EISENHOWER (I-290) RESURFACING
Illinois Department of Transportation
|
| |
|
| Cost: |
Approximately $90 million |
| Start/End Date: |
Spring 2010-Fall 2010 |
| Miles: |
Approximately 27 mile stretch |
| Project Limits: |
Eisenhower (I-290) from Thorndale to the Circle Interchange |
| Scope of Work: |
Mill and resurfacing, bridge rehabilitation, ramp resurfacing |
| Project link: |
http://www.dot.il.gov/I290/index.html |
| Contact Information: |
http://www.dot.il.gov/contact.html |
|
 |
CONGRESS PARKWAY STREETSCAPE IMPROVEMENT
Chicago Department of Transportation
|
| |
|
| Cost: |
$10 to $20 million |
| Start/End Date: |
Spring 2010-Spring 2012 |
| Miles: |
.5 miles |
| Project Limits: |
Wells Street to Michigan Avenue |
| Scope of Work: |
Refurbishment of Congress Parkway; includes new
sidewalks, sidewalk planters, lighting, community identifiers, and
other streetscape elements |
| Project link: |
www.wackerdrive.org |
| Contact Information: |
cdotnews@cityofchicago.org |
|
 |
WACKER DRIVE RECONSTRUCTION
Chicago Department of Transportation
|
| |
|
| Cost: |
$366 million |
| Start/End Date: |
Spring 2010-Fall 2012 |
| Miles: |
.6 miles |
| Project Limits: |
Wacker Drive from Randolph Street to Congress
Parkway |
| Scope of Work: |
Complete reconstruction of north-south segment of
Wacker Drive providing smooth driving surface, increased clearance,
and new service drive on lower Wacker |
| Project link: |
www.wackerdrive.org |
| Contact Information: |
cdotnews@cityofchicago.org |
|
|

Chicago Area Construction Projects*
* Click on link to download and
print .pdf file |
 Chicago Area Construction Projects
Fall
2009*
Spring 2010*
* Click on link to receive video |