ILLINOIS DEPARTMENT OF TRANSPORTATION PAGE: 1 04/05/02 07:29:57 U N I T P R I C E T A B U L A T I O N O F B I D S LETTING DATE: 03/08/2002 LETTING TYPE: SCHEDULED CONTRACT NUMBER: 66103 LETTING ITEM NUMBER: 084 RESPONSIBLE DISTRICT: 03 BIDS LOCKED: Y SECTION: (28,29)RS-2,I COUNTY: LASALLE LIVINGSTON ESTIMATE: -------------------------- SUMMARY OF CONTRACTOR BIDS -------------------------- "AS READ" SUMMATION SUMMATION OF NBR BIDR CONTR COMB ITEM CONTR BIDDER OF BIDDER CALCULATED LOW BIDR CALC BLANK NBR BIDDER NAME GROUP COMB GRP NBR GROUP TOTAL PRICE EXTENSIONS EXTENSIONS BID EXTENSION DIFF BIDS 4887 Bob Propheter Construction, L.L.C. NO ALT 989,380.46 989,380.46 989,380.46 5765 Streator Asphalt, Inc. NO ALT 829,710.01 * 829,710.03 829,710.03 * 6085 Len Trovero Construction NO ALT 1,005,346.71 1,005,346.71 1,005,346.71 **** TOTAL GROUP NO ALT PAY ITEMS FOR THIS CONTRACT = 83 ---------------------- DETAIL CONTRACTOR BIDS ---------------------- ITEM NBR ITEM DESCRIPTION UNIT OF UNIT BIDDER CALCULATED BIDR CALC BIDR NBR BIDDER NAME QUANTITY MEASURE PRICE EXTENSION EXTENSION EXTENSION DIFF X0932150 CURB & GUT OUTLET SPL 1.000 EACH 4887 Bob Propheter Construction, L.L.C. 1,852.1800 1,852.18 1,852.18 5765 Streator Asphalt, Inc. 540.0000 540.00 540.00 6085 Len Trovero Construction 500.0000 500.00 500.00 X0976500 END SECTIONS REMOVED 3.000 EACH 4887 Bob Propheter Construction, L.L.C. 338.6300 1,015.89 1,015.89 5765 Streator Asphalt, Inc. 80.0000 240.00 240.00 6085 Len Trovero Construction 100.0000 300.00 300.00 X3550510 BIT BC SUPER 8 1/2 396.000 SQ YD 4887 Bob Propheter Construction, L.L.C. 26.8000 10,612.80 10,612.80 5765 Streator Asphalt, Inc. 28.7500 11,385.00 11,385.00 6085 Len Trovero Construction 37.0000 14,652.00 14,652.00 X4066424 BC SC SUPER "D" N50 10,645.000 TON 4887 Bob Propheter Construction, L.L.C. 41.4700 441,448.15 441,448.15 5765 Streator Asphalt, Inc. 36.9000 392,800.50 392,800.50 6085 Len Trovero Construction 37.0000 393,865.00 393,865.00 X4066614 BCBC SUP IL-19.0 N50 56.000 TON 4887 Bob Propheter Construction, L.L.C. 65.7900 3,684.24 3,684.24 5765 Streator Asphalt, Inc. 59.0000 3,304.00 3,304.00 6085 Len Trovero Construction 37.0000 2,072.00 2,072.00 X5428800 CIP RC END SEC 4.000 CU YD 4887 Bob Propheter Construction, L.L.C. 1,852.2000 7,408.80 7,408.80 5765 Streator Asphalt, Inc. 1,200.0000 4,800.00 4,800.00 6085 Len Trovero Construction 950.0000 3,800.00 3,800.00 Z0013825 CONTR LOW-STRENG MATL 267.000 CU YD 4887 Bob Propheter Construction, L.L.C. 91.2200 24,355.74 24,355.74 5765 Streator Asphalt, Inc. 64.5000 17,221.50 17,221.50 6085 Len Trovero Construction 75.0000 20,025.00 20,025.00 Z0055300 RUMBLE STRIP 6.000 EACH 4887 Bob Propheter Construction, L.L.C. 1,541.2900 9,247.74 9,247.74 5765 Streator Asphalt, Inc. 510.0000 3,060.00 3,060.00 6085 Len Trovero Construction 650.0000 3,900.00 3,900.00 20200100 EARTH EXCAVATION 286.000 CU YD 4887 Bob Propheter Construction, L.L.C. 14.3500 4,104.10 4,104.10 5765 Streator Asphalt, Inc. 17.4000 4,976.40 4,976.40 6085 Len Trovero Construction 20.0000 5,720.00 5,720.00 20201200 REM & DISP UNS MATL 57.000 CU YD 4887 Bob Propheter Construction, L.L.C. 15.1100 861.27 861.27 5765 Streator Asphalt, Inc. 10.5000 598.50 598.50 6085 Len Trovero Construction 25.0000 1,425.00 1,425.00 20201450 SUB GRAN MAT A 87.600 CU YD 4887 Bob Propheter Construction, L.L.C. 31.6400 2,771.66 2,771.66 5765 Streator Asphalt, Inc. 64.6000 5,658.96 5,658.96 6085 Len Trovero Construction 26.0000 2,277.60 2,277.60 20400800 FURNISHED EXCAV 92.800 CU YD 4887 Bob Propheter Construction, L.L.C. 13.1000 1,215.68 1,215.68 5765 Streator Asphalt, Inc. 34.7500 3,224.80 3,224.80 6085 Len Trovero Construction 20.0000 1,856.00 1,856.00 20700220 POROUS GRAN EMBANK 27.500 CU YD 4887 Bob Propheter Construction, L.L.C. 24.7500 680.63 680.63 5765 Streator Asphalt, Inc. 32.7000 899.25 899.25 6085 Len Trovero Construction 25.0000 687.50 687.50 20800150 TRENCH BACKFILL 9.100 CU YD 4887 Bob Propheter Construction, L.L.C. 12.1100 110.20 110.20 5765 Streator Asphalt, Inc. 41.4000 376.74 376.74 6085 Len Trovero Construction 25.0000 227.50 227.50 25000200 SEEDING CL 2 .250 ACRE 4887 Bob Propheter Construction, L.L.C. 4,500.0000 1,125.00 1,125.00 5765 Streator Asphalt, Inc. 525.0000 131.25 131.25 6085 Len Trovero Construction 1,000.0000 250.00 250.00 25000400 NITROGEN FERT NUTR 34.830 POUND 4887 Bob Propheter Construction, L.L.C. 1.0000 34.83 34.83 5765 Streator Asphalt, Inc. 0.6000 20.90 20.90 6085 Len Trovero Construction 1.0000 34.83 34.83 25000500 PHOSPHORUS FERT NUTR 34.830 POUND 4887 Bob Propheter Construction, L.L.C. 1.0000 34.83 34.83 5765 Streator Asphalt, Inc. 0.6000 20.90 20.90 6085 Len Trovero Construction 1.0000 34.83 34.83 25000600 POTASSIUM FERT NUTR 34.830 POUND 4887 Bob Propheter Construction, L.L.C. 1.0000 34.83 34.83 5765 Streator Asphalt, Inc. 0.6000 20.90 20.90 6085 Len Trovero Construction 1.0000 34.83 34.83 25100630 EROSION CONTR BLANKET 1,231.300 SQ YD 4887 Bob Propheter Construction, L.L.C. 1.2500 1,539.13 1,539.13 5765 Streator Asphalt, Inc. 3.2500 4,001.73 4,001.73 6085 Len Trovero Construction 3.5000 4,309.55 4,309.55 25200110 SODDING SALT TOLERANT 684.600 SQ YD 4887 Bob Propheter Construction, L.L.C. 4.0000 2,738.40 2,738.40 5765 Streator Asphalt, Inc. 9.9000 6,777.54 6,777.54 6085 Len Trovero Construction 11.0000 7,530.60 7,530.60 25200200 SUPPLE WATERING 34.000 UNIT 4887 Bob Propheter Construction, L.L.C. 12.0000 408.00 408.00 5765 Streator Asphalt, Inc. 95.0000 3,230.00 3,230.00 6085 Len Trovero Construction 100.0000 3,400.00 3,400.00 40200800 AGG SURF CSE B 30.100 TON 4887 Bob Propheter Construction, L.L.C. 18.6100 560.16 560.16 5765 Streator Asphalt, Inc. 14.9500 450.00 450.00 6085 Len Trovero Construction 20.0000 602.00 602.00 40600100 BIT MATLS PR CT 10,482.000 GALLON 4887 Bob Propheter Construction, L.L.C. 0.5000 5,241.00 5,241.00 5765 Streator Asphalt, Inc. 0.0100 104.82 104.82 6085 Len Trovero Construction 1.4000 14,674.80 14,674.80 40600300 AGG PR CT 264.700 TON 4887 Bob Propheter Construction, L.L.C. 1.0000 264.70 264.70 5765 Streator Asphalt, Inc. 0.0100 2.65 2.65 6085 Len Trovero Construction 18.0000 4,764.60 4,764.60 40600400 MIX CR JTS FLANGEWYS 38.000 TON 4887 Bob Propheter Construction, L.L.C. 106.4100 4,043.58 4,043.58 5765 Streator Asphalt, Inc. 95.0000 3,610.00 3,610.00 6085 Len Trovero Construction 100.0000 3,800.00 3,800.00 40600895 CONSTRUC TEST STRIP 1.000 EACH 4887 Bob Propheter Construction, L.L.C. 1,804.9700 1,804.97 1,804.97 5765 Streator Asphalt, Inc. 2,600.0000 2,600.00 2,600.00 6085 Len Trovero Construction 1,700.0000 1,700.00 1,700.00 40600980 BIT SURF REM BUTT JT 2,146.100 SQ YD 4887 Bob Propheter Construction, L.L.C. 10.9700 23,542.72 23,542.72 5765 Streator Asphalt, Inc. 8.1000 17,383.41 17,383.41 6085 Len Trovero Construction 10.0000 21,461.00 21,461.00 40600985 PCC SURF REM BUTT JT 657.900 SQ YD 4887 Bob Propheter Construction, L.L.C. 11.3400 7,460.59 7,460.59 5765 Streator Asphalt, Inc. 8.1000 5,328.99 5,328.99 6085 Len Trovero Construction 11.0000 7,236.90 7,236.90 40600990 TEMPORARY RAMP 286.700 SQ YD 4887 Bob Propheter Construction, L.L.C. 16.8300 4,825.16 4,825.16 5765 Streator Asphalt, Inc. 25.0000 7,167.50 7,167.50 6085 Len Trovero Construction 11.0000 3,153.70 3,153.70 40800040 INCIDENTAL BIT SURF 574.200 TON 4887 Bob Propheter Construction, L.L.C. 66.5900 38,235.98 38,235.98 5765 Streator Asphalt, Inc. 75.0000 43,065.00 43,065.00 6085 Len Trovero Construction 60.0000 34,452.00 34,452.00 42400100 PC CONC SIDEWALK 4 443.000 SQ FT 4887 Bob Propheter Construction, L.L.C. 9.1200 4,040.16 4,040.16 5765 Streator Asphalt, Inc. 5.6500 2,502.95 2,502.95 6085 Len Trovero Construction 3.5000 1,550.50 1,550.50 44000003 BIT SURF REM 3/4 126,723.000 SQ YD 4887 Bob Propheter Construction, L.L.C. 0.5400 68,430.42 68,430.42 5765 Streator Asphalt, Inc. 0.6500 82,369.95 82,369.95 6085 Len Trovero Construction 0.8000 101,378.40 101,378.40 44000100 PAVEMENT REM 171.000 SQ YD 4887 Bob Propheter Construction, L.L.C. 10.1300 1,732.23 1,732.23 5765 Streator Asphalt, Inc. 9.5000 1,624.50 1,624.50 6085 Len Trovero Construction 16.0000 2,736.00 2,736.00 44000500 COMB CURB GUTTER REM 277.000 FOOT 4887 Bob Propheter Construction, L.L.C. 4.8900 1,354.53 1,354.53 5765 Streator Asphalt, Inc. 3.8000 1,052.60 1,052.60 6085 Len Trovero Construction 6.0000 1,662.00 1,662.00 44000600 SIDEWALK REM 294.000 SQ FT 4887 Bob Propheter Construction, L.L.C. 1.1500 338.10 338.10 5765 Streator Asphalt, Inc. 2.3500 690.90 690.90 6085 Len Trovero Construction 1.5000 441.00 441.00 44201789 CL D PATCH T2 12 53.300 SQ YD 4887 Bob Propheter Construction, L.L.C. 79.9700 4,262.40 4,262.40 5765 Streator Asphalt, Inc. 67.0000 3,571.10 3,571.10 6085 Len Trovero Construction 140.0000 7,462.00 7,462.00 44201794 CL D PATCH T3 12 20.000 SQ YD 4887 Bob Propheter Construction, L.L.C. 68.1100 1,362.20 1,362.20 5765 Streator Asphalt, Inc. 55.0000 1,100.00 1,100.00 6085 Len Trovero Construction 125.0000 2,500.00 2,500.00 48101200 AGGREGATE SHLDS B 2,078.000 TON 4887 Bob Propheter Construction, L.L.C. 12.8400 26,681.52 26,681.52 5765 Streator Asphalt, Inc. 14.6500 30,442.70 30,442.70 6085 Len Trovero Construction 15.0000 31,170.00 31,170.00 48200400 BIT SHOULDERS 6 196.000 SQ YD 4887 Bob Propheter Construction, L.L.C. 28.6600 5,617.36 5,617.36 5765 Streator Asphalt, Inc. 12.8500 2,518.60 2,518.60 6085 Len Trovero Construction 20.0000 3,920.00 3,920.00 50100100 REM EXIST STRUCT 2.000 EACH 4887 Bob Propheter Construction, L.L.C. 10,492.3400 20,984.68 20,984.68 5765 Streator Asphalt, Inc. 3,300.0000 6,600.00 6,600.00 6085 Len Trovero Construction 6,000.0000 12,000.00 12,000.00 50104400 CONC HDWL REM 2.000 EACH 4887 Bob Propheter Construction, L.L.C. 508.2900 1,016.58 1,016.58 5765 Streator Asphalt, Inc. 175.0000 350.00 350.00 6085 Len Trovero Construction 200.0000 400.00 400.00 50105220 PIPE CULVERT REMOV 62.000 FOOT 4887 Bob Propheter Construction, L.L.C. 11.4300 708.66 708.66 5765 Streator Asphalt, Inc. 17.0000 1,054.00 1,054.00 6085 Len Trovero Construction 15.0000 930.00 930.00 50800105 REINFORCEMENT BARS 232.500 POUND 4887 Bob Propheter Construction, L.L.C. 2.4100 560.33 560.33 5765 Streator Asphalt, Inc. 3.2000 744.00 744.00 6085 Len Trovero Construction 2.0000 465.00 465.00 54001000 BOX CUL END SECT 1.000 EACH 4887 Bob Propheter Construction, L.L.C. 3,700.2200 3,700.22 3,700.22 5765 Streator Asphalt, Inc. 2,170.0000 2,170.00 2,170.00 6085 Len Trovero Construction 4,000.0000 4,000.00 4,000.00 54020903 PCBC 9X3 (M273) 176.000 FOOT 4887 Bob Propheter Construction, L.L.C. 552.1400 97,176.64 97,176.64 5765 Streator Asphalt, Inc. 340.0000 59,840.00 59,840.00 6085 Len Trovero Construction 400.0000 70,400.00 70,400.00 542A0217 P CUL CL A 1 12 32.000 FOOT 4887 Bob Propheter Construction, L.L.C. 63.3500 2,027.20 2,027.20 5765 Streator Asphalt, Inc. 29.0000 928.00 928.00 6085 Len Trovero Construction 44.0000 1,408.00 1,408.00 542C0223 P CUL CL C 1 18 84.000 FOOT 4887 Bob Propheter Construction, L.L.C. 42.1600 3,541.44 3,541.44 5765 Streator Asphalt, Inc. 40.0000 3,360.00 3,360.00 6085 Len Trovero Construction 45.0000 3,780.00 3,780.00 54215553 MET END SEC 18 3.000 EACH 4887 Bob Propheter Construction, L.L.C. 126.3400 379.02 379.02 5765 Streator Asphalt, Inc. 135.0000 405.00 405.00 6085 Len Trovero Construction 140.0000 420.00 420.00 54248510 CONCRETE COLLAR .980 CU YD 4887 Bob Propheter Construction, L.L.C. 1,211.4700 1,187.24 1,187.24 5765 Streator Asphalt, Inc. 735.0000 720.30 720.30 6085 Len Trovero Construction 2,000.0000 1,960.00 1,960.00 56109210 WATER VALVES ADJUST 3.000 EACH 4887 Bob Propheter Construction, L.L.C. 338.5200 1,015.56 1,015.56 5765 Streator Asphalt, Inc. 55.0000 165.00 165.00 6085 Len Trovero Construction 125.0000 375.00 375.00 60235700 INLETS TA T3F&G 1.000 EACH 4887 Bob Propheter Construction, L.L.C. 1,141.8900 1,141.89 1,141.89 5765 Streator Asphalt, Inc. 965.0000 965.00 965.00 6085 Len Trovero Construction 775.0000 775.00 775.00 60255500 MAN ADJUST 1.000 EACH 4887 Bob Propheter Construction, L.L.C. 406.6200 406.62 406.62 5765 Streator Asphalt, Inc. 640.0000 640.00 640.00 6085 Len Trovero Construction 300.0000 300.00 300.00 60500060 REMOV INLETS 1.000 EACH 4887 Bob Propheter Construction, L.L.C. 273.3400 273.34 273.34 5765 Streator Asphalt, Inc. 125.0000 125.00 125.00 6085 Len Trovero Construction 250.0000 250.00 250.00 60603800 COMB CC&G TB6.12 44.000 FOOT 4887 Bob Propheter Construction, L.L.C. 45.7900 2,014.76 2,014.76 5765 Streator Asphalt, Inc. 23.0000 1,012.00 1,012.00 6085 Len Trovero Construction 20.0000 880.00 880.00 60604400 COMB CC&G TB6.18 30.000 FOOT 4887 Bob Propheter Construction, L.L.C. 65.4700 1,964.10 1,964.10 5765 Streator Asphalt, Inc. 29.0000 870.00 870.00 6085 Len Trovero Construction 23.0000 690.00 690.00 60605000 COMB CC&G TB6.24 180.300 FOOT 4887 Bob Propheter Construction, L.L.C. 37.8200 6,818.95 6,818.95 5765 Streator Asphalt, Inc. 19.0000 3,425.70 3,425.70 6085 Len Trovero Construction 28.0000 5,048.40 5,048.40 63300210 REM REIN EX SPBGR TB 12.500 FOOT 4887 Bob Propheter Construction, L.L.C. 75.0000 937.50 937.50 5765 Streator Asphalt, Inc. 20.0000 250.00 250.00 6085 Len Trovero Construction 70.0000 875.00 875.00 66600105 FUR ERECT ROW MARKERS 4.000 EACH 4887 Bob Propheter Construction, L.L.C. 70.4000 281.60 281.60 5765 Streator Asphalt, Inc. 85.0000 340.00 340.00 6085 Len Trovero Construction 80.0000 320.00 320.00 67000400 ENGR FIELD OFFICE A 3.000 CAL MO 4887 Bob Propheter Construction, L.L.C. 1,552.7900 4,658.37 4,658.37 5765 Streator Asphalt, Inc. 1,400.0000 4,200.00 4,200.00 6085 Len Trovero Construction 1,300.0000 3,900.00 3,900.00 67100100 MOBILIZATION 1.000 L SUM 4887 Bob Propheter Construction, L.L.C. 59,364.0000 59,364.00 59,364.00 5765 Streator Asphalt, Inc. 30,000.0000 30,000.00 30,000.00 6085 Len Trovero Construction 61,000.0000 61,000.00 61,000.00 70100450 TRAF CONT-PROT 701201 1.000 L SUM 4887 Bob Propheter Construction, L.L.C. 4,500.0000 4,500.00 4,500.00 5765 Streator Asphalt, Inc. 1,530.0000 1,530.00 1,530.00 6085 Len Trovero Construction 46,000.0000 46,000.00 46,000.00 70100460 TRAF CONT-PROT 701306 1.000 L SUM 4887 Bob Propheter Construction, L.L.C. 5,500.0000 5,500.00 5,500.00 5765 Streator Asphalt, Inc. 3,860.0000 3,860.00 3,860.00 6085 Len Trovero Construction 5,000.0000 5,000.00 5,000.00 70100500 TRAF CONT-PROT 701326 1.000 L SUM 4887 Bob Propheter Construction, L.L.C. 6,500.0000 6,500.00 6,500.00 5765 Streator Asphalt, Inc. 1,130.0000 1,130.00 1,130.00 6085 Len Trovero Construction 7,000.0000 7,000.00 7,000.00 70102620 TR CONT & PROT 701501 1.000 L SUM 4887 Bob Propheter Construction, L.L.C. 5,000.0000 5,000.00 5,000.00 5765 Streator Asphalt, Inc. 1,100.0000 1,100.00 1,100.00 6085 Len Trovero Construction 6,000.0000 6,000.00 6,000.00 70300100 SHORT-TERM PAVT MKING 3,070.000 FOOT 4887 Bob Propheter Construction, L.L.C. 0.5000 1,535.00 1,535.00 5765 Streator Asphalt, Inc. 0.4500 1,381.50 1,381.50 6085 Len Trovero Construction 0.6000 1,842.00 1,842.00 70300210 TEMP PVT MK LTR & SYM 62.400 SQ FT 4887 Bob Propheter Construction, L.L.C. 1.0000 62.40 62.40 5765 Streator Asphalt, Inc. 0.0000 0.00 0.00 6085 Len Trovero Construction 1.5000 93.60 93.60 70300220 TEMP PVT MK LINE 4 101,905.000 FOOT 4887 Bob Propheter Construction, L.L.C. 0.0800 8,152.40 8,152.40 5765 Streator Asphalt, Inc. 0.0000 0.00 0.00 6085 Len Trovero Construction 0.1300 13,247.65 13,247.65 70300240 TEMP PVT MK LINE 6 9,559.000 FOOT 4887 Bob Propheter Construction, L.L.C. 0.0900 860.31 860.31 5765 Streator Asphalt, Inc. 0.0000 0.00 0.00 6085 Len Trovero Construction 0.4500 4,301.55 4,301.55 70300250 TEMP PVT MK LINE 8 694.000 FOOT 4887 Bob Propheter Construction, L.L.C. 0.2000 138.80 138.80 5765 Streator Asphalt, Inc. 0.0000 0.00 0.00 6085 Len Trovero Construction 0.6000 416.40 416.40 70300260 TEMP PVT MK LINE 12 586.000 FOOT 4887 Bob Propheter Construction, L.L.C. 0.5000 293.00 293.00 5765 Streator Asphalt, Inc. 0.0000 0.00 0.00 6085 Len Trovero Construction 0.9000 527.40 527.40 70300280 TEMP PVT MK LINE 24 178.000 FOOT 4887 Bob Propheter Construction, L.L.C. 1.0000 178.00 178.00 5765 Streator Asphalt, Inc. 0.0000 0.00 0.00 6085 Len Trovero Construction 1.8000 320.40 320.40 70301000 WORK ZONE PAVT MK REM 510.000 SQ FT 4887 Bob Propheter Construction, L.L.C. 3.1500 1,606.50 1,606.50 5765 Streator Asphalt, Inc. 8.2500 4,207.50 4,207.50 6085 Len Trovero Construction 2.0000 1,020.00 1,020.00 78000100 THPL PVT MK LTR & SYM 62.400 SQ FT 4887 Bob Propheter Construction, L.L.C. 3.7500 234.00 234.00 5765 Streator Asphalt, Inc. 3.7500 234.00 234.00 6085 Len Trovero Construction 2.7500 171.60 171.60 78000200 THPL PVT MK LINE 4 10,532.000 FOOT 4887 Bob Propheter Construction, L.L.C. 0.3700 3,896.84 3,896.84 5765 Streator Asphalt, Inc. 0.3700 3,896.84 3,896.84 6085 Len Trovero Construction 0.4500 4,739.40 4,739.40 78000400 THPL PVT MK LINE 6 130.000 FOOT 4887 Bob Propheter Construction, L.L.C. 0.5900 76.70 76.70 5765 Streator Asphalt, Inc. 0.5900 76.70 76.70 6085 Len Trovero Construction 0.6500 84.50 84.50 78000500 THPL PVT MK LINE 8 694.000 FOOT 4887 Bob Propheter Construction, L.L.C. 0.6500 451.10 451.10 5765 Streator Asphalt, Inc. 0.6500 451.10 451.10 6085 Len Trovero Construction 0.8500 589.90 589.90 78000600 THPL PVT MK LINE 12 586.000 FOOT 4887 Bob Propheter Construction, L.L.C. 1.3500 791.10 791.10 5765 Streator Asphalt, Inc. 1.3500 791.10 791.10 6085 Len Trovero Construction 1.2500 732.50 732.50 78000650 THPL PVT MK LINE 24 178.000 FOOT 4887 Bob Propheter Construction, L.L.C. 2.3500 418.30 418.30 5765 Streator Asphalt, Inc. 2.3500 418.30 418.30 6085 Len Trovero Construction 2.5000 445.00 445.00 78001110 PAINT PVT MK LINE 4 91,373.000 FOOT 4887 Bob Propheter Construction, L.L.C. 0.0800 7,309.84 7,309.84 5765 Streator Asphalt, Inc. 0.0800 7,309.84 7,309.84 6085 Len Trovero Construction 0.1400 12,792.22 12,792.22 78001130 PAINT PVT MK LINE 6 9,429.000 FOOT 4887 Bob Propheter Construction, L.L.C. 0.0900 848.61 848.61 5765 Streator Asphalt, Inc. 0.0900 848.61 848.61 6085 Len Trovero Construction 0.4500 4,243.05 4,243.05 78100100 RAISED REFL PAVT MKR 524.000 EACH 4887 Bob Propheter Construction, L.L.C. 23.5000 12,314.00 12,314.00 5765 Streator Asphalt, Inc. 23.5000 12,314.00 12,314.00 6085 Len Trovero Construction 23.0000 12,052.00 12,052.00 78200300 PRISMATIC CURB REFL 24.000 EACH 4887 Bob Propheter Construction, L.L.C. 12.0000 288.00 288.00 5765 Streator Asphalt, Inc. 12.0000 288.00 288.00 6085 Len Trovero Construction 10.0000 240.00 240.00 78300200 RAISED REF PVT MK REM 218.000 EACH 4887 Bob Propheter Construction, L.L.C. 14.6100 3,184.98 3,184.98 5765 Streator Asphalt, Inc. 13.0000 2,834.00 2,834.00 6085 Len Trovero Construction 8.0000 1,744.00 1,744.00