Illinois Department of Transportation, Erica Borggren, Acting Secretary
Loading
Patrick J. Quinn, Governor
Traveling PublicMapsProjectsRoad ClosuresNewsDoing BusinessLetting & BiddingCareers@IDOTGeneral Info


 

YEAR 4


PHASE 2 ENGINEERING

  • Prepare a job site construction plan and develop construction material requirements used in preparing final contract to be bid on by contractors
  • Federal Aviation Administration - Coordinate with FAA if building within a mile of an airport to check if structures interfere with airplane glide paths
  • Begin preliminary contract plans
  • For bridge construction, make structure borings
  • Complete all bridge and pavement reconstruction reports
      LAND ACQUISITION
  • Conduct land surveys, appraise property, negotiate with land owners, notify Attorney General to appoint private attorney if court settlement is needed, relocation
  • Complete preliminary contract plans
  • Complete land acquisition
     UTILITY RELOCATIONS
  • Prepare agreements with local agencies
  • Prepare traffic control plans
  • Complete final review of project’s plans
  • Complete utility relocations
  • Complete agreements with local agencies or private entities
      LOCAL AGENCY AGREEMENTS
  • Coordinate with local agencies on scope of work
  • Determine limits of local participation
  • Prepare agreements with local agencies
  • Make final construction plans
  • Complete agreements with local agencies
  • Complete PHASE 2 ENGINEERING
  • If federally funded, Federal Highway Administration authorizes federal funds

 