ILLINOIS DEPARTMENT OF TRANSPORTATION PAGE: 1 03/05/10 16:23:57 U N I T P R I C E T A B U L A T I O N O F B I D S LETTING DATE: 01/15/2010 LETTING TYPE: SCHEDULED CONTRACT NUMBER: 85486 LETTING ITEM NUMBER: 083 RESPONSIBLE DISTRICT: 02 BIDS LOCKED: Y SECTION: 09-00242-00-RP COUNTY: ROCK ISLAND ESTIMATE: STATE JOB NUMBER: C-92-168-09 MUNICIPALITY: MOLINE PROJECT NUMBER: ARA-5074/083/000 -------------------------- SUMMARY OF CONTRACTOR BIDS -------------------------- "AS READ" SUMMATION SUMMATION OF NBR BIDR CONTR COMB ITEM CONTR BIDDER OF BIDDER CALCULATED LOW BIDR CALC BLANK NBR BIDDER NAME GROUP COMB GRP NBR GROUP TOTAL PRICE EXTENSIONS EXTENSIONS BID EXTENSION DIFF BIDS 0593 Brandt Construction Co. NO ALT 2,802,730.60 2,802,730.60 2,802,730.60 1799 Fischer Excavating, Inc. NO ALT 2,764,346.77 2,764,346.77 2,764,346.77 3375 Langman Construction, Inc. NO ALT 2,587,162.91 2,587,162.91 2,587,162.91 3392 Walter D. Laud, Inc. NO ALT 2,237,995.25 * 2,237,995.25 2,237,995.25 * 3815 McCarthy Improvement Company & Foley Construction Company NO ALT 2,829,659.75 2,829,659.75 2,829,659.75 6210 Valley Construction Co. NO ALT 2,594,854.65 2,594,854.65 2,594,854.65 **** TOTAL GROUP NO ALT PAY ITEMS FOR THIS CONTRACT = 111 ---------------------- DETAIL CONTRACTOR BIDS ---------------------- ITEM NBR ITEM DESCRIPTION UNIT OF UNIT BIDDER CALCULATED BIDR CALC BIDR NBR BIDDER NAME QUANTITY MEASURE PRICE EXTENSION EXTENSION EXTENSION DIFF A2008920 T-ULMUS REGAL 2-1/2 30.000 EACH 0593 Brandt Construction Co. 505.0000 15,150.00 15,150.00 1799 Fischer Excavating, Inc. 395.0000 11,850.00 11,850.00 3375 Langman Construction, Inc. 450.0000 13,500.00 13,500.00 3815 McCarthy Improvement Company & Foley Construction Company 475.0000 14,250.00 14,250.00 6210 Valley Construction Co. 395.0000 11,850.00 11,850.00 3392 Walter D. Laud, Inc. 425.0000 12,750.00 12,750.00 B2006216 T-SYRING RET TF 2 20.000 EACH 0593 Brandt Construction Co. 450.0000 9,000.00 9,000.00 1799 Fischer Excavating, Inc. 350.0000 7,000.00 7,000.00 3375 Langman Construction, Inc. 402.0000 8,040.00 8,040.00 3815 McCarthy Improvement Company & Foley Construction Company 400.0000 8,000.00 8,000.00 6210 Valley Construction Co. 350.0000 7,000.00 7,000.00 3392 Walter D. Laud, Inc. 375.0000 7,500.00 7,500.00 C2C10118 S-SPIREA JAP GM 18C 45.000 EACH 0593 Brandt Construction Co. 56.0000 2,520.00 2,520.00 1799 Fischer Excavating, Inc. 36.0000 1,620.00 1,620.00 3375 Langman Construction, Inc. 50.0000 2,250.00 2,250.00 3815 McCarthy Improvement Company & Foley Construction Company 42.0000 1,890.00 1,890.00 6210 Valley Construction Co. 36.0000 1,620.00 1,620.00 3392 Walter D. Laud, Inc. 50.0000 2,250.00 2,250.00 C2C15761 S-SPIREA JAP NEON 5GC 148.000 EACH 0593 Brandt Construction Co. 56.0000 8,288.00 8,288.00 1799 Fischer Excavating, Inc. 36.0000 5,328.00 5,328.00 3375 Langman Construction, Inc. 50.0000 7,400.00 7,400.00 3815 McCarthy Improvement Company & Foley Construction Company 42.0000 6,216.00 6,216.00 6210 Valley Construction Co. 36.0000 5,328.00 5,328.00 3392 Walter D. Laud, Inc. 40.0000 5,920.00 5,920.00 K0030401 P P CAL ACUT K F 1GAL 76.000 EACH 0593 Brandt Construction Co. 30.0000 2,280.00 2,280.00 1799 Fischer Excavating, Inc. 16.0000 1,216.00 1,216.00 3375 Langman Construction, Inc. 25.0000 1,900.00 1,900.00 3815 McCarthy Improvement Company & Foley Construction Company 40.0000 3,040.00 3,040.00 6210 Valley Construction Co. 16.0000 1,216.00 1,216.00 3392 Walter D. Laud, Inc. 40.0000 3,040.00 3,040.00 K0030442 P PL PEN ALOPE HAM 1G 40.000 EACH 0593 Brandt Construction Co. 30.0000 1,200.00 1,200.00 1799 Fischer Excavating, Inc. 16.0000 640.00 640.00 3375 Langman Construction, Inc. 25.0000 1,000.00 1,000.00 3815 McCarthy Improvement Company & Foley Construction Company 40.0000 1,600.00 1,600.00 6210 Valley Construction Co. 16.0000 640.00 640.00 3392 Walter D. Laud, Inc. 40.0000 1,600.00 1,600.00 K0039125 HEMERCL HAP RET CG 1G 1.210 UNIT 0593 Brandt Construction Co. 2,800.0000 3,388.00 3,388.00 1799 Fischer Excavating, Inc. 1,400.0000 1,694.00 1,694.00 3375 Langman Construction, Inc. 2,500.0000 3,025.00 3,025.00 3815 McCarthy Improvement Company & Foley Construction Company 1,800.0000 2,178.00 2,178.00 6210 Valley Construction Co. 1,400.0000 1,694.00 1,694.00 3392 Walter D. Laud, Inc. 1,700.0000 2,057.00 2,057.00 K0040334 PER SEDUM SPECT 1G 13.000 EACH 0593 Brandt Construction Co. 35.0000 455.00 455.00 1799 Fischer Excavating, Inc. 14.0000 182.00 182.00 3375 Langman Construction, Inc. 30.0000 390.00 390.00 3815 McCarthy Improvement Company & Foley Construction Company 18.0000 234.00 234.00 6210 Valley Construction Co. 14.0000 182.00 182.00 3392 Walter D. Laud, Inc. 20.0000 260.00 260.00 K1003455 LANDSCAPE FILL SOIL 348.000 CU YD 0593 Brandt Construction Co. 83.5000 29,058.00 29,058.00 1799 Fischer Excavating, Inc. 48.0000 16,704.00 16,704.00 3375 Langman Construction, Inc. 50.0000 17,400.00 17,400.00 3815 McCarthy Improvement Company & Foley Construction Company 54.0000 18,792.00 18,792.00 6210 Valley Construction Co. 48.0000 16,704.00 16,704.00 3392 Walter D. Laud, Inc. 68.0000 23,664.00 23,664.00 LR420129 PCC PVMT 8 SPL W IC 6,313.000 SQ YD 0593 Brandt Construction Co. 58.0000 366,154.00 366,154.00 1799 Fischer Excavating, Inc. 59.2400 373,982.12 373,982.12 3375 Langman Construction, Inc. 76.0000 479,788.00 479,788.00 3815 McCarthy Improvement Company & Foley Construction Company 65.0000 410,345.00 410,345.00 6210 Valley Construction Co. 63.8000 402,769.40 402,769.40 3392 Walter D. Laud, Inc. 58.0000 366,154.00 366,154.00 XX000739 CURB STOP & BOX 1 16.000 EACH 0593 Brandt Construction Co. 575.0000 9,200.00 9,200.00 1799 Fischer Excavating, Inc. 223.7400 3,579.84 3,579.84 3375 Langman Construction, Inc. 200.0000 3,200.00 3,200.00 3815 McCarthy Improvement Company & Foley Construction Company 300.0000 4,800.00 4,800.00 6210 Valley Construction Co. 600.0000 9,600.00 9,600.00 3392 Walter D. Laud, Inc. 325.0000 5,200.00 5,200.00 XX001186 PLANTER REMOVAL 25.000 EACH 0593 Brandt Construction Co. 485.0000 12,125.00 12,125.00 1799 Fischer Excavating, Inc. 275.7200 6,893.00 6,893.00 3375 Langman Construction, Inc. 500.0000 12,500.00 12,500.00 3815 McCarthy Improvement Company & Foley Construction Company 600.0000 15,000.00 15,000.00 6210 Valley Construction Co. 500.0000 12,500.00 12,500.00 3392 Walter D. Laud, Inc. 600.0000 15,000.00 15,000.00 XX003526 D I WAT MNF 8X6 RED 1.000 EACH 0593 Brandt Construction Co. 710.0000 710.00 710.00 1799 Fischer Excavating, Inc. 296.3200 296.32 296.32 3375 Langman Construction, Inc. 200.0000 200.00 200.00 3815 McCarthy Improvement Company & Foley Construction Company 300.0000 300.00 300.00 6210 Valley Construction Co. 220.0000 220.00 220.00 3392 Walter D. Laud, Inc. 285.0000 285.00 285.00 XX003531 WAT SER CONN 1 16.000 EACH 0593 Brandt Construction Co. 460.0000 7,360.00 7,360.00 1799 Fischer Excavating, Inc. 202.4100 3,238.56 3,238.56 3375 Langman Construction, Inc. 300.0000 4,800.00 4,800.00 3815 McCarthy Improvement Company & Foley Construction Company 450.0000 7,200.00 7,200.00 6210 Valley Construction Co. 320.0000 5,120.00 5,120.00 3392 Walter D. Laud, Inc. 1,000.0000 16,000.00 16,000.00 XX003532 WAT SER CONN 1.5 3.000 EACH 0593 Brandt Construction Co. 620.0000 1,860.00 1,860.00 1799 Fischer Excavating, Inc. 399.5100 1,198.53 1,198.53 3375 Langman Construction, Inc. 500.0000 1,500.00 1,500.00 3815 McCarthy Improvement Company & Foley Construction Company 600.0000 1,800.00 1,800.00 6210 Valley Construction Co. 540.0000 1,620.00 1,620.00 3392 Walter D. Laud, Inc. 1,400.0000 4,200.00 4,200.00 XX003539 D I WAT MNF 8 X 6 TEE 2.000 EACH 0593 Brandt Construction Co. 900.0000 1,800.00 1,800.00 1799 Fischer Excavating, Inc. 524.1500 1,048.30 1,048.30 3375 Langman Construction, Inc. 350.0000 700.00 700.00 3815 McCarthy Improvement Company & Foley Construction Company 500.0000 1,000.00 1,000.00 6210 Valley Construction Co. 360.0000 720.00 720.00 3392 Walter D. Laud, Inc. 500.0000 1,000.00 1,000.00 XX003614 REC (GFI) WEATHER CVR 61.000 EACH 0593 Brandt Construction Co. 310.0000 18,910.00 18,910.00 1799 Fischer Excavating, Inc. 175.0000 10,675.00 10,675.00 3375 Langman Construction, Inc. 252.2000 15,384.20 15,384.20 3815 McCarthy Improvement Company & Foley Construction Company 200.0000 12,200.00 12,200.00 6210 Valley Construction Co. 190.1300 11,597.93 11,597.93 3392 Walter D. Laud, Inc. 275.0000 16,775.00 16,775.00 XX003803 SAN SEWER SERVICE 6 202.000 FOOT 0593 Brandt Construction Co. 142.1000 28,704.20 28,704.20 1799 Fischer Excavating, Inc. 88.7800 17,933.56 17,933.56 3375 Langman Construction, Inc. 40.0000 8,080.00 8,080.00 3815 McCarthy Improvement Company & Foley Construction Company 70.0000 14,140.00 14,140.00 6210 Valley Construction Co. 87.0000 17,574.00 17,574.00 3392 Walter D. Laud, Inc. 47.0000 9,494.00 9,494.00 XX004446 SEEDING CL 2 SPL 250.000 SQ YD 0593 Brandt Construction Co. 6.0000 1,500.00 1,500.00 1799 Fischer Excavating, Inc. 4.0000 1,000.00 1,000.00 3375 Langman Construction, Inc. 5.0000 1,250.00 1,250.00 3815 McCarthy Improvement Company & Foley Construction Company 3.0000 750.00 750.00 6210 Valley Construction Co. 4.0000 1,000.00 1,000.00 3392 Walter D. Laud, Inc. 3.0000 750.00 750.00 XX004997 WAT SER CONN 2 3.000 EACH 0593 Brandt Construction Co. 700.0000 2,100.00 2,100.00 1799 Fischer Excavating, Inc. 475.4700 1,426.41 1,426.41 3375 Langman Construction, Inc. 600.0000 1,800.00 1,800.00 3815 McCarthy Improvement Company & Foley Construction Company 700.0000 2,100.00 2,100.00 6210 Valley Construction Co. 580.0000 1,740.00 1,740.00 3392 Walter D. Laud, Inc. 1,500.0000 4,500.00 4,500.00 XX005003 D I WAT MNF 10X6 TEE 7.000 EACH 0593 Brandt Construction Co. 980.0000 6,860.00 6,860.00 1799 Fischer Excavating, Inc. 466.0700 3,262.49 3,262.49 3375 Langman Construction, Inc. 400.0000 2,800.00 2,800.00 3815 McCarthy Improvement Company & Foley Construction Company 600.0000 4,200.00 4,200.00 6210 Valley Construction Co. 400.0000 2,800.00 2,800.00 3392 Walter D. Laud, Inc. 600.0000 4,200.00 4,200.00 XX005005 D I WAT MNF 10X8 TEE 1.000 EACH 0593 Brandt Construction Co. 1,030.0000 1,030.00 1,030.00 1799 Fischer Excavating, Inc. 721.8500 721.85 721.85 3375 Langman Construction, Inc. 500.0000 500.00 500.00 3815 McCarthy Improvement Company & Foley Construction Company 600.0000 600.00 600.00 6210 Valley Construction Co. 530.0000 530.00 530.00 3392 Walter D. Laud, Inc. 700.0000 700.00 700.00 XX005565 REM AND RES BRICK PAV 42.000 SQ FT 0593 Brandt Construction Co. 24.5000 1,029.00 1,029.00 1799 Fischer Excavating, Inc. 24.2000 1,016.40 1,016.40 3375 Langman Construction, Inc. 10.0000 420.00 420.00 3815 McCarthy Improvement Company & Foley Construction Company 55.0000 2,310.00 2,310.00 6210 Valley Construction Co. 24.2000 1,016.40 1,016.40 3392 Walter D. Laud, Inc. 30.0000 1,260.00 1,260.00 XX005763 CATCH BASINS, DOUBLE 10.000 EACH 0593 Brandt Construction Co. 2,650.0000 26,500.00 26,500.00 1799 Fischer Excavating, Inc. 3,414.3000 34,143.00 34,143.00 3375 Langman Construction, Inc. 5,000.0000 50,000.00 50,000.00 3815 McCarthy Improvement Company & Foley Construction Company 4,000.0000 40,000.00 40,000.00 6210 Valley Construction Co. 3,700.0000 37,000.00 37,000.00 3392 Walter D. Laud, Inc. 3,000.0000 30,000.00 30,000.00 XX005764 CATCH BASINS, SINGLE 3.000 EACH 0593 Brandt Construction Co. 1,665.0000 4,995.00 4,995.00 1799 Fischer Excavating, Inc. 2,145.7000 6,437.10 6,437.10 3375 Langman Construction, Inc. 4,500.0000 13,500.00 13,500.00 3815 McCarthy Improvement Company & Foley Construction Company 3,000.0000 9,000.00 9,000.00 6210 Valley Construction Co. 2,500.0000 7,500.00 7,500.00 3392 Walter D. Laud, Inc. 2,500.0000 7,500.00 7,500.00 XX005781 D I WM FIT PLUG 8 2.000 EACH 0593 Brandt Construction Co. 430.0000 860.00 860.00 1799 Fischer Excavating, Inc. 150.4900 300.98 300.98 3375 Langman Construction, Inc. 100.0000 200.00 200.00 3815 McCarthy Improvement Company & Foley Construction Company 400.0000 800.00 800.00 6210 Valley Construction Co. 150.0000 300.00 300.00 3392 Walter D. Laud, Inc. 200.0000 400.00 400.00 XX005790 REC SAN S LAT 6 10.000 EACH 0593 Brandt Construction Co. 1,280.0000 12,800.00 12,800.00 1799 Fischer Excavating, Inc. 739.3700 7,393.70 7,393.70 3375 Langman Construction, Inc. 500.0000 5,000.00 5,000.00 3815 McCarthy Improvement Company & Foley Construction Company 1,700.0000 17,000.00 17,000.00 6210 Valley Construction Co. 350.0000 3,500.00 3,500.00 3392 Walter D. Laud, Inc. 1,500.0000 15,000.00 15,000.00 XX006077 GATE VALVE AND BOX 6 3.000 EACH 0593 Brandt Construction Co. 1,300.0000 3,900.00 3,900.00 1799 Fischer Excavating, Inc. 1,212.4400 3,637.32 3,637.32 3375 Langman Construction, Inc. 700.0000 2,100.00 2,100.00 3815 McCarthy Improvement Company & Foley Construction Company 1,000.0000 3,000.00 3,000.00 6210 Valley Construction Co. 750.0000 2,250.00 2,250.00 3392 Walter D. Laud, Inc. 1,050.0000 3,150.00 3,150.00 XX006241 GATE VALVE & BOX 8 2.000 EACH 0593 Brandt Construction Co. 1,600.0000 3,200.00 3,200.00 1799 Fischer Excavating, Inc. 1,546.9700 3,093.94 3,093.94 3375 Langman Construction, Inc. 1,000.0000 2,000.00 2,000.00 3815 McCarthy Improvement Company & Foley Construction Company 1,400.0000 2,800.00 2,800.00 6210 Valley Construction Co. 1,000.0000 2,000.00 2,000.00 3392 Walter D. Laud, Inc. 1,300.0000 2,600.00 2,600.00 XX006266 CURB STOP & BOX 1.5" 3.000 EACH 0593 Brandt Construction Co. 855.0000 2,565.00 2,565.00 1799 Fischer Excavating, Inc. 950.9000 2,852.70 2,852.70 3375 Langman Construction, Inc. 300.0000 900.00 900.00 3815 McCarthy Improvement Company & Foley Construction Company 400.0000 1,200.00 1,200.00 6210 Valley Construction Co. 360.0000 1,080.00 1,080.00 3392 Walter D. Laud, Inc. 350.0000 1,050.00 1,050.00 XX006782 TEMP HMA BC 8" 3,500.000 SQ YD 0593 Brandt Construction Co. 30.0000 105,000.00 105,000.00 1799 Fischer Excavating, Inc. 55.2200 193,270.00 193,270.00 3375 Langman Construction, Inc. 20.0000 70,000.00 70,000.00 3815 McCarthy Improvement Company & Foley Construction Company 25.0000 87,500.00 87,500.00 6210 Valley Construction Co. 25.0000 87,500.00 87,500.00 3392 Walter D. Laud, Inc. 0.0100 35.00 35.00 XX006796 D I WM BEND 90 6 1.000 EACH 0593 Brandt Construction Co. 730.0000 730.00 730.00 1799 Fischer Excavating, Inc. 265.7400 265.74 265.74 3375 Langman Construction, Inc. 300.0000 300.00 300.00 3815 McCarthy Improvement Company & Foley Construction Company 300.0000 300.00 300.00 6210 Valley Construction Co. 250.0000 250.00 250.00 3392 Walter D. Laud, Inc. 275.0000 275.00 275.00 XX006805 PCC BSE CSE 4 SPL 3,632.000 SQ FT 0593 Brandt Construction Co. 4.7500 17,252.00 17,252.00 1799 Fischer Excavating, Inc. 11.5800 42,058.56 42,058.56 3375 Langman Construction, Inc. 8.2500 29,964.00 29,964.00 3815 McCarthy Improvement Company & Foley Construction Company 12.0000 43,584.00 43,584.00 6210 Valley Construction Co. 15.0000 54,480.00 54,480.00 3392 Walter D. Laud, Inc. 10.0000 36,320.00 36,320.00 XX006868 PCC PVT TEXT COLOR 8 377.000 SQ YD 0593 Brandt Construction Co. 148.5000 55,984.50 55,984.50 1799 Fischer Excavating, Inc. 200.8900 75,735.53 75,735.53 3375 Langman Construction, Inc. 110.0000 41,470.00 41,470.00 3815 McCarthy Improvement Company & Foley Construction Company 200.0000 75,400.00 75,400.00 6210 Valley Construction Co. 140.0000 52,780.00 52,780.00 3392 Walter D. Laud, Inc. 200.0000 75,400.00 75,400.00 XX007109 LIGHT FIXTURE TYPE B 20.000 EACH 0593 Brandt Construction Co. 1,780.0000 35,600.00 35,600.00 1799 Fischer Excavating, Inc. 815.0000 16,300.00 16,300.00 3375 Langman Construction, Inc. 1,462.7700 29,255.40 29,255.40 3815 McCarthy Improvement Company & Foley Construction Company 1,000.0000 20,000.00 20,000.00 6210 Valley Construction Co. 782.0600 15,641.20 15,641.20 3392 Walter D. Laud, Inc. 1,600.0000 32,000.00 32,000.00 XX007112 LIGHT FIXTURE TYPE C 13.000 EACH 0593 Brandt Construction Co. 1,455.0000 18,915.00 18,915.00 1799 Fischer Excavating, Inc. 920.0000 11,960.00 11,960.00 3375 Langman Construction, Inc. 1,196.8200 15,558.66 15,558.66 3815 McCarthy Improvement Company & Foley Construction Company 1,000.0000 13,000.00 13,000.00 6210 Valley Construction Co. 763.7800 9,929.14 9,929.14 3392 Walter D. Laud, Inc. 1,300.0000 16,900.00 16,900.00 XX007113 LIGHT FIXTURE TYPE D 10.000 EACH 0593 Brandt Construction Co. 400.0000 4,000.00 4,000.00 1799 Fischer Excavating, Inc. 545.0000 5,450.00 5,450.00 3375 Langman Construction, Inc. 329.2400 3,292.40 3,292.40 3815 McCarthy Improvement Company & Foley Construction Company 400.0000 4,000.00 4,000.00 6210 Valley Construction Co. 367.9800 3,679.80 3,679.80 3392 Walter D. Laud, Inc. 360.0000 3,600.00 3,600.00 XX007207 BUS SHELTER PLATFORM 2.000 EACH 0593 Brandt Construction Co. 8,000.0000 16,000.00 16,000.00 1799 Fischer Excavating, Inc. 18,785.9900 37,571.98 37,571.98 3375 Langman Construction, Inc. 5,500.0000 11,000.00 11,000.00 3815 McCarthy Improvement Company & Foley Construction Company 12,000.0000 24,000.00 24,000.00 6210 Valley Construction Co. 8,400.0000 16,800.00 16,800.00 3392 Walter D. Laud, Inc. 16,000.0000 32,000.00 32,000.00 XX007240 SAN SEW CLEAN OUT 4.000 EACH 0593 Brandt Construction Co. 1,675.0000 6,700.00 6,700.00 1799 Fischer Excavating, Inc. 1,753.1300 7,012.52 7,012.52 3375 Langman Construction, Inc. 1,000.0000 4,000.00 4,000.00 3815 McCarthy Improvement Company & Foley Construction Company 1,000.0000 4,000.00 4,000.00 6210 Valley Construction Co. 1,400.0000 5,600.00 5,600.00 3392 Walter D. Laud, Inc. 1,500.0000 6,000.00 6,000.00 XX007263 GATE VALVE W/ BOX 4 4.000 EACH 0593 Brandt Construction Co. 1,200.0000 4,800.00 4,800.00 1799 Fischer Excavating, Inc. 1,059.5300 4,238.12 4,238.12 3375 Langman Construction, Inc. 700.0000 2,800.00 2,800.00 3815 McCarthy Improvement Company & Foley Construction Company 1,000.0000 4,000.00 4,000.00 6210 Valley Construction Co. 750.0000 3,000.00 3,000.00 3392 Walter D. Laud, Inc. 880.0000 3,520.00 3,520.00 XX007379 CLEANOUT REMOVED 5.000 EACH 0593 Brandt Construction Co. 300.0000 1,500.00 1,500.00 1799 Fischer Excavating, Inc. 149.5100 747.55 747.55 3375 Langman Construction, Inc. 200.0000 1,000.00 1,000.00 3815 McCarthy Improvement Company & Foley Construction Company 650.0000 3,250.00 3,250.00 6210 Valley Construction Co. 100.0000 500.00 500.00 3392 Walter D. Laud, Inc. 300.0000 1,500.00 1,500.00 XX008212 UD 4#4 #1G EPR-RHW 2 5,085.000 FOOT 0593 Brandt Construction Co. 8.0000 40,680.00 40,680.00 1799 Fischer Excavating, Inc. 9.5900 48,765.15 48,765.15 3375 Langman Construction, Inc. 6.5800 33,459.30 33,459.30 3815 McCarthy Improvement Company & Foley Construction Company 8.0000 40,680.00 40,680.00 6210 Valley Construction Co. 8.0500 40,934.25 40,934.25 3392 Walter D. Laud, Inc. 7.2000 36,612.00 36,612.00 XX008213 UD 8#4 #1G EPR-RHW 2 11,145.000 FOOT 0593 Brandt Construction Co. 12.1000 134,854.50 134,854.50 1799 Fischer Excavating, Inc. 14.9100 166,171.95 166,171.95 3375 Langman Construction, Inc. 9.9600 111,004.20 111,004.20 3815 McCarthy Improvement Company & Foley Construction Company 12.0000 133,740.00 133,740.00 6210 Valley Construction Co. 11.9200 132,848.40 132,848.40 3392 Walter D. Laud, Inc. 11.0000 122,595.00 122,595.00 XX008214 SAN SEW 16 70.000 FOOT 0593 Brandt Construction Co. 247.5000 17,325.00 17,325.00 1799 Fischer Excavating, Inc. 233.7400 16,361.80 16,361.80 3375 Langman Construction, Inc. 145.0000 10,150.00 10,150.00 3815 McCarthy Improvement Company & Foley Construction Company 100.0000 7,000.00 7,000.00 6210 Valley Construction Co. 174.0000 12,180.00 12,180.00 3392 Walter D. Laud, Inc. 200.0000 14,000.00 14,000.00 XX008215 D I WAT MNF 4X3 RED 1.000 EACH 0593 Brandt Construction Co. 620.0000 620.00 620.00 1799 Fischer Excavating, Inc. 189.4300 189.43 189.43 3375 Langman Construction, Inc. 150.0000 150.00 150.00 3815 McCarthy Improvement Company & Foley Construction Company 300.0000 300.00 300.00 6210 Valley Construction Co. 140.0000 140.00 140.00 3392 Walter D. Laud, Inc. 180.0000 180.00 180.00 XX008216 PCC SIDEWALK TEX C 4 5,366.000 SQ FT 0593 Brandt Construction Co. 14.1500 75,928.90 75,928.90 1799 Fischer Excavating, Inc. 12.9500 69,489.70 69,489.70 3375 Langman Construction, Inc. 9.2500 49,635.50 49,635.50 3815 McCarthy Improvement Company & Foley Construction Company 13.0000 69,758.00 69,758.00 6210 Valley Construction Co. 11.0000 59,026.00 59,026.00 3392 Walter D. Laud, Inc. 11.0000 59,026.00 59,026.00 XX008217 D I WAT MNF 10X4 TEE 4.000 EACH 0593 Brandt Construction Co. 950.0000 3,800.00 3,800.00 1799 Fischer Excavating, Inc. 590.7100 2,362.84 2,362.84 3375 Langman Construction, Inc. 400.0000 1,600.00 1,600.00 3815 McCarthy Improvement Company & Foley Construction Company 500.0000 2,000.00 2,000.00 6210 Valley Construction Co. 450.0000 1,800.00 1,800.00 3392 Walter D. Laud, Inc. 525.0000 2,100.00 2,100.00 XX008218 CATCH BASINS, TRIPLE 2.000 EACH 0593 Brandt Construction Co. 3,550.0000 7,100.00 7,100.00 1799 Fischer Excavating, Inc. 8,105.4600 16,210.92 16,210.92 3375 Langman Construction, Inc. 6,000.0000 12,000.00 12,000.00 3815 McCarthy Improvement Company & Foley Construction Company 5,000.0000 10,000.00 10,000.00 6210 Valley Construction Co. 4,400.0000 8,800.00 8,800.00 3392 Walter D. Laud, Inc. 4,000.0000 8,000.00 8,000.00 XX008219 INST FURNISHED BENCH 10.000 EACH 0593 Brandt Construction Co. 270.0000 2,700.00 2,700.00 1799 Fischer Excavating, Inc. 376.3500 3,763.50 3,763.50 3375 Langman Construction, Inc. 300.0000 3,000.00 3,000.00 3815 McCarthy Improvement Company & Foley Construction Company 900.0000 9,000.00 9,000.00 6210 Valley Construction Co. 250.0000 2,500.00 2,500.00 3392 Walter D. Laud, Inc. 350.0000 3,500.00 3,500.00 XX008220 ELECTRICAL CONTR CAB 1.000 EACH 0593 Brandt Construction Co. 20,450.0000 20,450.00 20,450.00 1799 Fischer Excavating, Inc. 19,625.0000 19,625.00 19,625.00 3375 Langman Construction, Inc. 16,809.5300 16,809.53 16,809.53 3815 McCarthy Improvement Company & Foley Construction Company 16,000.0000 16,000.00 16,000.00 6210 Valley Construction Co. 14,871.3200 14,871.32 14,871.32 3392 Walter D. Laud, Inc. 18,500.0000 18,500.00 18,500.00 X0301115 LANDSCAPE EDGING 546.000 FOOT 0593 Brandt Construction Co. 17.0000 9,282.00 9,282.00 1799 Fischer Excavating, Inc. 7.0000 3,822.00 3,822.00 3375 Langman Construction, Inc. 15.0000 8,190.00 8,190.00 3815 McCarthy Improvement Company & Foley Construction Company 9.0000 4,914.00 4,914.00 6210 Valley Construction Co. 7.0000 3,822.00 3,822.00 3392 Walter D. Laud, Inc. 8.5000 4,641.00 4,641.00 X0321566 MULCH SPL 265.000 SQ YD 0593 Brandt Construction Co. 11.1500 2,954.75 2,954.75 1799 Fischer Excavating, Inc. 4.3400 1,150.10 1,150.10 3375 Langman Construction, Inc. 10.0000 2,650.00 2,650.00 3815 McCarthy Improvement Company & Foley Construction Company 28.0000 7,420.00 7,420.00 6210 Valley Construction Co. 4.3400 1,150.10 1,150.10 3392 Walter D. Laud, Inc. 30.0000 7,950.00 7,950.00 X0323171 DI WM BEND 45 6" 2.000 EACH 0593 Brandt Construction Co. 715.0000 1,430.00 1,430.00 1799 Fischer Excavating, Inc. 242.8700 485.74 485.74 3375 Langman Construction, Inc. 150.0000 300.00 300.00 3815 McCarthy Improvement Company & Foley Construction Company 300.0000 600.00 600.00 6210 Valley Construction Co. 250.0000 500.00 500.00 3392 Walter D. Laud, Inc. 250.0000 500.00 500.00 X0323350 FUR & SET BRICK PAVER 2,930.000 SQ FT 0593 Brandt Construction Co. 29.5000 86,435.00 86,435.00 1799 Fischer Excavating, Inc. 18.0000 52,740.00 52,740.00 3375 Langman Construction, Inc. 10.0000 29,300.00 29,300.00 3815 McCarthy Improvement Company & Foley Construction Company 21.0000 61,530.00 61,530.00 6210 Valley Construction Co. 10.0000 29,300.00 29,300.00 3392 Walter D. Laud, Inc. 28.0000 82,040.00 82,040.00 X0324443 DI WAT MNF 10X8 CROSS 1.000 EACH 0593 Brandt Construction Co. 1,100.0000 1,100.00 1,100.00 1799 Fischer Excavating, Inc. 820.9900 820.99 820.99 3375 Langman Construction, Inc. 600.0000 600.00 600.00 3815 McCarthy Improvement Company & Foley Construction Company 800.0000 800.00 800.00 6210 Valley Construction Co. 600.0000 600.00 600.00 3392 Walter D. Laud, Inc. 1,000.0000 1,000.00 1,000.00 X0324444 DI WAT MNF 10X10 CRSS 1.000 EACH 0593 Brandt Construction Co. 1,150.0000 1,150.00 1,150.00 1799 Fischer Excavating, Inc. 909.8100 909.81 909.81 3375 Langman Construction, Inc. 600.0000 600.00 600.00 3815 McCarthy Improvement Company & Foley Construction Company 800.0000 800.00 800.00 6210 Valley Construction Co. 680.0000 680.00 680.00 3392 Walter D. Laud, Inc. 1,000.0000 1,000.00 1,000.00 X0324448 D I WT MNF 10 45 BEND 12.000 EACH 0593 Brandt Construction Co. 875.0000 10,500.00 10,500.00 1799 Fischer Excavating, Inc. 490.6200 5,887.44 5,887.44 3375 Langman Construction, Inc. 300.0000 3,600.00 3,600.00 3815 McCarthy Improvement Company & Foley Construction Company 500.0000 6,000.00 6,000.00 6210 Valley Construction Co. 350.0000 4,200.00 4,200.00 3392 Walter D. Laud, Inc. 475.0000 5,700.00 5,700.00 X0324525 PLANTING MIX F & P 36 247.000 SQ YD 0593 Brandt Construction Co. 56.0000 13,832.00 13,832.00 1799 Fischer Excavating, Inc. 42.0000 10,374.00 10,374.00 3375 Langman Construction, Inc. 50.0000 12,350.00 12,350.00 3815 McCarthy Improvement Company & Foley Construction Company 87.0000 21,489.00 21,489.00 6210 Valley Construction Co. 42.0000 10,374.00 10,374.00 3392 Walter D. Laud, Inc. 7.0000 1,729.00 1,729.00 X0324693 CURB STOP & BOX 2 3.000 EACH 0593 Brandt Construction Co. 755.0000 2,265.00 2,265.00 1799 Fischer Excavating, Inc. 446.0500 1,338.15 1,338.15 3375 Langman Construction, Inc. 400.0000 1,200.00 1,200.00 3815 McCarthy Improvement Company & Foley Construction Company 500.0000 1,500.00 1,500.00 6210 Valley Construction Co. 550.0000 1,650.00 1,650.00 3392 Walter D. Laud, Inc. 400.0000 1,200.00 1,200.00 X0325003 REM EX VALVE & VAULT 6.000 EACH 0593 Brandt Construction Co. 2,115.0000 12,690.00 12,690.00 1799 Fischer Excavating, Inc. 543.6700 3,262.02 3,262.02 3375 Langman Construction, Inc. 500.0000 3,000.00 3,000.00 3815 McCarthy Improvement Company & Foley Construction Company 1,500.0000 9,000.00 9,000.00 6210 Valley Construction Co. 950.0000 5,700.00 5,700.00 3392 Walter D. Laud, Inc. 500.0000 3,000.00 3,000.00 X0325151 REMOVE EX LIGHT POLE 24.000 EACH 0593 Brandt Construction Co. 450.0000 10,800.00 10,800.00 1799 Fischer Excavating, Inc. 450.0000 10,800.00 10,800.00 3375 Langman Construction, Inc. 365.0100 8,760.24 8,760.24 3815 McCarthy Improvement Company & Foley Construction Company 200.0000 4,800.00 4,800.00 6210 Valley Construction Co. 200.0100 4,800.24 4,800.24 3392 Walter D. Laud, Inc. 400.0000 9,600.00 9,600.00 X0325545 PLANTING MIX F & P 18 83.000 SQ YD 0593 Brandt Construction Co. 44.5500 3,697.65 3,697.65 1799 Fischer Excavating, Inc. 21.0000 1,743.00 1,743.00 3375 Langman Construction, Inc. 40.0000 3,320.00 3,320.00 3815 McCarthy Improvement Company & Foley Construction Company 60.0000 4,980.00 4,980.00 6210 Valley Construction Co. 21.0000 1,743.00 1,743.00 3392 Walter D. Laud, Inc. 7.0000 581.00 581.00 X5640150 FIRE HYDNT ASSY COMP 4.000 EACH 0593 Brandt Construction Co. 5,900.0000 23,600.00 23,600.00 1799 Fischer Excavating, Inc. 4,639.5300 18,558.12 18,558.12 3375 Langman Construction, Inc. 4,000.0000 16,000.00 16,000.00 3815 McCarthy Improvement Company & Foley Construction Company 3,000.0000 12,000.00 12,000.00 6210 Valley Construction Co. 4,400.0000 17,600.00 17,600.00 3392 Walter D. Laud, Inc. 4,000.0000 16,000.00 16,000.00 X6700410 ENGR FLD OFF A SPL 6.000 CAL MO 0593 Brandt Construction Co. 1,750.0000 10,500.00 10,500.00 1799 Fischer Excavating, Inc. 2,570.3500 15,422.10 15,422.10 3375 Langman Construction, Inc. 500.0000 3,000.00 3,000.00 3815 McCarthy Improvement Company & Foley Construction Company 1,500.0000 9,000.00 9,000.00 6210 Valley Construction Co. 900.0000 5,400.00 5,400.00 3392 Walter D. Laud, Inc. 1,500.0000 9,000.00 9,000.00 Z0056900 SAN SEW 8 674.000 FOOT 0593 Brandt Construction Co. 120.0000 80,880.00 80,880.00 1799 Fischer Excavating, Inc. 113.7100 76,640.54 76,640.54 3375 Langman Construction, Inc. 130.0000 87,620.00 87,620.00 3815 McCarthy Improvement Company & Foley Construction Company 85.0000 57,290.00 57,290.00 6210 Valley Construction Co. 78.0000 52,572.00 52,572.00 3392 Walter D. Laud, Inc. 117.5000 79,195.00 79,195.00 20800150 TRENCH BACKFILL 3,337.000 CU YD 0593 Brandt Construction Co. 25.5000 85,093.50 85,093.50 1799 Fischer Excavating, Inc. 37.8800 126,405.56 126,405.56 3375 Langman Construction, Inc. 24.0000 80,088.00 80,088.00 3815 McCarthy Improvement Company & Foley Construction Company 40.0000 133,480.00 133,480.00 6210 Valley Construction Co. 33.0000 110,121.00 110,121.00 3392 Walter D. Laud, Inc. 10.0000 33,370.00 33,370.00 21001000 GEOTECH FAB F/GR STAB 7,467.000 SQ YD 0593 Brandt Construction Co. 1.0000 7,467.00 7,467.00 1799 Fischer Excavating, Inc. 1.9100 14,261.97 14,261.97 3375 Langman Construction, Inc. 1.0000 7,467.00 7,467.00 3815 McCarthy Improvement Company & Foley Construction Company 2.0000 14,934.00 14,934.00 6210 Valley Construction Co. 1.2000 8,960.40 8,960.40 3392 Walter D. Laud, Inc. 1.2500 9,333.75 9,333.75 28000500 INLET & PIPE PROTECT 32.000 EACH 0593 Brandt Construction Co. 167.0000 5,344.00 5,344.00 1799 Fischer Excavating, Inc. 120.0000 3,840.00 3,840.00 3375 Langman Construction, Inc. 150.0000 4,800.00 4,800.00 3815 McCarthy Improvement Company & Foley Construction Company 200.0000 6,400.00 6,400.00 6210 Valley Construction Co. 120.0000 3,840.00 3,840.00 3392 Walter D. Laud, Inc. 150.0000 4,800.00 4,800.00 31102300 SUB GRAN MAT C 6 6,642.000 SQ YD 0593 Brandt Construction Co. 13.9500 92,655.90 92,655.90 1799 Fischer Excavating, Inc. 9.4500 62,766.90 62,766.90 3375 Langman Construction, Inc. 7.0000 46,494.00 46,494.00 3815 McCarthy Improvement Company & Foley Construction Company 20.0000 132,840.00 132,840.00 6210 Valley Construction Co. 14.4000 95,644.80 95,644.80 3392 Walter D. Laud, Inc. 9.2500 61,438.50 61,438.50 40200500 AGG SURF CSE A 6 7.000 SQ YD 0593 Brandt Construction Co. 49.5000 346.50 346.50 1799 Fischer Excavating, Inc. 76.8600 538.02 538.02 3375 Langman Construction, Inc. 15.0000 105.00 105.00 3815 McCarthy Improvement Company & Foley Construction Company 35.0000 245.00 245.00 6210 Valley Construction Co. 22.0000 154.00 154.00 3392 Walter D. Laud, Inc. 20.0000 140.00 140.00 42300300 PCC DRIVEWAY PAVT 7 235.000 SQ YD 0593 Brandt Construction Co. 65.0000 15,275.00 15,275.00 1799 Fischer Excavating, Inc. 75.8100 17,815.35 17,815.35 3375 Langman Construction, Inc. 55.0000 12,925.00 12,925.00 3815 McCarthy Improvement Company & Foley Construction Company 70.0000 16,450.00 16,450.00 6210 Valley Construction Co. 58.0000 13,630.00 13,630.00 3392 Walter D. Laud, Inc. 62.0000 14,570.00 14,570.00 42400100 PC CONC SIDEWALK 4 35,756.000 SQ FT 0593 Brandt Construction Co. 6.0500 216,323.80 216,323.80 1799 Fischer Excavating, Inc. 6.9100 247,073.96 247,073.96 3375 Langman Construction, Inc. 4.4000 157,326.40 157,326.40 3815 McCarthy Improvement Company & Foley Construction Company 5.0000 178,780.00 178,780.00 6210 Valley Construction Co. 7.9000 282,472.40 282,472.40 3392 Walter D. Laud, Inc. 5.2500 187,719.00 187,719.00 44000100 PAVEMENT REM 6,363.000 SQ YD 0593 Brandt Construction Co. 18.0000 114,534.00 114,534.00 1799 Fischer Excavating, Inc. 10.9000 69,356.70 69,356.70 3375 Langman Construction, Inc. 25.0000 159,075.00 159,075.00 3815 McCarthy Improvement Company & Foley Construction Company 10.0000 63,630.00 63,630.00 6210 Valley Construction Co. 18.0000 114,534.00 114,534.00 3392 Walter D. Laud, Inc. 11.0000 69,993.00 69,993.00 44000200 DRIVE PAVEMENT REM 220.000 SQ YD 0593 Brandt Construction Co. 18.0000 3,960.00 3,960.00 1799 Fischer Excavating, Inc. 10.2600 2,257.20 2,257.20 3375 Langman Construction, Inc. 25.0000 5,500.00 5,500.00 3815 McCarthy Improvement Company & Foley Construction Company 15.0000 3,300.00 3,300.00 6210 Valley Construction Co. 12.0000 2,640.00 2,640.00 3392 Walter D. Laud, Inc. 13.0000 2,860.00 2,860.00 44000600 SIDEWALK REM 51,400.000 SQ FT 0593 Brandt Construction Co. 1.2500 64,250.00 64,250.00 1799 Fischer Excavating, Inc. 1.3400 68,876.00 68,876.00 3375 Langman Construction, Inc. 1.0000 51,400.00 51,400.00 3815 McCarthy Improvement Company & Foley Construction Company 1.5000 77,100.00 77,100.00 6210 Valley Construction Co. 1.5000 77,100.00 77,100.00 3392 Walter D. Laud, Inc. 1.0000 51,400.00 51,400.00 44200934 CL B PATCH T2 8 180.000 SQ YD 0593 Brandt Construction Co. 90.0000 16,200.00 16,200.00 1799 Fischer Excavating, Inc. 188.8400 33,991.20 33,991.20 3375 Langman Construction, Inc. 125.0000 22,500.00 22,500.00 3815 McCarthy Improvement Company & Foley Construction Company 170.0000 30,600.00 30,600.00 6210 Valley Construction Co. 35.0000 6,300.00 6,300.00 3392 Walter D. Laud, Inc. 130.0000 23,400.00 23,400.00 55019500 SS 1 RCP CL 4 12 728.000 FOOT 0593 Brandt Construction Co. 62.0000 45,136.00 45,136.00 1799 Fischer Excavating, Inc. 54.0000 39,312.00 39,312.00 3375 Langman Construction, Inc. 75.0000 54,600.00 54,600.00 3815 McCarthy Improvement Company & Foley Construction Company 75.0000 54,600.00 54,600.00 6210 Valley Construction Co. 59.0000 42,952.00 42,952.00 3392 Walter D. Laud, Inc. 45.0000 32,760.00 32,760.00 55019600 SS 1 RCP CL 4 15 39.000 FOOT 0593 Brandt Construction Co. 97.0500 3,784.95 3,784.95 1799 Fischer Excavating, Inc. 81.5700 3,181.23 3,181.23 3375 Langman Construction, Inc. 80.0000 3,120.00 3,120.00 3815 McCarthy Improvement Company & Foley Construction Company 65.0000 2,535.00 2,535.00 6210 Valley Construction Co. 59.0000 2,301.00 2,301.00 3392 Walter D. Laud, Inc. 64.0000 2,496.00 2,496.00 55019700 SS 1 RCP CL 4 18 104.000 FOOT 0593 Brandt Construction Co. 81.5000 8,476.00 8,476.00 1799 Fischer Excavating, Inc. 88.2600 9,179.04 9,179.04 3375 Langman Construction, Inc. 85.0000 8,840.00 8,840.00 3815 McCarthy Improvement Company & Foley Construction Company 80.0000 8,320.00 8,320.00 6210 Valley Construction Co. 65.0000 6,760.00 6,760.00 3392 Walter D. Laud, Inc. 66.0000 6,864.00 6,864.00 55022000 SS 2 RCP CL 3 24 419.000 FOOT 0593 Brandt Construction Co. 83.2500 34,881.75 34,881.75 1799 Fischer Excavating, Inc. 62.7900 26,309.01 26,309.01 3375 Langman Construction, Inc. 90.0000 37,710.00 37,710.00 3815 McCarthy Improvement Company & Foley Construction Company 100.0000 41,900.00 41,900.00 6210 Valley Construction Co. 65.0000 27,235.00 27,235.00 3392 Walter D. Laud, Inc. 70.0000 29,330.00 29,330.00 55022400 SS 2 RCP CL 3 36 89.000 FOOT 0593 Brandt Construction Co. 143.0000 12,727.00 12,727.00 1799 Fischer Excavating, Inc. 178.9100 15,922.99 15,922.99 3375 Langman Construction, Inc. 105.0000 9,345.00 9,345.00 3815 McCarthy Improvement Company & Foley Construction Company 150.0000 13,350.00 13,350.00 6210 Valley Construction Co. 118.0000 10,502.00 10,502.00 3392 Walter D. Laud, Inc. 105.0000 9,345.00 9,345.00 55100500 STORM SEWER REM 12 310.000 FOOT 0593 Brandt Construction Co. 22.0000 6,820.00 6,820.00 1799 Fischer Excavating, Inc. 20.8100 6,451.10 6,451.10 3375 Langman Construction, Inc. 5.0000 1,550.00 1,550.00 3815 McCarthy Improvement Company & Foley Construction Company 33.0000 10,230.00 10,230.00 6210 Valley Construction Co. 18.0000 5,580.00 5,580.00 3392 Walter D. Laud, Inc. 10.0000 3,100.00 3,100.00 55100700 STORM SEWER REM 15 213.000 FOOT 0593 Brandt Construction Co. 26.2500 5,591.25 5,591.25 1799 Fischer Excavating, Inc. 20.8000 4,430.40 4,430.40 3375 Langman Construction, Inc. 5.0000 1,065.00 1,065.00 3815 McCarthy Improvement Company & Foley Construction Company 33.0000 7,029.00 7,029.00 6210 Valley Construction Co. 18.0000 3,834.00 3,834.00 3392 Walter D. Laud, Inc. 15.0000 3,195.00 3,195.00 56102900 D I WATER MAIN 4 118.000 FOOT 0593 Brandt Construction Co. 91.1000 10,749.80 10,749.80 1799 Fischer Excavating, Inc. 56.7100 6,691.78 6,691.78 3375 Langman Construction, Inc. 100.0000 11,800.00 11,800.00 3815 McCarthy Improvement Company & Foley Construction Company 80.0000 9,440.00 9,440.00 6210 Valley Construction Co. 140.0000 16,520.00 16,520.00 3392 Walter D. Laud, Inc. 70.0000 8,260.00 8,260.00 56103000 D I WATER MAIN 6 139.000 FOOT 0593 Brandt Construction Co. 105.5000 14,664.50 14,664.50 1799 Fischer Excavating, Inc. 57.7200 8,023.08 8,023.08 3375 Langman Construction, Inc. 105.0000 14,595.00 14,595.00 3815 McCarthy Improvement Company & Foley Construction Company 110.0000 15,290.00 15,290.00 6210 Valley Construction Co. 180.0000 25,020.00 25,020.00 3392 Walter D. Laud, Inc. 70.0000 9,730.00 9,730.00 56103100 D I WATER MAIN 8 127.000 FOOT 0593 Brandt Construction Co. 106.5000 13,525.50 13,525.50 1799 Fischer Excavating, Inc. 92.9400 11,803.38 11,803.38 3375 Langman Construction, Inc. 110.0000 13,970.00 13,970.00 3815 McCarthy Improvement Company & Foley Construction Company 66.0000 8,382.00 8,382.00 6210 Valley Construction Co. 76.0000 9,652.00 9,652.00 3392 Walter D. Laud, Inc. 70.0000 8,890.00 8,890.00 56103200 D I WATER MAIN 10 1,365.000 FOOT 0593 Brandt Construction Co. 93.0000 126,945.00 126,945.00 1799 Fischer Excavating, Inc. 68.9200 94,075.80 94,075.80 3375 Langman Construction, Inc. 115.0000 156,975.00 156,975.00 3815 McCarthy Improvement Company & Foley Construction Company 95.0000 129,675.00 129,675.00 6210 Valley Construction Co. 65.0000 88,725.00 88,725.00 3392 Walter D. Laud, Inc. 74.0000 101,010.00 101,010.00 56105740 BUTTERFLY VALVES 10 6.000 EACH 0593 Brandt Construction Co. 4,350.0000 26,100.00 26,100.00 1799 Fischer Excavating, Inc. 3,426.5200 20,559.12 20,559.12 3375 Langman Construction, Inc. 5,000.0000 30,000.00 30,000.00 3815 McCarthy Improvement Company & Foley Construction Company 5,000.0000 30,000.00 30,000.00 6210 Valley Construction Co. 4,300.0000 25,800.00 25,800.00 3392 Walter D. Laud, Inc. 5,600.0000 33,600.00 33,600.00 56200300 WATER SERV LINE 1 868.000 FOOT 0593 Brandt Construction Co. 40.0000 34,720.00 34,720.00 1799 Fischer Excavating, Inc. 31.5900 27,420.12 27,420.12 3375 Langman Construction, Inc. 30.0000 26,040.00 26,040.00 3815 McCarthy Improvement Company & Foley Construction Company 45.0000 39,060.00 39,060.00 6210 Valley Construction Co. 27.0000 23,436.00 23,436.00 3392 Walter D. Laud, Inc. 15.0000 13,020.00 13,020.00 56200500 WATER SERV LINE 1 1/2 150.000 FOOT 0593 Brandt Construction Co. 45.0000 6,750.00 6,750.00 1799 Fischer Excavating, Inc. 39.6400 5,946.00 5,946.00 3375 Langman Construction, Inc. 45.0000 6,750.00 6,750.00 3815 McCarthy Improvement Company & Foley Construction Company 45.0000 6,750.00 6,750.00 6210 Valley Construction Co. 32.0000 4,800.00 4,800.00 3392 Walter D. Laud, Inc. 19.0000 2,850.00 2,850.00 56200700 WATER SERV LINE 2 162.000 FOOT 0593 Brandt Construction Co. 46.0000 7,452.00 7,452.00 1799 Fischer Excavating, Inc. 47.9200 7,763.04 7,763.04 3375 Langman Construction, Inc. 40.0000 6,480.00 6,480.00 3815 McCarthy Improvement Company & Foley Construction Company 45.0000 7,290.00 7,290.00 6210 Valley Construction Co. 36.0000 5,832.00 5,832.00 3392 Walter D. Laud, Inc. 30.0000 4,860.00 4,860.00 56400500 FIRE HYDNTS TO BE REM 5.000 EACH 0593 Brandt Construction Co. 650.0000 3,250.00 3,250.00 1799 Fischer Excavating, Inc. 553.0900 2,765.45 2,765.45 3375 Langman Construction, Inc. 800.0000 4,000.00 4,000.00 3815 McCarthy Improvement Company & Foley Construction Company 600.0000 3,000.00 3,000.00 6210 Valley Construction Co. 520.0000 2,600.00 2,600.00 3392 Walter D. Laud, Inc. 600.0000 3,000.00 3,000.00 60107600 PIPE UNDERDRAINS 4 2,850.000 FOOT 0593 Brandt Construction Co. 16.0000 45,600.00 45,600.00 1799 Fischer Excavating, Inc. 10.0100 28,528.50 28,528.50 3375 Langman Construction, Inc. 15.0000 42,750.00 42,750.00 3815 McCarthy Improvement Company & Foley Construction Company 10.0000 28,500.00 28,500.00 6210 Valley Construction Co. 15.0000 42,750.00 42,750.00 3392 Walter D. Laud, Inc. 11.0000 31,350.00 31,350.00 60218300 MAN TA 4 DIA T1F OL 3.000 EACH 0593 Brandt Construction Co. 2,000.0000 6,000.00 6,000.00 1799 Fischer Excavating, Inc. 2,297.6800 6,893.04 6,893.04 3375 Langman Construction, Inc. 3,500.0000 10,500.00 10,500.00 3815 McCarthy Improvement Company & Foley Construction Company 2,600.0000 7,800.00 7,800.00 6210 Valley Construction Co. 2,800.0000 8,400.00 8,400.00 3392 Walter D. Laud, Inc. 2,100.0000 6,300.00 6,300.00 60218400 MAN TA 4 DIA T1F CL 4.000 EACH 0593 Brandt Construction Co. 3,200.0000 12,800.00 12,800.00 1799 Fischer Excavating, Inc. 3,747.2800 14,989.12 14,989.12 3375 Langman Construction, Inc. 4,000.0000 16,000.00 16,000.00 3815 McCarthy Improvement Company & Foley Construction Company 5,000.0000 20,000.00 20,000.00 6210 Valley Construction Co. 5,700.0000 22,800.00 22,800.00 3392 Walter D. Laud, Inc. 2,800.0000 11,200.00 11,200.00 60221100 MAN TA 5 DIA T1F CL 2.000 EACH 0593 Brandt Construction Co. 2,575.0000 5,150.00 5,150.00 1799 Fischer Excavating, Inc. 4,093.1700 8,186.34 8,186.34 3375 Langman Construction, Inc. 4,800.0000 9,600.00 9,600.00 3815 McCarthy Improvement Company & Foley Construction Company 4,000.0000 8,000.00 8,000.00 6210 Valley Construction Co. 3,500.0000 7,000.00 7,000.00 3392 Walter D. Laud, Inc. 3,000.0000 6,000.00 6,000.00 60247900 JUNCTION CHAMBER SPL 1.000 EACH 0593 Brandt Construction Co. 20,000.0000 20,000.00 20,000.00 1799 Fischer Excavating, Inc. 15,349.8100 15,349.81 15,349.81 3375 Langman Construction, Inc. 11,000.0000 11,000.00 11,000.00 3815 McCarthy Improvement Company & Foley Construction Company 15,000.0000 15,000.00 15,000.00 6210 Valley Construction Co. 12,000.0000 12,000.00 12,000.00 3392 Walter D. Laud, Inc. 11,000.0000 11,000.00 11,000.00 60255500 MAN ADJUST 2.000 EACH 0593 Brandt Construction Co. 450.0000 900.00 900.00 1799 Fischer Excavating, Inc. 594.9700 1,189.94 1,189.94 3375 Langman Construction, Inc. 400.0000 800.00 800.00 3815 McCarthy Improvement Company & Foley Construction Company 400.0000 800.00 800.00 6210 Valley Construction Co. 800.0000 1,600.00 1,600.00 3392 Walter D. Laud, Inc. 600.0000 1,200.00 1,200.00 60266910 VALVE BOX REMOVED 6.000 EACH 0593 Brandt Construction Co. 400.0000 2,400.00 2,400.00 1799 Fischer Excavating, Inc. 102.4300 614.58 614.58 3375 Langman Construction, Inc. 100.0000 600.00 600.00 3815 McCarthy Improvement Company & Foley Construction Company 90.0000 540.00 540.00 6210 Valley Construction Co. 120.0000 720.00 720.00 3392 Walter D. Laud, Inc. 100.0000 600.00 600.00 60500040 REMOV MANHOLES 4.000 EACH 0593 Brandt Construction Co. 800.0000 3,200.00 3,200.00 1799 Fischer Excavating, Inc. 760.2300 3,040.92 3,040.92 3375 Langman Construction, Inc. 500.0000 2,000.00 2,000.00 3815 McCarthy Improvement Company & Foley Construction Company 900.0000 3,600.00 3,600.00 6210 Valley Construction Co. 500.0000 2,000.00 2,000.00 3392 Walter D. Laud, Inc. 700.0000 2,800.00 2,800.00 60500060 REMOV INLETS 10.000 EACH 0593 Brandt Construction Co. 500.0000 5,000.00 5,000.00 1799 Fischer Excavating, Inc. 439.2400 4,392.40 4,392.40 3375 Langman Construction, Inc. 300.0000 3,000.00 3,000.00 3815 McCarthy Improvement Company & Foley Construction Company 600.0000 6,000.00 6,000.00 6210 Valley Construction Co. 350.0000 3,500.00 3,500.00 3392 Walter D. Laud, Inc. 300.0000 3,000.00 3,000.00 67100100 MOBILIZATION 1.000 L SUM 0593 Brandt Construction Co. 151,000.0000 151,000.00 151,000.00 1799 Fischer Excavating, Inc. 165,860.8000 165,860.80 165,860.80 3375 Langman Construction, Inc. 155,000.0000 155,000.00 155,000.00 3815 McCarthy Improvement Company & Foley Construction Company 170,000.0000 170,000.00 170,000.00 6210 Valley Construction Co. 148,000.0000 148,000.00 148,000.00 3392 Walter D. Laud, Inc. 30,000.0000 30,000.00 30,000.00 70101700 TRAF CONT & PROT 1.000 L SUM 0593 Brandt Construction Co. 20,000.0000 20,000.00 20,000.00 1799 Fischer Excavating, Inc. 13,875.0000 13,875.00 13,875.00 3375 Langman Construction, Inc. 13,000.0000 13,000.00 13,000.00 3815 McCarthy Improvement Company & Foley Construction Company 75,000.0000 75,000.00 75,000.00 6210 Valley Construction Co. 27,000.0000 27,000.00 27,000.00 3392 Walter D. Laud, Inc. 34,000.0000 34,000.00 34,000.00 78001110 PAINT PVT MK LINE 4 2,145.000 FOOT 0593 Brandt Construction Co. 1.4000 3,003.00 3,003.00 1799 Fischer Excavating, Inc. 1.2500 2,681.25 2,681.25 3375 Langman Construction, Inc. 1.2500 2,681.25 2,681.25 3815 McCarthy Improvement Company & Foley Construction Company 1.2500 2,681.25 2,681.25 6210 Valley Construction Co. 1.2500 2,681.25 2,681.25 3392 Walter D. Laud, Inc. 1.3000 2,788.50 2,788.50 78001180 PAINT PVT MK LINE 24 171.000 FOOT 0593 Brandt Construction Co. 6.1500 1,051.65 1,051.65 1799 Fischer Excavating, Inc. 5.5000 940.50 940.50 3375 Langman Construction, Inc. 5.5000 940.50 940.50 3815 McCarthy Improvement Company & Foley Construction Company 6.0000 1,026.00 1,026.00 6210 Valley Construction Co. 5.5000 940.50 940.50 3392 Walter D. Laud, Inc. 5.7500 983.25 983.25 81000800 CON T 3 GALVS 2,375.000 FOOT 0593 Brandt Construction Co. 15.5000 36,812.50 36,812.50 1799 Fischer Excavating, Inc. 15.6900 37,263.75 37,263.75 3375 Langman Construction, Inc. 12.7500 30,281.25 30,281.25 3815 McCarthy Improvement Company & Foley Construction Company 15.0000 35,625.00 35,625.00 6210 Valley Construction Co. 14.7000 34,912.50 34,912.50 3392 Walter D. Laud, Inc. 14.0000 33,250.00 33,250.00 81021330 CON P 2 PVC 2,405.000 FOOT 0593 Brandt Construction Co. 13.5000 32,467.50 32,467.50 1799 Fischer Excavating, Inc. 5.0000 12,025.00 12,025.00 3375 Langman Construction, Inc. 11.1200 26,743.60 26,743.60 3815 McCarthy Improvement Company & Foley Construction Company 6.5000 15,632.50 15,632.50 6210 Valley Construction Co. 6.2100 14,935.05 14,935.05 3392 Walter D. Laud, Inc. 12.2500 29,461.25 29,461.25 81306500 REM EX JUNCTION BOX 3.000 EACH 0593 Brandt Construction Co. 85.0000 255.00 255.00 1799 Fischer Excavating, Inc. 300.0000 900.00 900.00 3375 Langman Construction, Inc. 68.7800 206.34 206.34 3815 McCarthy Improvement Company & Foley Construction Company 55.0000 165.00 165.00 6210 Valley Construction Co. 49.1800 147.54 147.54 3392 Walter D. Laud, Inc. 75.0000 225.00 225.00 81400100 HANDHOLE 44.000 EACH 0593 Brandt Construction Co. 535.0000 23,540.00 23,540.00 1799 Fischer Excavating, Inc. 570.0000 25,080.00 25,080.00 3375 Langman Construction, Inc. 440.2100 19,369.24 19,369.24 3815 McCarthy Improvement Company & Foley Construction Company 300.0000 13,200.00 13,200.00 6210 Valley Construction Co. 302.3500 13,303.40 13,303.40 3392 Walter D. Laud, Inc. 480.0000 21,120.00 21,120.00 81400700 HANDHOLE PCC 10.000 EACH 0593 Brandt Construction Co. 2,180.0000 21,800.00 21,800.00 1799 Fischer Excavating, Inc. 1,120.0000 11,200.00 11,200.00 3375 Langman Construction, Inc. 1,793.8500 17,938.50 17,938.50 3815 McCarthy Improvement Company & Foley Construction Company 300.0000 3,000.00 3,000.00 6210 Valley Construction Co. 302.3500 3,023.50 3,023.50 3392 Walter D. Laud, Inc. 2,000.0000 20,000.00 20,000.00 89502380 REMOV EX HANDHOLE 7.000 EACH 0593 Brandt Construction Co. 310.0000 2,170.00 2,170.00 1799 Fischer Excavating, Inc. 350.0000 2,450.00 2,450.00 3375 Langman Construction, Inc. 252.2000 1,765.40 1,765.40 3815 McCarthy Improvement Company & Foley Construction Company 300.0000 2,100.00 2,100.00 6210 Valley Construction Co. 24.5900 172.13 172.13 3392 Walter D. Laud, Inc. 275.0000 1,925.00 1,925.00