,801.60 0802 James Cape & Sons Co. 396.0000 3,801.60 3,801.60 3702 Martam Construction Incorporated 520.0000 4,992.00 4,992.00 4813 Plote Construction, Inc. 444.6000 4,268.16 4,268.16 M8380200 CONC FDN TY D 2.400 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 660.0000 1,584.00 1,584.00 0802 James Cape & Sons Co. 660.0000 1,584.00 1,584.00 3702 Martam Construction Incorporated 1,500.0000 3,600.00 3,600.00 4813 Plote Construction, Inc. 1,286.9000 3,088.56 3,088.56 M8380400 CONC FDN TY E 750D 36.800 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 400.0000 14,720.00 14,720.00 0802 James Cape & Sons Co. 400.0000 14,720.00 14,720.00 3702 Martam Construction Incorporated 380.0000 13,984.00 13,984.00 4813 Plote Construction, Inc. 328.0000 12,070.40 12,070.40 M8650100 BKWY DEV TR B 381BC 25.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 400.0000 10,000.00 10,000.00 0802 James Cape & Sons Co. 400.0000 10,000.00 10,000.00 3702 Martam Construction Incorporated 500.0000 12,500.00 12,500.00 4813 Plote Construction, Inc. 422.3000 10,557.50 10,557.50 M8680100 TR & BKFIL F ELECT WK 3,943.000 METER 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 5.0000 19,715.00 19,715.00 0802 James Cape & Sons Co. 5.0000 19,715.00 19,715.00 3702 Martam Construction Incorporated 9.2000 36,275.60 36,275.60 4813 Plote Construction, Inc. 8.1000 31,938.30 31,938.30 XX002112 TEMP LUM SV HR MT 400 24.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 395.0000 9,480.00 9,480.00 0802 James Cape & Sons Co. 395.0000 9,480.00 9,480.00 3702 Martam Construction Incorporated 360.0000 8,640.00 8,640.00 4813 Plote Construction, Inc. 319.5000 7,668.00 7,668.00 XX002113 TEMP LIGHT CONTROLLER 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 4,200.0000 4,200.00 4,200.00 0802 James Cape & Sons Co. 4,200.0000 4,200.00 4,200.00 3702 Martam Construction Incorporated 1,800.0000 1,800.00 1,800.00 4813 Plote Construction, Inc. 1,539.6000 1,539.60 1,539.60 XX003011 REM EX LIGHTING CONTR 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 410.0000 410.00 410.00 0802 James Cape & Sons Co. 400.0000 400.00 400.00 3702 Martam Construction Incorporated 300.0000 300.00 300.00 4813 Plote Construction, Inc. 254.0000 254.00 254.00 XX003451 LIGHT CONTR PAD MOUNT 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 4,900.0000 4,900.00 4,900.00 0802 James Cape & Sons Co. 4,900.0000 4,900.00 4,900.00 3702 Martam Construction Incorporated 7,200.0000 7,200.00 7,200.00 4813 Plote Construction, Inc. 6,204.8000 6,204.80 6,204.80 X0321193 TEMP CATCH BASINS 14.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,550.0000 21,700.00 21,700.00 0802 James Cape & Sons Co. 1,755.0000 24,570.00 24,570.00 3702 Martam Construction Incorporated 2,600.0000 36,400.00 36,400.00 4813 Plote Construction, Inc. 1,501.0000 21,014.00 21,014.00 X0323410 TRIANGULAR SILT DIKE 4.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 115.0000 460.00 460.00 0802 James Cape & Sons Co. 100.0000 400.00 400.00 3702 Martam Construction Incorporated 200.0000 800.00 800.00 4813 Plote Construction, Inc. 100.0000 400.00 400.00 X0323426 SED CONT DR ST INL CL 62.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 325.0000 20,150.00 20,150.00 0802 James Cape & Sons Co. 50.0000 3,100.00 3,100.00 3702 Martam Construction Incorporated 50.0000 3,100.00 3,100.00 4813 Plote Construction, Inc. 110.0000 6,820.00 6,820.00 X0323427 SED CONT DR ST INL FL 62.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 325.0000 20,150.00 20,150.00 0802 James Cape & Sons Co. 200.0000 12,400.00 12,400.00 3702 Martam Construction Incorporated 150.0000 9,300.00 9,300.00 4813 Plote Construction, Inc. 50.0000 3,100.00 3,100.00 X0323636 SH LED 1F 3S CANT MT 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 875.0000 875.00 875.00 0802 James Cape & Sons Co. 875.0000 875.00 875.00 3702 Martam Construction Incorporated 2,200.0000 2,200.00 2,200.00 4813 Plote Construction, Inc. 1,905.0000 1,905.00 1,905.00 X0323637 R&R TIMBER RETAIN WAL 1.000 L SUM 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 5,500.0000 5,500.00 5,500.00 0802 James Cape & Sons Co. 5,000.0000 5,000.00 5,000.00 3702 Martam Construction Incorporated 4,000.0000 4,000.00 4,000.00 4813 Plote Construction, Inc. 4,000.0000 4,000.00 4,000.00 X2800100 TEMP DITCH CHK ROL EX 4.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 80.0000 320.00 320.00 0802 James Cape & Sons Co. 100.0000 400.00 400.00 3702 Martam Construction Incorporated 150.0000 600.00 600.00 4813 Plote Construction, Inc. 75.0000 300.00 300.00 X4021000 TEMP ACCESS- PRIV ENT 4.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 550.0000 2,200.00 2,200.00 0802 James Cape & Sons Co. 600.0000 2,400.00 2,400.00 3702 Martam Construction Incorporated 600.0000 2,400.00 2,400.00 4813 Plote Construction, Inc. 400.0000 1,600.00 1,600.00 X4022000 TEMP ACCESS- COM ENT 2.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 750.0000 1,500.00 1,500.00 0802 James Cape & Sons Co. 1,700.0000 3,400.00 3,400.00 3702 Martam Construction Incorporated 800.0000 1,600.00 1,600.00 4813 Plote Construction, Inc. 1,300.0000 2,600.00 2,600.00 X4023000 TEMP ACCESS- ROAD 7.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 2,500.0000 17,500.00 17,500.00 0802 James Cape & Sons Co. 2,200.0000 15,400.00 15,400.00 3702 Martam Construction Incorporated 800.0000 5,600.00 5,600.00 4813 Plote Construction, Inc. 1,400.0000 9,800.00 9,800.00 X7015000 CHANGEABLE MESSAGE SN 8.000 CAL MO 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 100.0000 800.00 800.00 0802 James Cape & Sons Co. 100.0000 800.00 800.00 3702 Martam Construction Incorporated 3,200.0000 25,600.00 25,600.00 4813 Plote Construction, Inc. 100.0000 800.00 800.00 X8400020 SH LED 1F 3S MAM 13.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 810.0000 10,530.00 10,530.00 0802 James Cape & Sons Co. 810.0000 10,530.00 10,530.00 3702 Martam Construction Incorporated 1,100.0000 14,300.00 14,300.00 4813 Plote Construction, Inc. 918.4000 11,939.20 11,939.20 X8400035 SH LED 1F 3S BM 5.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 760.0000 3,800.00 3,800.00 0802 James Cape & Sons Co. 760.0000 3,800.00 3,800.00 3702 Martam Construction Incorporated 1,050.0000 5,250.00 5,250.00 4813 Plote Construction, Inc. 870.1000 4,350.50 4,350.50 X8400045 SH LED 1F 5S MAM 2.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,163.0000 2,326.00 2,326.00 0802 James Cape & Sons Co. 1,163.0000 2,326.00 2,326.00 3702 Martam Construction Incorporated 1,700.0000 3,400.00 3,400.00 4813 Plote Construction, Inc. 1,395.9000 2,791.80 2,791.80 X8400060 SH LED 2F 3S BM 4.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,453.0000 5,812.00 5,812.00 0802 James Cape & Sons Co. 1,453.0000 5,812.00 5,812.00 3702 Martam Construction Incorporated 2,000.0000 8,000.00 8,000.00 4813 Plote Construction, Inc. 1,709.7000 6,838.80 6,838.80 X8400070 SH LED 2F 5S BM 2.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 2,150.0000 4,300.00 4,300.00 0802 James Cape & Sons Co. 2,150.0000 4,300.00 4,300.00 3702 Martam Construction Incorporated 3,000.0000 6,000.00 6,000.00 4813 Plote Construction, Inc. 2,566.7000 5,133.40 5,133.40 X8490015 TEMP TR SIG INTER SYS 1.000 L SUM 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 17,500.0000 17,500.00 17,500.00 0802 James Cape & Sons Co. 17,500.0000 17,500.00 17,500.00 3702 Martam Construction Incorporated 13,000.0000 13,000.00 13,000.00 4813 Plote Construction, Inc. 10,525.4000 10,525.40 10,525.40 X8670015 SERV INSTALL POLE MT 2.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,600.0000 3,200.00 3,200.00 0802 James Cape & Sons Co. 1,600.0000 3,200.00 3,200.00 3702 Martam Construction Incorporated 980.0000 1,960.00 1,960.00 4813 Plote Construction, Inc. 827.6000 1,655.20 1,655.20 X8710110 REM LT POLE FDN PART 13.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 300.0000 3,900.00 3,900.00 0802 James Cape & Sons Co. 300.0000 3,900.00 3,900.00 3702 Martam Construction Incorporated 180.0000 2,340.00 2,340.00 4813 Plote Construction, Inc. 152.4000 1,981.20 1,981.20 Z0013798 CONSTRUCTION LAYOUT 1.000 L SUM 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 85,000.0000 85,000.00 85,000.00 0802 James Cape & Sons Co. 70,000.0000 70,000.00 70,000.00 3702 Martam Construction Incorporated 50,000.0000 50,000.00 50,000.00 4813 Plote Construction, Inc. 42,000.0000 42,000.00 42,000.00 Z0018500 DRAINAGE STR CLEANED 5.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 100.0000 500.00 500.00 0802 James Cape & Sons Co. 250.0000 1,250.00 1,250.00 3702 Martam Construction Incorporated 300.0000 1,500.00 1,500.00 4813 Plote Construction, Inc. 169.0000 845.00 845.00 Z0048665 RR PROT LIABILITY INS 1.000 L SUM 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 5,000.0000 5,000.00 5,000.00 0802 James Cape & Sons Co. 4,000.0000 4,000.00 4,000.00 3702 Martam Construction Incorporated 5,000.0000 5,000.00 5,000.00 4813 Plote Construction, Inc. 2,000.0000 2,000.00 2,000.00 Z0076600 TRAINEES 1,500.000 HOUR 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 0.8000 1,200.00 1,200.00 0802 James Cape & Sons Co. 0.8000 1,200.00 1,200.00 3702 Martam Construction Incorporated 0.8000 1,200.00 1,200.00 4813 Plote Construction, Inc. 0.8000 1,200.00 1,200.00 28000500 INLET & PIPE PROTECT 62.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 65.0000 4,030.00 4,030.00 0802 James Cape & Sons Co. 45.0000 2,790.00 2,790.00 3702 Martam Construction Incorporated 80.0000 4,960.00 4,960.00 4813 Plote Construction, Inc. 65.0000 4,030.00 4,030.00 60208240 CB TC T24F&G 5.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 750.0000 3,750.00 3,750.00 0802 James Cape & Sons Co. 769.5000 3,847.50 3,847.50 3702 Martam Construction Incorporated 1,000.0000 5,000.00 5,000.00 4813 Plote Construction, Inc. 848.0000 4,240.00 4,240.00 60237470 INLETS TA T24F&G 12.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 800.0000 9,600.00 9,600.00 0802 James Cape & Sons Co. 857.3000 10,287.60 10,287.60 3702 Martam Construction Incorporated 800.0000 9,600.00 9,600.00 4813 Plote Construction, Inc. 697.3000 8,367.60 8,367.60 60265700 VV ADJUST 10.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 325.0000 3,250.00 3,250.00 0802 James Cape & Sons Co. 405.0000 4,050.00 4,050.00 3702 Martam Construction Incorporated 350.0000 3,500.00 3,500.00 4813 Plote Construction, Inc. 174.0000 1,740.00 1,740.00 60266500 VV REMOVED 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 350.0000 350.00 350.00 0802 James Cape & Sons Co. 266.0000 266.00 266.00 3702 Martam Construction Incorporated 500.0000 500.00 500.00 4813 Plote Construction, Inc. 115.5000 115.50 115.50 60500040 REMOV MANHOLES 6.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 350.0000 2,100.00 2,100.00 0802 James Cape & Sons Co. 498.2000 2,989.20 2,989.20 3702 Martam Construction Incorporated 500.0000 3,000.00 3,000.00 4813 Plote Construction, Inc. 115.5000 693.00 693.00 60500060 REMOV INLETS 3.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 350.0000 1,050.00 1,050.00 0802 James Cape & Sons Co. 295.7000 887.10 887.10 3702 Martam Construction Incorporated 200.0000 600.00 600.00 4813 Plote Construction, Inc. 94.0000 282.00 282.00 67000600 ENGR FIELD LAB 16.000 CAL MO 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 100.0000 1,600.00 1,600.00 0802 James Cape & Sons Co. 1,000.0000 16,000.00 16,000.00 3702 Martam Construction Incorporated 3,300.0000 52,800.00 52,800.00 4813 Plote Construction, Inc. 1,000.0000 16,000.00 16,000.00 67100100 MOBILIZATION 1.000 L SUM 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 310,000.0000 310,000.00 310,000.00 0802 James Cape & Sons Co. 282,497.5000 282,497.50 282,497.50 3702 Martam Construction Incorporated 270,000.0000 270,000.00 270,000.00 4813 Plote Construction, Inc. 277,600.0000 277,600.00 277,600.00 70101800 TRAF CONT & PROT SPL 1.000 L SUM 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 150,000.0000 150,000.00 150,000.00 0802 James Cape & Sons Co. 146,050.0000 146,050.00 146,050.00 3702 Martam Construction Incorporated 130,000.0000 130,000.00 130,000.00 4813 Plote Construction, Inc. 140,000.0000 140,000.00 140,000.00 70103815 TR CONT SURVEILLANCE 373.000 CAL DA 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1.0000 373.00 373.00 0802 James Cape & Sons Co. 1.0000 373.00 373.00 3702 Martam Construction Incorporated 660.0000 246,180.00 246,180.00 4813 Plote Construction, Inc. 1.0000 373.00 373.00 78100100 RAISED REFL PAVT MKR 358.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 22.0000 7,876.00 7,876.00 0802 James Cape & Sons Co. 22.5000 8,055.00 8,055.00 3702 Martam Construction Incorporated 32.0000 11,456.00 11,456.00 4813 Plote Construction, Inc. 22.0000 7,876.00 7,876.00 78100200 TEMP RAIS REF PVT MKR 666.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 8.0000 5,328.00 5,328.00 0802 James Cape & Sons Co. 15.5000 10,323.00 10,323.00 3702 Martam Construction Incorporated 26.0000 17,316.00 17,316.00 4813 Plote Construction, Inc. 8.0000 5,328.00 5,328.00 78300200 RAISED REF PVT MK REM 30.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 10.0000 300.00 300.00 0802 James Cape & Sons Co. 41.7000 1,251.00 1,251.00 3702 Martam Construction Incorporated 8.0000 240.00 240.00 4813 Plote Construction, Inc. 18.0000 540.00 540.00 81400100 HANDHOLE 15.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 750.0000 11,250.00 11,250.00 0802 James Cape & Sons Co. 750.0000 11,250.00 11,250.00 3702 Martam Construction Incorporated 900.0000 13,500.00 13,500.00 4813 Plote Construction, Inc. 738.0000 11,070.00 11,070.00 81400200 HD HANDHOLE 5.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 900.0000 4,500.00 4,500.00 0802 James Cape & Sons Co. 900.0000 4,500.00 4,500.00 3702 Martam Construction Incorporated 1,200.0000 6,000.00 6,000.00 4813 Plote Construction, Inc. 1,049.0000 5,245.00 5,245.00 81400300 DBL HANDHOLE 2.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,300.0000 2,600.00 2,600.00 0802 James Cape & Sons Co. 1,300.0000 2,600.00 2,600.00 3702 Martam Construction Incorporated 1,500.0000 3,000.00 3,000.00 4813 Plote Construction, Inc. 1,306.6000 2,613.20 2,613.20 83900200 DRILL EX HANDHOLE 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 80.0000 80.00 80.00 0802 James Cape & Sons Co. 80.0000 80.00 80.00 3702 Martam Construction Incorporated 180.0000 180.00 180.00 4813 Plote Construction, Inc. 152.4000 152.40 152.40 84024130 OPSH 1F 3S MAM 2.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 2,100.0000 4,200.00 4,200.00 0802 James Cape & Sons Co. 2,100.0000 4,200.00 4,200.00 3702 Martam Construction Incorporated 3,000.0000 6,000.00 6,000.00 4813 Plote Construction, Inc. 2,414.9000 4,829.80 4,829.80 84200100 TS BACKPLATE 18.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 100.0000 1,800.00 1,800.00 0802 James Cape & Sons Co. 100.0000 1,800.00 1,800.00 3702 Martam Construction Incorporated 120.0000 2,160.00 2,160.00 4813 Plote Construction, Inc. 105.5000 1,899.00 1,899.00 84400400 LUM SV HOR MT 400W 31.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 395.0000 12,245.00 12,245.00 0802 James Cape & Sons Co. 395.0000 12,245.00 12,245.00 3702 Martam Construction Incorporated 380.0000 11,780.00 11,780.00 4813 Plote Construction, Inc. 338.6000 10,496.60 10,496.60 84600100 INDUCTIVE LOOP DETECT 19.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 140.0000 2,660.00 2,660.00 0802 James Cape & Sons Co. 140.0000 2,660.00 2,660.00 3702 Martam Construction Incorporated 180.0000 3,420.00 3,420.00 4813 Plote Construction, Inc. 153.9000 2,924.10 2,924.10 84800200 ILLUM SIGN FIB-OPT 2.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,800.0000 3,600.00 3,600.00 0802 James Cape & Sons Co. 1,800.0000 3,600.00 3,600.00 3702 Martam Construction Incorporated 2,800.0000 5,600.00 5,600.00 4813 Plote Construction, Inc. 2,313.5000 4,627.00 4,627.00 84900100 TEMP TR SIG INSTALL 2.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 30,000.0000 60,000.00 60,000.00 0802 James Cape & Sons Co. 28,000.0000 56,000.00 56,000.00 3702 Martam Construction Incorporated 18,000.0000 36,000.00 36,000.00 4813 Plote Construction, Inc. 15,575.0000 31,150.00 31,150.00 85000200 MAIN EX TR SIG INSTAL 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 750.0000 750.00 750.00 0802 James Cape & Sons Co. 750.0000 750.00 750.00 3702 Martam Construction Incorporated 720.0000 720.00 720.00 4813 Plote Construction, Inc. 660.4000 660.40 660.40 85200200 LIGHT DETECTOR 6.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 615.0000 3,690.00 3,690.00 0802 James Cape & Sons Co. 615.0000 3,690.00 3,690.00 3702 Martam Construction Incorporated 780.0000 4,680.00 4,680.00 4813 Plote Construction, Inc. 673.0000 4,038.00 4,038.00 85200300 LIGHT DETECTOR AMP 2.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,260.0000 2,520.00 2,520.00 0802 James Cape & Sons Co. 1,260.0000 2,520.00 2,520.00 3702 Martam Construction Incorporated 1,600.0000 3,200.00 3,200.00 4813 Plote Construction, Inc. 1,415.4000 2,830.80 2,830.80 85700205 FAC T4 CAB SPL 2.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 9,900.0000 19,800.00 19,800.00 0802 James Cape & Sons Co. 9,900.0000 19,800.00 19,800.00 3702 Martam Construction Incorporated 13,000.0000 26,000.00 26,000.00 4813 Plote Construction, Inc. 10,713.9000 21,427.80 21,427.80 86400100 TRANSCEIVER - FIB OPT 2.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,950.0000 3,900.00 3,900.00 0802 James Cape & Sons Co. 1,950.0000 3,900.00 3,900.00 3702 Martam Construction Incorporated 2,600.0000 5,200.00 5,200.00 4813 Plote Construction, Inc. 2,242.8000 4,485.60 4,485.60 86600100 ELECT SERV INSTALL 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,200.0000 1,200.00 1,200.00 0802 James Cape & Sons Co. 1,200.0000 1,200.00 1,200.00 3702 Martam Construction Incorporated 700.0000 700.00 700.00 4813 Plote Construction, Inc. 639.0000 639.00 639.00 86600200 ELECT UTIL SERV CONN 1.000 L SUM 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 4,000.0000 4,000.00 4,000.00 0802 James Cape & Sons Co. 4,000.0000 4,000.00 4,000.00 3702 Martam Construction Incorporated 4,000.0000 5,200.00 4,000.00 1,200.00- 4813 Plote Construction, Inc. 4,000.0000 4,600.00 4,000.00 600.00- 87100100 REM EX LT UNIT SALV 13.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 280.0000 3,640.00 3,640.00 0802 James Cape & Sons Co. 280.0000 3,640.00 3,640.00 3702 Martam Construction Incorporated 300.0000 3,900.00 3,900.00 4813 Plote Construction, Inc. 254.0000 3,302.00 3,302.00 87302375 REMOV EX TS EQUIP 1.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 1,600.0000 1,600.00 1,600.00 0802 James Cape & Sons Co. 1,600.0000 1,600.00 1,600.00 3702 Martam Construction Incorporated 1,200.0000 1,200.00 1,200.00 4813 Plote Construction, Inc. 1,016.0000 1,016.00 1,016.00 87302380 REMOV EX HANDHOLE 9.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 300.0000 2,700.00 2,700.00 0802 James Cape & Sons Co. 300.0000 2,700.00 2,700.00 3702 Martam Construction Incorporated 40.0000 360.00 360.00 4813 Plote Construction, Inc. 31.8000 286.20 286.20 87302385 REMOV EX CONC FDN 11.000 EACH 0394 Berger Excavating Contractors, Inc. & Alliance Contractors, Inc. 300.0000 3,300.00 3,300.00 0802 James Cape & Sons Co. 300.0000 3,300.00 3,300.00 3702 Martam Construction Incorporated 40.0000 440.00 440.00 4813 Plote Construction, Inc. 31.8000 349.80 349.80