|
Download IFP
DOT-OPS-ITS2008-01
The following questions
have been raised regarding the Invitation For Bids on DOT-OPS-ITS2008-01
(Intelligent Transportation System Maintenance Services). Included are the IDOT
responses to those questions
Questions Regarding Specific Sections of the Contract
Section 2.3.1.4 – Labor Rates
Question:
Can you clarify sentence three concerning “premium” pay rates. Is it your
intention to multiply the quoted straight time rates by 1.5 or 2 times for
premium rates (as applicable) or are the quoted hourly rates supposed to cover
any/all premium time?
Answer::
Premium time shall be considered as time at higher rates for work completed as
overtime, after hours or Saturday or Sunday.
Section 2.3.1.5 – Incidental Material
Question:
This item makes no sense. Any item with less that a $25.00 value is incidental
to the contract. If we were to replace 10 fiber optic terminations at $20.00
each plus breakout kits and other associated material, we would be giving
hundreds of dollars worth of material away. During a 2-year contract, this
would add up in the thousands of dollars for materials that would not be paid.
Answer:
The cost of incidental parts and materials under $25.00, which are not
included in Part 3 would not apply to this contract. There is no Part 3 of the
contract which describes the parts and materials that would be considered
incidental to the contract.
Section 2.3.1.6 – Knockdown Debris
Question:
The hauling of knocked down
debris is incidental. Again it takes time to pick up, haul, and unload items
such as pole assemblies. IL D.O.T, storage yards are not always near the sign
locations. For example, to retrieve a pole assembly, it could take 8-10
man-hours to deal with this item. How can this be incidental?
Answer:
The majority of the equipment to be maintained under this contract is mounted
on overhead sign structures; therefore the amount of debris needed to be removed
from a knockdown should be minimal. In the event that an overhead sign
structure or the equipment is damaged and is a hazard to the motoring public,
the work would be completed in accordance with Article 109.04 of the Standard
Specifications.
Section 2.3.1.6 – Travel Time
Question 1:
Is it the intent NOT to pay for travel time to the sites but “chargeable” time
begins upon arrival at the site and log-in?
Question 2:
Are we to somehow bury or inflate our base rate to cover travel time to and from
these sites? Our employees have to paid to travel to and from jobs.
Answer 1 & 2:
It is the intent of the contract not to pay for travel time. The contractor’s
time starts once the contractor arrives at the site to begin work. We note the
contract is set up so that a contractor may bid on the entire contract or the
contract for individual districts or multiple districts. The intent of this
provision is to encourage contractors to bid on the contract that are able to
respond to maintenance issues within the time provisions of the contract.
Section 2.3.1.8 – Response Time
Question 1:
It is physically not possible to get to all of these locations from our office
in 1 ½ hours. Are we to bid only those we can reach? Since normal service is
24-response, it seems a shame not to be able to bid all of them. I do not think
there is any one contractor that has offices in all of these areas.
Question 2:
(see first question on 2.3.1.4) Based on the furthest service area(s) emergency
response times from our Peoria location are not attainable. It is your intent
to routinely assess liquidated damages per 2.3.1.9?
Answer 1 & 2:
Response times for the maintenance of this equipment could become an issue in
providing timely information to the motoring public. In the case of an
emergency where damaged equipment could become a hazard to the motoring public,
the response time could become critical. If a contractor bids on the entire
contract then the contractor should have a subcontractor available in this
instance to meet the response time specified in the contract.
Section 2.3.1.11 – Traffic Control
Question:
It is virtually impossible to determine what traffic control will be required,
how many lane closures might be required, etc. It is really your intent to have
all costs associated with traffic control included in the schedule of pricing in
the IFB? Is your intent also to assess a substantial penalty for failure to
clear a traffic lane? Would the department consider having maintenance provide
lane closure if/when required to help reduce costs?
Answer:
Traffic control for maintenance purposes should require no more than a lane
closure depending on the location of the equipment and if the contractor has
access to the equipment from the shoulder. In the event that equipment needs to
be completely removed for servicing and/or repair that would require a complete
temporary road closure with coordination with State Police goes beyond the
intended scope of this maintenance contract and would be considered as extra
work.
Section 2.3.1.15 – Work Item
Question:
Paragraph 2 is quite detailed concerning various items of maintenance (ie:
video vehicle detection, etc.) however, Section 2.6 only indicates locations
concerning VMS. What exactly is the scope of work we can expect to be involved
in this contract? Does this contract only concern VMS locations, or are traffic
signal installations also included?
Answer:
At the present time the primary purpose of the contract is for the maintenance
of the VMS panels. One district does have surveillance cameras mounted at
several interchanges, which are only about a year old and covered under
warranty. When the warranty expires, these cameras will be maintained under
this contract. No traffic signal installations will be maintained under this
contract.
General Questions
Regarding “Transportation of
Parts is Incidental”:
While there are times this
would be true, there also will be times when replacement parts must be paid
for. For example, if we were to go to a D.O.T. yard and pick up a pole, and
haul it to a site, this would be a special trip and should be compensated for.
Response:
Most of the time when maintenance is being performed at a location, a
representative from the district will be available at the site. The parts to be
transported in this instance will probably be circuit boards, cables,
controllers, and LED modules, which the district representative will have with
them. At this time we do not foresee any large objects having to be transported
from a district storage facility to the site.
Question:
I have not seen any reference to markup allowed for materials (cost plus X%), is
there a reference that I missed in my review of the documents?
Answer:
Markup allowance for materials used for maintaining the equipment under this
contract is covered under the second paragraph Section 2.3.1.5 “Parts and
Materials” of the
contract.
Question:
It appears that various operating software is in used in different areas of
service. If required, will the department provide copies of software/licenses
for our use (if needed) or will all programming or testing be the responsibility
of district personnel?
Answer:
Operating software will not be made available to the contractor for programming
and testing purposes. A representative from the district familiar with the
operation of the equipment should be available at the time f maintenance and/or
repairs to assist in the programming and testing of the equipment for proper
operation.
Question:
Is all software necessary for programming and troubleshooting being provided by
the IL I.D.OT.? Will a laptop be required?
Answer:
Operating software will be necessary for programming, troubleshooting and
testing purposes. A representative from the district familiar with the
operation of the equipment should be available at the time of maintenance and/or
repairs to assist in the programming, troubleshooting and testing of the
equipment for proper operation.
Question:
All bid items show a truck-mounted attenuator. Is this required? We do not own
one. Is there an alternate that we may use?
Answer:
Traffic control for maintenance purposes should require no more than a lane
closure depending on the location of the equipment and if the contractor has
access to the equipment from the shoulder. Truck mounted attenuators are
normally used for moving operations, but that is not to say that a district
could require the contractor to supply one due to the location of the work. It
is a separate pay item in the contract. One of these could probably be leased
from one of the traffic control companies, if a district would require it to be
used.
Question:
You are requesting labor rates for repairs by the district and not by specific
locations. This is not necessarily in the D.O.T.’s best interest. Some
districts have up to three prevailing wage rates. To protect ourselves, we
would have to quote the highest rate in that district. If you would request
rates by county (or location), the D.O.T. could save up to $12.00 per hour.
Answer:
Exhibit 1 contains the prevailing wages of the counties where the work will be
performed. This contract involves labor rates for seven counties so all of the
counties in a district are not included in the contract, so the various labor
rates should not be a problem. |