PROJECT OVERVIEW

The Illinois Department of Transportation will mill and resurface approximately 27 miles along Interstate 290 from Thorndale Avenue to Interstate 90/94, and Interstate 355 from Army Trail Road to Interstate 290 located within Cook & DuPage Counties. The Interstate 290 project repairs 37 bridges along the project area including entrance and exit ramps. Interstate 290 was last resurfaced 11 years ago. The construction is scheduled to begin April 1, 2010 with completion in the fall of 2010. Milling the pavement consists of grinding, treating, and shaping the pavement. The completed construction project will provide a smoother and safer ride along with strength and stability of the pavement for the motoring public. The estimated cost for this one-year project is $95 million.

Interstate 290 generally consists of three to four-lanes in each direction with variable width shoulders. Construction will take place in both directions simultaneously inbound and outbound. Starting April 1st, traffic will be driven on the inside lanes. Permanent lane closures will be required during bridge repairs, which will reduce one lane along Interstate 290 in each direction. The project consists of six main contracts, which will be described in more detail below.

IDOT is dedicated to providing the residents of Illinois with interstates, state routes, and mass transit options that are safe, and ensure the highest quality of life. IDOT wants to improve public awareness and involvement through improved external communications from the public. Please check back periodically for web site updates. The Illinois Department of Transportation looks forward to your input and support throughout this project.

Project Details

Contract 60G51-- I-290 from Thorndale Avenue to east of Church Road, and I-355 from Army Trail Road to I-290.

  • Project start date is April 1, 2010.
  • Bridge completion date is August 27, 2010.
  • Resurfacing completion date is October 31, 2010.
  • Total length is approximately 8.6 miles.
  • Pavement patching.
  • Hot-Mix Asphalt Surface Removal.
  • Resurface with Polymerized Hot-Mix Asphalt (HMA), Stone Matrix Asphalt (SMA) Binder Course, 2”; and HMA Stone Matrix Asphalt Surface Course, 2”.
  • Signing
  • Landscaping
  • Resurfacing of interstate shoulder.
  • Resurfacing of ramps at all interchanges.
  • Milling & resurfacing will be utilizing temporary night lane closures.
  • Bridge repair of 16 structures.
    • Structure work includes bridge deck sealing, barrier wall and joint repair, deck overlay, approach pavement replacement, and expansion joint reconstruction.
    • Structure work will be utilizing permanent lane closures.
  • Final pavement markings and raised reflective pavement markers.

Contract 60I57-- I-290 from east of Church Road to I-88

  • Project start date is April 1, 2010.
  • Bridge completion date is August 27, 2010.
  • Patching completion date is October 31, 2010.
  • Total length is approximately 4.3 miles.
  • Bridge repair of 12 structures.
    • Structure work includes bridge deck sealing, barrier wall and joint repair, deck overlay, approach pavement replacement, and expansion joint reconstruction.
    • Structure work will be utilizing permanent lane closures.
  • No resurfacing will be done within this contract.
  • Resurfacing of ramps at all interchanges
  • Signing
  • Landscaping
  • Final pavement markings and raised reflective pavement markers.

Contract 60K12-- I-290 from I-88 to 9th Avenue

  • Project start date is April 1, 2010.
  • Bridge completion date is June 25, 2010.
  • Resurfacing completion date is October 31, 2010.
  • Total length is approximately 3.39 miles
  • Hot-Mix Asphalt Surface Removal.
  • Resurface with Polymerized Hot-Mix Asphalt (HMA), Stone Matrix Asphalt (SMA) Binder Course, 2”; and HMA Stone Matrix Asphalt Surface Course, 2”.
  • Resurfacing of interstate shoulder.
  • Resurfacing of ramps at all interchanges.
  • Signing
  • Landscaping
  • Milling & resurfacing will be utilizing temporary night lane closures.
  • Bridge repair of 6 structures.
    • Structure work includes bridge deck and approach pavement patching and sealing, barrier wall and joint repair, expansion joint reconstruction and substructure repair.
    • Structure work will be utilizing permanent lane closures.
  • Final pavement markings and raised reflective pavement markers.

Contract 60K10-- I-290 from 9th Avenue to Austin Avenue

  • Project start date is April 1, 2010.
  • Bridge completion date is June 25, 2010.
  • Resurfacing completion date is October 31, 2010.
  • Total length is approximately 3.86 miles.
  • Pavement patching.
  • Hot-Mix Asphalt Surface Removal.
  • Signing
  • Landscaping
  • Resurface with Polymerized Hot-Mix Asphalt (HMA), Stone Matrix Asphalt (SMA) Binder Course, 2”; and HMA Stone Matrix Asphalt Surface Course, 2”.
  • Resurfacing of interstate shoulder.
  • Resurfacing of ramps at all interchanges.
  • Milling & resurfacing will be utilizing temporary night lane closures.
  • Bridge repair of 1 structure (Des Plaines River). 
    • Structure work includes bridge deck and approach pavement patching and sealing, barrier wall and joint repair.
    • Structure work will be utilizing permanent lane closures.
  • Main drain sewer cleaning and repairs.
  • Final pavement markings and raised reflective pavement markers.

Contract 60K13-- I-290 from Austin Avenue to Sacramento Boulevard

  • Project start date is April 1, 2010.
  • Bridge completion date is June 25, 2010.
  • Resurfacing completion date is October 31, 2010.
  • Total length is approximately 3.79 miles.
  • Pavement patching.
  • Hot-Mix Asphalt Surface Removal.
  • Signing
  • Landscaping
  • Resurface with Polymerized Hot-Mix Asphalt (HMA), Stone Matrix Asphalt (SMA) Binder Course, 2”; and HMA Stone Matrix Asphalt Surface Course, 2”.
  • Resurfacing of interstate shoulder.
  • Resurfacing of ramps at all interchanges.
  • Milling & resurfacing will be utilizing temporary night lane closures.
  • Bridge repair of 2 structures (Central Avenue).
    • Structure work includes bridge deck sealing, barrier wall and joint repair, deck overlay, approach pavement replacement, and expansion joint reconstruction.
    • Structure work will be utilizing permanent lane closures.
  • Structure work will utilize permanent lane closures.
  • Diamond grinding of existing Portland Cement Concrete (PCC) pavement.
  • Final pavement markings and raised reflective pavement markers.

Contract 60K11-- I-290 from Sacramento Boulevard to I-90/94 (Circle Interchange)

  • Project start date is April 1, 2010.
  • Bridge completion date is June 25, 2010.
  • Resurfacing completion date is October 31, 2010.
  • Total length is approximately 2.71 miles.
  • Pavement patching.
  • Hot-Mix Asphalt Surface Removal.
  • Signing
  • Landscaping
  • Resurface with Polymerized Hot-Mix Asphalt (HMA), Stone Matrix Asphalt (SMA) Binder Course, 2”; and HMA Stone Matrix Asphalt Surface Course, 2”.
  • Resurfacing of interstate shoulder.
  • Resurfacing of ramps at all interchanges.
  • Milling & resurfacing will be utilizing temporary night lane closures.
  • Main drain sewer cleaning and repairs.
  • Final pavement markings and raised reflective pavement markers.
  • There are no bridge repairs in this contract.


 